CONTRACT CHANGE ORDER NO. 1
Project No: C5 -PK -8A-15-11 Project Title: Richardson Park Pool Demolition
Contractor: Big nes Construction
Description of Change: Additional Electrical
Detail as Appropriate: See Attached
Contract Bid Amount: $ 78,029.00
SALES TAX @ 8.6%: $ 6,710.49
Total: $ 84,739.49
PREVIOUS CHANGE ORDER
CURRENT CHANGE
Subtotal
Subtotal $ 850.00
Sales tax @ 8.6%
Sales tax @ 8.6% $ 73.10
Total -
Total 923.10
Total Change Orders To Date $ 923.10
New Contract Amount $ 85,662.59
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................. 45
Modification to Contract time by this Change Order .................... 0
revised Total Contract Time .................................................... 45
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
CONTRACTOR Date
APPROVED:
l2le6." c/es
CONSTRUCTION MANAGER Date
APP
Pq0S i
P J CT MANAGER Date
Memo
1. ' • .l
Engineering
TO: Kent McCue, Construction Manager
Rick Terway, Administrative and Community Service Director
FROM: David Tanner, Civil Engineer
DATE: April 28, 2015
RE: Richardson Park Pool Demolition - Change Order 1
Additional Electrical
Please review and approve the attached change order, and supporting documentation
for additional electrical work necessary to install a new service and disconnect for the
proposed irrigation system and existing park lights. The original intent of the design was
for relocation of existing services only and this work should be considered as a change
in condition.
Submitted costs where for total electrical work, and after negotiation with the contractor,
the City has agreed to pay half of the costs incurred to cover the necessary additional
work to add a new service and disconnect. Staff recommends approving this change
order for $850.00 plus tax.
• Page 1
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.2
Project No: C5 -PK -8A-15-11 Project Title: Richardson Park Pool Demolition
Contractor: Big D's Construction
Description of Change: Change to a full court basketball court
Detail as Appropriate: See Attached
Contract Bid Amount: $ 78,029.00
SALES TAX @ 8.6%: $ 6,710.49
Total: $ 84,739.49
Total Change Orders To Date $ 3,449.11
New Contract Amount $ 88.188.60
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order...- ............................ 45
Modification to Contract time by this Change Order .................... 0
revised Total Contract Time .................................................... 45
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREE TO AND ACCEPTED:
CONTRACTOR Dale
APPROVED:
C-; �1� _Z: /'�� -' -/61s
C NSTRUCTION MANAGER Ute
APP O
PROJECT MANAGER Dale
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $
Sales tax @ 8.6%
Total T
850.00
73.10
923.10
Subtotal $
Sales tax @ 8.6% $
Total
2,325.98
200.03
2,526.01
Total Change Orders To Date $ 3,449.11
New Contract Amount $ 88.188.60
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order...- ............................ 45
Modification to Contract time by this Change Order .................... 0
revised Total Contract Time .................................................... 45
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREE TO AND ACCEPTED:
CONTRACTOR Dale
APPROVED:
C-; �1� _Z: /'�� -' -/61s
C NSTRUCTION MANAGER Ute
APP O
PROJECT MANAGER Dale
Memo
l.' •.1
Engineering
TO: Kent McCue, Construction Manager
Rick Terway, Administrative and Community Service Director
FROM: David Tanner, Civil Engineer
DATE: April 28, 2015
RE: Richardson Park Pool Demolition - Change Order 2
Change from two half court to one full court basketball court
Please review and approve the attached change order, and supporting documentation
for the change from two half court to one full court basketball court, for the Richardson
Park Pool Demolition project. The change was made at the request of the Facilities
services Manager at the pre -construction meeting.
The total costs submitted for the requested change are very close to the engineer's
estimated costs for this work, as shown on the attached supporting documentation, and
staff recommends approving the change request as submitted. All costs appear
reasonable for the work performed, and Staff recommends approving this change order
for $2,325.98 plus tax.
0 Page 1
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 3
Project No: C5 -PK -8A-15-11 Project Title: Richardson Park Pool Demolition
Contractor: Big D's Construction
Description of Change: Change in construction methods for additional sidewalks - No Cost
Detail as Appropriate: See Attached
Contract Bid Amount: $ 78,029.00
SALES TAX @ 8.6%: $ 6,710.49
Total: $ 84,739.49
Total Change Orders To Date $ 3,449.11
New Contract Amount $ 88,188.60
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER ES NO
Contract Time Prior to this Change Order ................................. 45
Modification to Contract time by this Change Order ...... ............. 2
revised Total Contract Time .................................................... 47
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
CONTRACTOR Date
APPROVED:
S�s.5
CON�GEft— Date
Pf6do tr.
APPROVED:
V,
Date
Cts n
PREVIOUS CHANGE ORDER
CURRENT CHANGE
ORDER
Subtotal $
Sales tax @ 8.6% $
Total $
3,175.98
273.13
3,449.11
Subtotal
Sales tax @ 8.6%
Total
$
$
$
Total Change Orders To Date $ 3,449.11
New Contract Amount $ 88,188.60
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER ES NO
Contract Time Prior to this Change Order ................................. 45
Modification to Contract time by this Change Order ...... ............. 2
revised Total Contract Time .................................................... 47
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
CONTRACTOR Date
APPROVED:
S�s.5
CON�GEft— Date
Pf6do tr.
APPROVED:
V,
Date
Cts n
Memo
Engineering
TO: Kent McCue, Construction Manager
Rick Terway, Administrative and Community Service Director
FROM: David Tanner, Civil Engineer
DATE: April 28, 2015
RE: Richardson Park Pool Demolition - Change Order 3
No Cost Change in Construction Methods for Additional Sidewalks
Please review and approve the attached change order, and supporting documentation
for revised demolition methods in exchange for additional sidewalk replacement. As
previously discussed and approved, the City is excepting an alternative method of
demolition for the pool in exchange for replacing the existing sidewalk along 19th
extending from the project limits on the East to the fence at the north property line to the
West (excluding the existing ADA ramp).
There is no cost or additional time associated with this change order.