HomeMy WebLinkAboutBallard Marine - Change Orders 1 & 2 C7-WT-2R-14-06 Butterfield WTP Intake ScreensCITY OF PASCO/1 /��/� A PUBLIC WORKS DEPARTMENT �O�,V,' CONTRACT CHANGE ORDER NO. 1 Project No: C7 -WT -2R-14-06 Project Title: Butterfield Water Treatment Plant Intake Screens Contractor: Ballard Marine Construction, 727 S 27th St., Washougal, WA 98671 Description of Change: Refer to Backup Sheet Detail as Appropriate: Refer to Backup Sheet Contract Bid Amount: $ 669,955.00 SALES TAX @ 8.6%: $ 57,616.13 Total: $ 727,571.13 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal Subtotal $ 10,970.00 Sales tax @ 8.6% $ - Sales tax @ 8.6% $ 943.42 Total $ - Total $ 11,913.42 Total Change Orders To Date $ 11,913.42 New Contract Amount $ 739,484.55 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO Contract Time Prior to this Change Order ................................................... 40/100 Modification to Contract time by this Change Order ....................................... 2 Revised Total Contract Time.................................................................... 40/102 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: C TRACT R Date /APPROVED: -/s- C40NSTRUCTION MANAGER Date APPROVED: A PROJECT MANAGER e a S APPROVED: /#1 _Z9 PUBLIC WOR Date DIRECTOR as?3 F— LU W W 2 N IL Y Q m O z w LU 0 O W a 2 U H U a z O U H CL LU 0 3 a a O U Y N m u 0 W O w IL IL Q G LU H IL LU U U Q z Q O G W W Q 0 „ o O O O^i_ FEo T � R Y O R F �7 0 0 c o O C U Q o Y� O c U � 0 C ' m O a fA 'C U acnL N c T C m R Cr a� w a� w C N 0 C O N m c co U O N � N C R N N _ U a d � 3 u 0) R R m E _ 0 c °'z0 U s F 0 W O w IL IL Q G LU H IL LU U U Q z Q O G W W Q Project: Butterfield WTP Intake Structure Contractor: Client Name : City of Pasco Street Address; 525 N. 3rd Ave. City, State ZIP Pasco, WA 99301 CHANGE ORDER # 001 INITIATION DATE January 20.2015 PROJECT NUMBER: #C7 -WT -2R-14-06 CONTRACT DATE: November 14. 2014 to the sediment and debris levels within the intake structure the intake screens won't be able to be installed until it is removed. This trial can be dredged out using pumps and discharged back into the Columbia River. Below is a breakout of equipment and labor in order to >rm this task. It is anticipated to take two days to complete this work, therefor two days would be requested to be added to the schedule. EST UNIT ORG ITEM DESCRIPTION OTY UNIT AMT AMT 1 Labor 1 is 6,457.59 6,457.59 2 Equipment l is 3,148.67 3,148.67 3 Markup @ 15% 1 Is 1,363.74 1,363.74 Original Contract 727,571/3 Previous change orders - - Adjusted Contract 727,571.13 Current Change Order 10,970.00 Revised Contract ,3 ,541.13 Contract Completion Date: TBD Number of Days +/- added to or subtracted from Completion Date \00 Revised Contract Completion Date: "��' S Ccs I n TBD Ballard Marine Constmcion Client Name : City of Pasco I Sub -Contractor Contractor IWTr 727 S 27th St, Washougal, WA 98671 Address Street Address; 525 N. 3rd Ave. Address Pasco, WA 99301 77 By Date Memo Public Works Department Engineering Division To: Kent McCue, Construction Manager �/_w CC: Ryan Mahaffey, Construction Inspector \ Brenda Timpany, Admin Assistant 1 \ From: Teresa Reed -Jennings, P.E., Senior Civil Engin{� Date: January 20, 2015 2v1 uK� Vej +-beef -0-1 Re: Change Order #Z Butterfield Water Treatment Plant Intake Screens Change Order No. 2 reflects the revisions to the Butterfield Water Treatment Plant Intake Screens listed below. This change order was requested by the Contractor. After the preconstruct on meeting Ballard Marine Construction performed a dive which showed that there was considerable sediment and debris in the intake structure wetwell. This sediment and debris must be removed before the new intake screens can be installed. This material will be dredged out using pumps and discharged back into the Columbia River via