October 09, 2009
Mr. Anthony H. Krutsch
CH2M HILL
295 Bradley Boulevard, Suite 300
Richland, WA 99352
RE: Letter Agreement
Road 40 East Sewer -Cultural Resources Study
Dear Mr. Krutsch:
This letter Agreement is between the City of Pasco (City) and CH2M HILL authorizing
you to proceed with a Cultural Resource Study of the Road 40 East Sewer Project in
Pasco, WA. The terms and conditions of the On -Call Professional Services Agreement
by and between the City and CH2M HILL, dated February 22, 2005, shall be in effect for
these services.
The Cultural Resource Study Scope of Services is attached hereto and made a part
hereof.
CH2M HILL agrees to provide the Road 40 East Sewer Project Cultural Resource Study
for a Fee at hourly rates not to exceed $4,000. The invoice for the services shall be
submitted to the Public Works Director.
Both parties agree to the terms of this Letter Agreement by signing below:
Sincerely,
Robert . Alberts Date Wallace W. Hickerson Dat4
Public Works Director Vice President
C)9
EXHIBIT A
Scope of Work for the Cultural Resource Study of Road 40
East Sewer Alignment for the City of Pasco
Purpose
This scope of work is for a cultural resource investigation for the Road 40 East Sewer
Alignment for the City of Pasco. This Scope of Work was prepared to meet the requests of
the City of Pasco and compliance with Section 106 of the National Historic Preservation Act.
Scope of Work
Task 1 -Document Review and Collection
CH2M HILL will review and collect the necessary documents to provide background
information for the cultural resource report. The review will be conducted in part through
the Department of Archaeology and Historic Preservation (DAHP) and through local
archaeological survey reports and historical documents.
Task 2- Archaeological Survey
CH2M HILL will conduct a pedestrian archaeological survey for the project corridor.
Task 3 -Report
Following the completion of the archaeological survey, a project specific report will be
prepared by CH2M HILL. The report will follow the Washington State Standards for
cultural resource reporting as required by the DAHP, and will provide background
information, survey methods, findings, and recommendations. GIS/CADD mapping and
technical editing will also be required for the report. A draft copy of the report will be
provided to City of Pasco for their review and comments (within 5 working days).
Following receipt of any comments, a final copy will be prepared and delivered to the City
of Pasco.
Assumptions
• No Tribal consultation will be required.
• No Traditional Cultural Properties (TCP) will be identified for the project areas.
• No archaeological sites or isolates will be discovered during the archaeological
survey. In the event archaeological sites or isolates are discovered additional services
may be necessary. No subsurface testing will be conducted.
• Preparation of final copy of report will depend upon getting all comments from the
City within the period noted. No additional time or expenses have been budgeted
for additional review cycles or subsequent revisions to address comments arriving
later.