CONTRACT CHANGE ORDER NO.2
Project No: C5 -GN -9A-14-01 Project Title: Pasco Police Community Services Building
Contractor: Total Site Services
Description of Change: Added vertical basement bars by engineer & installation of electrical
block outs
Detail as Appropriate: For supplying and installing additional 44 bars for the basement walls
Contract Bid Amount: $ 6,582,112.00
SALES TAX @ 8.6%: $ 566,061.63
Total: $ 7,148,173.63
Total Change Orders To Date $ 45,347.74
New Contract Amount $ 7,193,521.38
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order ...............................
Modification to Contract time by this Change Order. .... ..............
revised Total Contract Time ..................................................
YES NO
0
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO 9D ACCEPTED:
'oC l Z 5y/s--
CONTRALTO Dale
APPROVED:
Afr//
CON%UCTION A RE�G
APPROVED:
P OJECT MANAGER Dale
APP OVED'P
�3 l
PU Coo e
DIR CTOR
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 38,534.82
Sales tax @ 8.6% $ 3,313.99
Total $ 41,848.81
Subtotal $ 3,221.85
Sales tax @ 8.6% $ 277.08
Total $ 3,498.93
Total Change Orders To Date $ 45,347.74
New Contract Amount $ 7,193,521.38
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order ...............................
Modification to Contract time by this Change Order. .... ..............
revised Total Contract Time ..................................................
YES NO
0
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO 9D ACCEPTED:
'oC l Z 5y/s--
CONTRALTO Dale
APPROVED:
Afr//
CON%UCTION A RE�G
APPROVED:
P OJECT MANAGER Dale
APP OVED'P
�3 l
PU Coo e
DIR CTOR
Total Site Services, LLC
CHANGE PROPOSAL (CP) NO: 08
TO: City of Pasco
525 North Third Ave PROJECT NAME: Pasco Police Comn
Pasco, WA 99301 Services Building
ATTN: Kent McCue, Construction Manager CONTRACT M C5 -GN -9A-14-01
PROJECT NO: 15-006
DATE: 9/10/2015
VIA: E -Mail
FROM: Dennis Hollis
CP DESCRIPTION
Structural detail 5 on drawing 0251 called out #4 rebar 16" On Center (OC). Same Detail called out #5 rebar from the footing
into the wall at 12" OC. RFI XX confirmed the number 4 rebar was to be on 12" OC instead of 160C. These costs are for
supplying and installing additional #4 bars for the Basement Walls.
This Change Proposal, consisting of an estimate, responds to:
The total cost of the proposed change without WSST is:
This Change Proposal is good through:
The schedule effect of this change is: 2 Days - Required for extra rebar placement
Owner Request
$3,221.85
9/28/2015
Enclosures in support of this proposal includes:
1 ) TSS Estimate for Change
2) Concrete West pricing sheet
3) Harris Rebar
QUALIFICATIONS
IN This proposal covers only the specific items that have been priced as listed on the attached cost breakdown.
Our pricing is based on the quotes of our subcontractors and suppliers and includes any clarifications, qualifications, and exclusions contained
in their quotes
SUBMITTED BY:
Dennis Hollis - Project Manager
APPROVED BY:
of Pasco
09/10/15
DATE
,-
!
!!
)
()
)(
!i
§|
0224!
oncrete
West
INCORPORATED
COMMERCIAL & INDUSTRIAL
FOUNDATIONS
Total Site Services
Richland, WA.
RE; Pasco Police Community Services Building
Pasco, WA.
COMMERCIAL & INDUSTRIAL FOUNDATIONS
7-28-15
LIC.#CONCRW 1065DW
P.O. BOX 7341
KENNEWICK, WA 99336
509-735-8499
FAX: 509-735-9037
Change Order # I
Added Vertical Basement Bars by Engineer & Installation of Electrical Block Outs
Scope of Work, Includes the Following Details &QuantWes
1. 5/0251 1l'-11" Basement Foundation, Added Vertical Bars, were
12" on center out of footing, and then 16" on center into stem wall on
bid plans but, per engineer, were later changed to 12" on center into
stem wall.
This increase = 1, 726 pounds of added bar labor X .675 = 1,165.05
2. 5/0251 Added installation of electrical block outs. We had to cut
out the reinforcing steel, furnish & install 4 each #5 bars around
opening, & install block outs.
Labor = 9 hours x 75.00 = 675.00
Added Reinforcing Steel Furnished = 601 pounds x.57 = 342.57
Total This Change Order # 1 $2,182.62
Total This Change Order # I Price S 2,182.62 w/o sales tax
Payment Terms; Monthly requests for payment submitted by the 25th, with net payment, less 5% retainage by the
following 25th.
All material is guaranteed to be as specified and all work will be performed in a workmanship — like manner according to the specifications and
industry standards. Any alternation in the scope, manner of work or specifications may result in an increase of the stated price proportionate to
the contractor's increased costs and expenses. Any delay in commencement, performance or completion of work occasioned by causes beyond
the control, fruit or neglect of Concrete West may result in an increase of the stated price proportionate to our increased costs and expenses.
Purchaser agrees to pay forthwith onto Concrete West upon written demand therefore any and all costs and expenses incurred by Concrete West
in exercising or "forting any of the obligations of the purchaser herein or the rights of Concrete West hereunder, whether or not suit is
commenced, including reasonable attorney's fees inured in collection attempts and also attorney's fees and costs for preparation and filing
of labor and /or material liens.
Note; This proposal may be withdrawn if not accepted within _ 60 days.
Thank You
Robert Westfall, President
Acceptance of Proposal — The above prices and conditions are satisfactory and are hereby accepted. You are authorized to do the work as
specified. Payment will be made as outlined above.
Date of Acceptance