HomeMy WebLinkAboutC & E Trenching Change Order 1 & 2 GR1-ST-33-15-75 2014-2015 ADA RetrofitCITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 1
Project No: GRI -ST -33-15-75 Project Title:
2014-2015 ADA RETROFIT
Contractor: C & E Trenching
Description of Change: Replacement of existing frame and grate of Stormwater Catch Basin
Detail as Appropriate:
the SE corner of 15th A
of existinq frame and grate Storm Catch Basin located at
and
Contract Bid Amount:
SALES TAX @ 8.6%:
Total:
$ 296,382.03
N/A
$ 296,382.03
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $
Subtotal
$ 856.74
Sales tax @ 8.6% $
Sales tax @
8.6% N/A
Total $ -
Total
$ 856.74
Total Change Orders To Date
856.74
New Contract Amount $ 297,238.77
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................................... 87 Working Days
Modification to Contract time by this Change Order ....................................... N/A
Revised Total Contract Time.................................................................... 87 Working Days
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND AC EPTED:
CgWRACTOIR Date
APPROVED:
NSTRUCTION MANAGER ' Date
APPROVED:
YA�/ 10(2111 -SPR ANAGER Date
H
W
W
2
IL
Y
Q
m
r
O
z
w
W
0
Q'
O
W
U
z
Q
2
U
H
U
Q
f -
z
O
U
H
CL
W
CL
CL
IL
O
U
a
U-
0
H
W
Ir
0
0
Q
LO
0
N
V
C)
0
N
CL a
TF
I
u
a
W
O
w
a
a
Q
C
W
F
a
W
U
U
Q
0
a
O
0
W
W
Q
a
r
_=LO
A
l0
o
0
w
�Q
T
N
m C
O m
F
�7
V
r
CUp
O
l0
0
U O
�
Q
T
N
O c
U
3
0
c
'
a 0
00 O
Q
v3
d
'
a`
W
C
J
7
T
a C
m �
C!
r
C
C
N
C
N
O
N
U
C
m
O
U
(D
-O
N
N
m
�
C
m
�
L
O
C
U
0
m
a)
N
D
E
a
c
U-
E
N
m
�
m
a
L
U
a
m
m
�
U
`m
a
d z
0
U
L
r
a
W
O
w
a
a
Q
C
W
F
a
W
U
U
Q
0
a
O
0
W
W
Q
CAe
TRENCHING, LLC
Date: 10/05/2015
Attention: Maria Cerra
Company: City of Pasco
Phone/Fax/Email:
Project Name: 2014-2015 ADA Retrofit
C&E Proiect Number: J15949CH
Scope of Work Bid: Per Bid items
C & E Proiect Manager: Jake Wray
e0 CVie N 0 0 *.&
• P.O. Box 3788 • Pasco, WA 99302 • 509.545.6940 owice • 509.545.8671 FAX
Change Order Request#: 1
Change Order Reauest
We hereby submit the following change order request for changes in the work required under this Contract with the listed
changes in the Contract Sum listed below:
Change Order Reouest Scope of Work:
Description
I Quantity
I Unit
Unit Price
Ext Price
Remove and reinstall new frame and grate
1.000
1 LS
$428.37
$428.37
Grand Total:
$428.37
Summary of Changes in Contract
The Original Contract Sum Was $296,382.03
The Net Change by previous authorized change orders $0
Contract prior to this Change Order $296,382.03
This Change Order Request Contract Sum (Add) (Deduct) $428.37
New Contract Sum $296,810.40
Conditions/ Exclusions:
Pricing excludes sales tax
Pricine excludes sleevine. fencing, signage, lighdng, and site furnishhur.
We look submit the following Change Order Request for your review if accepted please sign below and return authorization of
work. Thank you for the opportunity to earn your work!!
Acceptance of Change Request: The above prices, specifications and conditions are satisfactory and are hereby accepted. You
are authorized to do the work as specified. Payment will be made as outlined.
