HomeMy WebLinkAboutPuget Sound Utility Services 719 S HugoCITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 1 Project No: M7 -WT -2R-15-02 Project Title: 2015 Water Meter Relocation Contractor: Puget Sound Utility Services Description of Change: Reverse plumbing for house located at 719 S Hugo Ave Detail as Appropriate: Due to the ;tence of concrete slabs and outside buildings, the connection by City Staff the need for the General Contractor to tie in the new water service at the front of the house and reverse the olumbina of the house with the assistance of a Licensed Plumber. Contract Bid Amount: SALES TAX @ 8.6%: Total: $ 92,528.00 $ 7,957.41 $ 100,485.41 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal Subtotal $ 625.00 Sales tax @ 8.6% $ Sales tax @ 8.6% $ 53.75 Total $ Total $ 678.75 Total Change Orders To Date $ 678.75 New Contract Amount $ 101,164.16 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO Contract Time Prior to this Change Order ................................................... 30 Working Days Modification to Contract time by this Change Order ....................................... N/A Revised Total Contract Time.................................................................... 30 Working Days It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: APPROVED: _ —�`1—�� 0065u 1RIkA L,Sok '5/15 COI' TOR Date PROJECT MANAGER Date APPROVED: C NSTRUCTION MANAGER bate APPROVE /J PU LIC Date DIRECTOR Memo To: Kent McCue, Construction Manager From: Maria Laura Serra, Associate Engineer Date: April 13, 2015 W. Re: Change order # 1, 2015 Water Meter Relocation Public Works Engineering Change order # 1 reflects the revision to the 2015 Water Meter Relocation project listed below. This change order addresses the fact that a Licensed Plumber was required to be hired to reverse the plumbing for the house located at 719 S Hugo Ave. For this particular property and given the conditions found during construction, the new water service connection was approved to be performed at the front of the house instead of the back of the house, as was originally required by the Contract Documents. The front of the house was determined to be the preferred connection location in order to avoid the disruption of existing concrete slabs and/or existing shop/shed located in the back of the property, as well as to provide the shortest new service length. The table below lists all changes and costs associated for 2015 Water Meter Relocation project: NUMBER ITEM UNIT UNIT PRICE QUANTITY TOTAL CO 1.1 Reverse Plumbing LS $625 1 $625.00 SUBTOTAL $625.00 TAX (8.6%) $53.75 TOTAL $678.75 CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 2 Project No: M7 -WT -2R-15-02 Project Title: 2015 Water Meter Relocation Contractor: Puget Sound Utility Services Description of Change: Installation of tee and cap assemblies to allow water service to existing irrigation system in yeard to remain operational Detail as Appropriate: This change order applies to the properties listed on the attached memo. Contract Bid Amount: $ 92,528.00 SALES TAX @ 8.6%: $ 7,957.41 Total: $ 100,485.41 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal $ 625.00 Subtotal $ 2,700.00 Sales tax @ 8.6% $ 53.75 Sales tax @ 8.6% $ 232.20 Total $ 678.75 Total $ 2,932.20 Total Change Orders To Date $ 3,610.95 New Contract Amount $ 104,096.36 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER Contract Time Prior to this Change Order ................................. Modification to Contract time by this Change Order .................... revised Total Contract Time .................................................... YES NO 30 0 30 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO//AND ACCEPTED: gGfUKACTOR Date APPROVED: y'1-, 5S PRO ECT MANAGER Date %APPROVED: APPROVED: / CONSTRUCTION MANAGER Date _� PUBLIC OR S Date DIRECTOR Memo To: Kent McCue, Construction Manager From: Maria [aura Serra, Associate Engineer M L S Date: April 16, 2015 Re: Change order# 2,2015 Water Meter Relocation -, a 1.1 Public Works Engineering Change order # 2 reflects the revision to the 2015 Water Meter Relocation project listed below. This change order addresses installation of Tee and Cap assemblies to provide water service to each unit of the triplex located at 128 S Hugo Ave and to allow existing irrigation systems to remain operational in yards (see addresses listed below). This situation was unforeseen and was only discovered after construction had started. The proposed tee assembly to connect the new water service to the existing one in the immediate proximity of the house and the installation of a cap behind the irrigation system deviation were analyzed and considered to be an appropriate solution. The tee assembly requires the use of two couplers, six stiffeners and a tee fitting, instead of one coupler and two stiffeners as was originally required by the Contract Documents. The cap assembly consists of a coupler and a cap. These items were special ordered and required overnight shipping to avoid delays in the project completion date. The properties affected by this change order are listed below: 1 & 2 130 and 132 S Hugo Ave (3 services were found instead of one and two of UNIT those services required tee and cap assembly) 3 517 S Waldemar Ave 4 630 S Cedar Ave 5 638 S Sycamore Ave 6 636 S Sycamore Ave 7 630 S Waldemar Ave 8 523 S Elm Ave 9 525 S Elm Ave The table below lists all changes and costs associated for 2015 Water Meter Relocation project: NUMBER ITEM UNIT UNIT PRICE QUANTITY TOTAL CO 2.1 Tee and Cap Assemblies EA $300 9 $2,700.00 SUBTOTAL $2,700.00 TAX (8.6%) $232.20 TOTAL $2,932.20