CONTRACT CHANGE ORDER NO. 1
Project No: C7 -SE -1A-15-42 Project Title: WWTP Caustic Soda Improvements
Contractor: Industrial Constructors, Inc.
Description of Change:
Detail as Appropriate:
e order to address desi
approved prior to beginning construction.
See Attached
Contract Bid Amount
SALES TAX @ 8.6%
Total
and
$ 164,200.00
$ 14,121.20
$ 178,321.20
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal
Subtotal $ 11,369.82
Sales tax @ 8.6% $
Sales tax @ 8.6% $ 977.80
Total $
Total $ 12,347.62
Total Change Orders To Date $ 12,347.62
New Contract Amount $ 190,668.82
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
YES NO
23
68
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to thA Change Order.
ACCEPTED:
APPROVED: -�
ITYMGINEER Date
f
C)(03'(;3
Memo
Public Works Department
Engineering Division
To:
Kent McCue, Construction Manager
CC:
Rene Lopez, Construction Inspector
Brenda Timpany, Admin Assistant 1
From:
David Tanner, P.E., Civil Engineer
Date:
October 5, 2015
Re:
Change Order#1, WWTP Caustic Soda Improvements
Change Order No. 1 reflects the revisions to the W WTP Caustic Soda Improvements listed below. This
change order was negotiated by the City and Contractor to address needed revisions to the project design
prior to beginning construction.
1. Upgrade the proposed Heat Trace system as recommended by the manufacturer and as reviewed
and approved by the Consultant Engineer. $3,978 plus tax.
2. Revisions to the piping and insulation system as recommended by the manufacturer and as
reviewed and approved by the Consultant Engineer. $6,701.46 plus tax.
3. Additional Signage as directed by the Consultant Engineer. $363.41
4. Revisions to the metering pump and valve board as directed by the Consultant Engineer. $326.86
The total change order being requested as part of Change Order #1 is for $11,369.82 plus tax. The
contractor is requesting an additional 23 contract days for time spent in the review and negotiation of the
above change order items.