Jake Wray Accepted by Date
"For ALL Your Excavating Needs"
www.candetrenching.com
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 2
Project No: GR1-ST-33-15-75 Project Title: 2014-2015 ADA RETROFIT
Contractor: C & E
Description of Change: Scope of projectis adjusted to include the replacement two(2)
non -conforming ramps
Detail as Appropriate: Existing ramps in Argent and 65th PI. exceed admisible slope and
need to be replaced
o?q!! Z• 03
Contract Bid Amount: $ 3v—,-23-
8 323 7%
SALES TAX @ 8.6%: N/A
Total: $ -297,236:77—
Allo, 38z• 63
PREVIOUS CHANGE ORDERS
CURRENT CHANGE ORDER
Subtotal $ 856.74
Subtotal $ AN/A
Sales tax @ 8.6% $ -
Sales tax @ 8.6%
Total $ 856.74
Total $
Total Change Orders To Date $ 5,903.94
New Contract Amount $ J
12
1J2k65'g7
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order .............................................. 87 Working Days
Modification to Contract time by this Change Order ................................. 0
Revised Total Contract Time............................................................... 87 Working Days
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is
(are) being made and that the compensation for this Change Order is full and complete and is the
only compensation due or owing for this Change Order. Further, it is mutually agreed that this
document will supplement the present Contract Documents and that the provisions of the previously
executed Contract Documents shall apply to this Change Order.
AGREED
/T�O�AND AC,CETTED: SCC
CONT CTOR / Date
APPROVED:
eONSTRDc'non MANAGER Dat6
APPROVED:
PROdIMT MANAGER Date
AP RO
j/ 67/ I �
PU LI WO Date
DIRECTOR
LL
O
w
W
a
0
Q
LO
0
N
7
0
N
IL
IL
W
0
0.
a
a
O
U
�u
6
w
O
w
IL
IL
a
a
LU
H
IL
LU
U
a
C]
Z
Q
O
H
LU
W
W
CC
Q
o
.
ro
o
o0
LO
H EE
v
T
N
A Y
O m
F- m
O
C
N
7
O
n
O
�
N
�
ER
a�
T
N
O c
U �
CY
00
a
6
O
N
m E
a
W
N
V
U
C •`
N
�a
En
N
C
W
J
o
O
r
C
m m
7
Ci
�
a)
w
(6
m
C
N
U
C
N
O
cl
m
-
L
c
3
�
o
U
cl
cl
Y
E
m��
QO
ul
U
L
U
(]
Q
`)
O
(a
a)
a)
m
O
m
p
C
m
o
O
E
h
U
m
o
a)
a)
O
d Z
O
M
m
L
H
6
w
O
w
IL
IL
a
a
LU
H
IL
LU
U
a
C]
Z
Q
O
H
LU
W
W
CC
Q
CAe
TRENCHING, LLC
Date: 10/16/2015
Attention: Maria Serra, Rene Lopez
Company: City of Pasco
Phone/Pax/Email:
Proiect Name: 65' place and Argent road.
C&EProiect Number: J15949CH2
Scope of Work Bid: Per Bid items
C & E Proiect Manaeer: Jake Wray
• P, 0. Box 3788 • Pasco, WA 99302 • 509.545.6940 oFFIcE • 509.545.8671 Fax
Change Order Request #: 2
Change Order Request
We hereby submit the following change order request for changes in the work required under this Contract with the listed
changes in the Contract Sum listed below:
Change Order Request Scope of Work:
Description
-Quantity
Unit
Unit Price
Ext Price
Demo and pour new ADA ramps with pedestrian
curbs and gravel under sidewalk and landscape.
2.000
EA
$2,273.60
$4,547.20
Traffic control
1.000
cs
$500.00
$500.00
Grand Total:
$
Summary of Changes in Contract
The Original Contract Sum Was $296,382.03
The Net Change by previous authorized change orders $428.37
Contract prior to this Change Order $296,810.40
This Change Order Request Contract Sum (Add) (Deduct) $`447.20-
New Contract Sum $301,357.60
Conditions/ Exclusions:
We look submit the following Change Order Request for your review if accepted please sign below and return authorization of
work. Thank you for the opportunity to earn your work!!
Acceptance of Change Request: The above prices, specifications and conditions are satisfactory and are hereby accepted. You
are authorized to do the work as specified. Payment will be made as outlined.
"For ALL Your Excavating Needs"
www.candetrenching.com
CAe
TRENCHING, LLC
Jake Wray
J060 "F .0 c e
• P.O. Box 3788 • Pasco, WA 99302 • 509.545.6940 omce • 509.545.8671 FAX
Accepted by
"For ALL Your Excavating Needs"
www. ca ndetrenc king. Com
Date