HomeMy WebLinkAboutBallard Marine - Change Orders 1 & 2 C7-WT-2R-14-06 Butterfield WTP Intake ScreensCITY OF PASCO/1 /��/�
A
PUBLIC WORKS DEPARTMENT �O�,V,'
CONTRACT CHANGE ORDER NO. 1
Project No: C7 -WT -2R-14-06 Project Title: Butterfield Water Treatment Plant Intake Screens
Contractor: Ballard Marine Construction, 727 S 27th St., Washougal, WA 98671
Description of Change: Refer to Backup Sheet
Detail as Appropriate: Refer to Backup Sheet
Contract Bid Amount: $ 669,955.00
SALES TAX @ 8.6%: $ 57,616.13
Total: $ 727,571.13
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal
Subtotal $ 10,970.00
Sales tax @ 8.6% $ -
Sales tax @ 8.6% $ 943.42
Total $ -
Total $ 11,913.42
Total Change Orders To Date $ 11,913.42
New Contract Amount $ 739,484.55
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................................... 40/100
Modification to Contract time by this Change Order ....................................... 2
Revised Total Contract Time.................................................................... 40/102
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
C TRACT R Date
/APPROVED:
-/s-
C40NSTRUCTION MANAGER Date
APPROVED:
A
PROJECT MANAGER e a S
APPROVED:
/#1 _Z9
PUBLIC WOR Date
DIRECTOR
as?3
F—
LU W
W
2
N
IL
Y
Q
m
O
z
w
LU
0
O
W
a
2
U
H
U
a
z
O
U
H
CL
LU
0
3
a
a
O
U
Y
N
m
u
0
W
O
w
IL
IL
Q
G
LU
H
IL
LU
U
U
Q
z
Q
O
G
W
W
Q
0
„
o
O O
O^i_
FEo
T
�
R Y
O R
F
�7
0
0
c
o
O
C
U
Q
o
Y�
O c
U �
0
C
'
m O
a
fA
'C U
acnL
N
c
T
C
m R
Cr
a�
w
a�
w
C
N
0
C
O
N
m
c
co
U
O
N
�
N
C
R
N
N
_
U
a
d
�
3
u
0)
R
R
m
E
_
0
c
°'z0
U
s
F
0
W
O
w
IL
IL
Q
G
LU
H
IL
LU
U
U
Q
z
Q
O
G
W
W
Q
Project: Butterfield WTP Intake Structure
Contractor:
Client Name : City of Pasco
Street Address; 525 N. 3rd Ave.
City, State ZIP Pasco, WA 99301
CHANGE ORDER # 001
INITIATION DATE January 20.2015
PROJECT NUMBER: #C7 -WT -2R-14-06
CONTRACT DATE: November 14. 2014
to the sediment and debris levels within the intake structure the intake screens won't be able to be installed until it is removed. This
trial can be dredged out using pumps and discharged back into the Columbia River. Below is a breakout of equipment and labor in order to
>rm this task. It is anticipated to take two days to complete this work, therefor two days would be requested to be added to the schedule.
EST UNIT ORG
ITEM DESCRIPTION OTY UNIT AMT AMT
1 Labor 1 is 6,457.59 6,457.59
2 Equipment l is 3,148.67 3,148.67
3 Markup @ 15%
1 Is 1,363.74 1,363.74
Original Contract
727,571/3
Previous change orders
- -
Adjusted Contract
727,571.13
Current Change Order
10,970.00
Revised Contract
,3 ,541.13
Contract Completion Date: TBD
Number of Days +/- added to or subtracted from Completion Date \00
Revised Contract Completion Date: "��' S Ccs I n TBD
Ballard Marine Constmcion Client Name : City of Pasco I
Sub -Contractor Contractor
IWTr
727 S 27th St, Washougal, WA 98671
Address
Street Address; 525 N. 3rd Ave.
Address Pasco, WA 99301
77 By Date
Memo
Public Works Department
Engineering Division
To: Kent McCue, Construction Manager �/_w
CC: Ryan Mahaffey, Construction Inspector \
Brenda Timpany, Admin Assistant 1 \
From: Teresa Reed -Jennings, P.E., Senior Civil Engin{�
Date: January 20, 2015 2v1 uK� Vej +-beef -0-1
Re: Change Order #Z Butterfield Water Treatment Plant Intake Screens
Change Order No. 2 reflects the revisions to the Butterfield Water Treatment Plant Intake Screens listed
below. This change order was requested by the Contractor.
