HomeMy WebLinkAboutPuget Sound Utility M7-WT-2R-15-02 Change No 306/01/2015 11:49 FAX 3607559452 PUGET SOUND UTILITY SVCS CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 3 Project No: M7 -WT -2R-15-02 Project Title: 2015 Water Meter Relocation Contractor: Puget Sound Utility Services Description of Change: Additional work necessary to abandon the mains in the alley. Detail as Appropriate: Please refer to backup sheets attached Contract Bid Amount: SALES TAX @ 8.6%: Total: Q005 $ 92,528.00 $ 7,957.41 $ 100,485.41 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDS Subtotal $ 3,325.00 Subtotal $ 5,142.30 Sales tax @ 8.6% $ 285.95 Sales tax @ 8.6% $ 442.24 Total $ 3,610.95 Total $ 5,584.54 Total Change Orders To Date $ 9,195.49 New Contract Amount $ 109,680.90 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO Contract Time Prior to this Change Order ................................. 30 Modification to Contract time by this Change Order .................... 0 revised Total Contract Time .................................................... 30 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: CONTRACTOR Date APPROVED: ,T.�,l�c���/is C STRUCTION A CCR Oath APPROVED: f; PROJECT M9NAGER Dale APP OV PUBL w Late DIRECTOR Y C LE too fi00 in SOAS A.LI'II.L[1 ONIIOS IHDRd V) ZS 669SLOH XVd 9b:TT STOUTO/90 Memo To: KentMcCue, Construction Manager From: Maria Laura Serra, Associate Engineer Date: May 12, 2015 Re: Change order # 3, 2015 Water Meter Relocation 1'' •.1 Public Works Engineering Change order # 3 reflects the revision to the 2015 Water Meter Relocation project listed below. This change order addresses installation of Brass Plugs and Romac Repair Band in the abandonment of existing water mains. Per City base maps the existing lines presented Tees and Crosses that the project called out to be replaced by the proposed flange spools. Once the contractor uncovered those areas, the existing mains actually presented several small stubs serving the alleyway. This situation was unforeseen and was only discovered after construction had started. In order to abandon the mains in the alley, brass plugs and a repair band were installed. The originally proposed flange spools were not utilized in the project. The table below lists changes and costs associated for 2015 Water Meter Relocation project: NUMBER ITEM UNIT UNIT PRICE QUANTITY TOTAL CO 3.1 Furnish and install %" Brass Plug EA $300 1 $300.00 CO 3.2 Furnish and Install 1" Brass Plug EA $450 4 $1,800.00 CO 3.3 Furnish and Install 6" x 12" Romac Repair Band EA $650 1 $650.00 CO 3.4 Flange Spool Restocking Fee LS $642.30 1 $642.30 CO 3.5 Install Valve Box EA $175 2 $350.00 CO 3.6 Excavation and Disposal LS $930 1 $930.00 CO 3.7 Furnish and Install Gravel LS $260 1 $260.00 CO 3.8 Cold Mix Asphalt Patch LS $210 1 $210.00 SUBTOTAL $5,142.30 TAX (8.6%) $442.24 TOTAL $5,584.54 NOTE: Unit prices for new line items (CO 3.X) were negotiated, as the original bid did not include them. 06/01/2015 11:49 FAX 3607559452 PUGET SOUND UTILITY SVCS CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 4 Project No: M7 -WT -2R-15-02 Project Title: 2015 Water Meter Relocation Contractor: Puget Sound Utility Services Description of Change: Final quantity reconciliation (0 006 Detail as Appropriate: Please refer to backup sheets attached Contract Bid Amount: $ 92,528.00 SALES TAX @ 8.6%: $ 7,957.41 Total: $ 100,485.41 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal $ 8,467.30 Subtotal $ 12,068.00); Sales tax @ 8.6% $ 728.19 Sales tax @ 8.6% $ (1,037.85 Total $ 9,195.49 Total § (93,105.85) Total Change Orders To Date $ (3,910.36) New Contract Amount $ 96,575.05 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO Contract Time Prior to this Change Order ................................. 30 Modification to Contract time by this Change Order .................... 0 revised Total Contract Time .................................................... 30 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: CONTRACTOR f rr.5 Date APPROVED: � 11/ A51 C NSiRUCI ]ON P NAGER —t- e APPROVED: l PROJECT MANAGER Date APPROV-C: 4(./ PU LI O. Date Di.ECTOR 0 w l - CL LU U U a Q z a 0 Q W W Q A Lown SOAS AIPTIJn MMOS .L89[ld 9GV699109£ XVd 66:TT STOZ/TO/90 Memo To: Kent McCue, Construction Manager From: Maria [aura Serra,Associate Engineer Date: May 12, 2015 Re: lead Joint Cross, 2015 Water Meter Relocation 1'' •.l Public Works Engineering The contract provided for the abandonment of the exisfing 2" water main located in the alley between S Sycamore Ave and S Elm Ave to the north of E Helena St. The excavation of the water mains in Helena St between S Sycamore Ave and S Elm Ave, revealed the existence of a 8" x 8" x 6" x 2" lead joint cross. Once the cross was uncovered and the lead joints were identified, it was recommended by the City's Water Department (Operations Division) not to allow the contractor to disturb these mains. Old lead joints are very vulnerable and under any stress or slight movement on these lines could easily cause leaks, jeopardizing the normal operation of the water system and the service to the neighborhood. It was agreed that the contractor would be compensated for the excavation performed and would be exempt from furnishing and installing the cap and concrete thrust block originally specified in the contract documents. The 2" water main abandonment would be performed instead by City Water Crews, who are better suited to conduce a water service shut down, remove the existing lead joint cross and install of a 8" x 6" Tee MJxMJ and reinstate the water service in a timely manner. This decision was based in the capabilifies of the water crew to perform this work with minimal disruption of the existing water lines and protection of the water system as a whole, counting on enough personnel to get the job done in a minimal amount of time.