the existing discharge chute. Ballard Marine Construction has provided a cost breakdown for the extra cleanup work. They have also requested an additional 2 working days to complete the wetwell cleanup. The last routinely scheduled wetwell cleaning cost approximately $5,000 in 2012. Io2— This change order will add 2 working days to the contract for a total ofWorking Days. The pre-tax cost associated with this change order is $10,970. The additional contract days extends the new completion date on June 1, 2015. The additional two days will change the completion date for Phase 1 from March 4, 2015 to March 6, 2015. This change has no effect on the water work window, which will still end on February 28, 2015. 0 Page 1 CITY CO PUBLIC ORF PAS ARTMENT 0p'v,' •41 CONTRACT CHANGE ORDER NO. 2 Project No: C7 -WT -2R-14-06 Project Title: Butterfield Water Treatment Plant Intake Screens Contractor: Ballard Marine Construction 727 S 27th St. Washougal WA 98671 Description of Change: Refer to Backup Sheet Detail as Appropriate: Refer to Backup Sheet Contract Bid Amount: SALES TAX @ 8.6%: Total: $ 669,955.00 $ 57,616.13 $ 727,571.13 PREVIOUS CHANGE ORDERS CURRENT CHANGE ORDER Subtotal $ 10,970.00 Subtotal $ 48,665.00 Sales tax @ 8.6% $ 943.42 Sales tax @ 8.6% $ 4,185.19 Total $ 11,913.42 Total $ 52,850.19 Total Change Orders To Date $ 64,763.61 New Contract Amount $ 792,334.74 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO Contract Time Prior to this Change Order... ............................... ............ 40/102 Modification to Contract time by this Change Order .................................. 4 Revised Total Contract Time............................................................... 40/106 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: CO TRA OR Date APPROVED: �Z�l/1�1 c� e Z - ZS1, (,5- CONSTRUCTION <S C NSTRUCTION MANAGER Date A�/PPROVED: A/Ye wo a - C PROJECT MANAGER Date /eJ APPROVED: _ C WOR - Date DIRECTOR F - w W 2 fn CL 7 Y L) m N d z w w 0 O W CD z Q 2 U F - v a F - z O U F- a W IL a O U 16, a 0 0 LO 0 o m ~av e» T +� C f- 7 O 0 0 c vi O 0 U O co aco >1 0 cc 3 0 c a c m E Q C O IL` N C J 7 w 'a c m � C� w C N 0 `a u O C MlU Q N Y U � L � ~ U � o � a N c c E f6 N L - U75 o a m 0 0 0 L 0 U � F- c LU O X CL a Q O W a W U U Q z Q O F- W W Q Memo To: Kent McCue, Construction Manager M4 Public Works Department Engineering Division CC: Ryan Mahaffey, Construction Inspector Brenda Timpany, Admin Assistant 1 From: Teresa Reed -Jennings, P.E., Senior Engineer Date: February 10, 2015 Re: Change Order#2, Butterfield Water Treatment Plant Intake Screens Change Order No. 2 reflects the revisions to the Butterfield Water Treatment Plant Intake Screens listed below. This change order was requested by the Contractor. After the preconstruction meeting Ballard Marine Construction performed a dive which showed that the wall thickness shown on the construction plans was inaccurate. This issue has caused the need to make some revisions to the original construction plan. Ballard Marine Construction has been worked to resolve the issue with the Design Engineer RI -12 Engineering. Ballard Marine Construction has provided a cost breakdown for the extra construction work. Additionally, the redesign has changed Ballard Marine Construction's project schedule. Due to this they have requested the addition of 4 working days to allow for the time to correct the issue. This change order will add 4 working days to the contract for a total of 106 Working Days. The pre-tax cost associated with this change order is $$48,665. The additional contract days extends the new completion date on May 28, 2015. The additional day will change the completion date for Phase 1 from March 6, 2015 to March 12, 2015. This change has no effect on the water work window, which will still end on February 28, 2015. 0 Page 1