After the preconstruct on meeting Ballard Marine Construction performed a dive which showed that there was
considerable sediment and debris in the intake structure wetwell. This sediment and debris must be removed
before the new intake screens can be installed. This material will be dredged out using pumps and
discharged back into the Columbia River via the existing discharge chute. Ballard Marine Construction has
provided a cost breakdown for the extra cleanup work. They have also requested an additional 2 working
days to complete the wetwell cleanup. The last routinely scheduled wetwell cleaning cost approximately
$5,000 in 2012.
Io2—
This change order will add 2 working days to the contract for a total ofWorking Days. The pre-tax cost
associated with this change order is $10,970. The additional contract days extends the new completion date
on June 1, 2015. The additional two days will change the completion date for Phase 1 from March 4, 2015 to
March 6, 2015. This change has no effect on the water work window, which will still end on February 28,
2015.
0 Page 1
CITY
CO
PUBLIC ORF PAS ARTMENT 0p'v,' •41
CONTRACT CHANGE ORDER NO. 2
Project No: C7 -WT -2R-14-06 Project Title: Butterfield Water Treatment Plant Intake Screens
Contractor: Ballard Marine Construction 727 S 27th St. Washougal WA 98671
Description of Change: Refer to Backup Sheet
Detail as Appropriate: Refer to Backup Sheet
Contract Bid Amount:
SALES TAX @ 8.6%:
Total:
$ 669,955.00
$ 57,616.13
$ 727,571.13
PREVIOUS CHANGE ORDERS
CURRENT CHANGE ORDER
Subtotal $
10,970.00
Subtotal $
48,665.00
Sales tax @ 8.6% $
943.42
Sales tax @ 8.6% $
4,185.19
Total $
11,913.42
Total $
52,850.19
Total Change Orders To Date $ 64,763.61
New Contract Amount $ 792,334.74
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
YES NO
Contract Time Prior to this Change Order... ............................... ............ 40/102
Modification to Contract time by this Change Order .................................. 4
Revised Total Contract Time............................................................... 40/106
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are)
being made and that the compensation for this Change Order is full and complete and is the only
compensation due or owing for this Change Order. Further, it is mutually agreed that this document will
supplement the present Contract Documents and that the provisions of the previously executed
Contract Documents shall apply to this Change Order.
AGREED TO AND ACCEPTED:
CO TRA OR Date
APPROVED:
�Z�l/1�1 c� e Z - ZS1, (,5-
CONSTRUCTION
<S
C NSTRUCTION MANAGER Date
A�/PPROVED:
A/Ye wo a - C
PROJECT MANAGER Date /eJ
APPROVED:
_ C WOR - Date
DIRECTOR
F -
w
W
2
fn
CL
7
Y
L)
m
N
d
z
w
w
0
O
W
CD
z
Q
2
U
F -
v
a
F -
z
O
U
F-
a
W
IL
a
O
U
16,
a
0
0
LO
0 o
m
~av
e»
T
+� C
f- 7
O
0
0
c
vi
O 0
U O
co
aco
>1
0
cc
3
0
c
a c
m E
Q
C O
IL`
N
C
J
7
w
'a c
m �
C�
w
C
N
0
`a
u
O
C
MlU
Q
N
Y
U
�
L
�
~
U
�
o
�
a
N
c
c
E
f6
N
L
-
U75
o
a
m
0
0
0
L
0
U
�
F-
c
LU
O
X
CL
a
Q
O
W
a
W
U
U
Q
z
Q
O
F-
W
W
Q
Memo
To: Kent McCue, Construction Manager M4
Public Works Department
Engineering Division
CC: Ryan Mahaffey, Construction Inspector
Brenda Timpany, Admin Assistant 1
From: Teresa Reed -Jennings, P.E., Senior Engineer
Date: February 10, 2015
Re: Change Order#2, Butterfield Water Treatment Plant Intake Screens
Change Order No. 2 reflects the revisions to the Butterfield Water Treatment Plant Intake Screens listed
below. This change order was requested by the Contractor.
After the preconstruction meeting Ballard Marine Construction performed a dive which showed that the wall
thickness shown on the construction plans was inaccurate. This issue has caused the need to make some
revisions to the original construction plan. Ballard Marine Construction has been worked to resolve the issue
with the Design Engineer RI -12 Engineering. Ballard Marine Construction has provided a cost breakdown for
the extra construction work. Additionally, the redesign has changed Ballard Marine Construction's project
schedule. Due to this they have requested the addition of 4 working days to allow for the time to correct the
issue.
This change order will add 4 working days to the contract for a total of 106 Working Days. The pre-tax cost
associated with this change order is $$48,665. The additional contract days extends the new completion date
on May 28, 2015. The additional day will change the completion date for Phase 1 from March 6, 2015 to
March 12, 2015. This change has no effect on the water work window, which will still end on February 28,
2015.