HomeMy WebLinkAbout1085 Resolution1085
RESOLUTION NO.
A RESOLUTION ACCEPTING THE WORK DONE BY
MID COLUMBIA CONSTRUCTION COMPANY, INC.
UNDER JOB NO. 76-2-02, COURT STREET
WATER LINE.
WHEREAS, the work done by Mid Columbia Construction, Inc., under Job
No. 76-2-02, Court Street Water Line has been duly examined by the City Engineer
and the City Engineer having found that the work on said project has been completed
in accordance with the plans and specifications of said project, and it appears
that the City should now accept the same and concur in the Engineer's recommendation,
NOW THEREFORE;
THE.CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, DO RESOLVE AS FOLLOWS:
Section 1. That the City Council concurs in the Engineer's recommendations
and finds that work done under Job No. 76-2-02, Court Street Water Line, has been
completed in accordance with the plans and specifications of said project, and
therefore, the City Council should accept the same.
Section 2. That the said City of Pasco does now accept the work done by
Mid Columbia Construction Company, Inc. on Job No. 76-2-02, Court Street Water
Line as the.same has been completed by said contractor in accordance with the
plans and specifications of said project.
Section 3. That the Department of Labor and Industries and the Washington
State Tax Commission be notified of the acceptance of this work.
PASSED BY THE CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, this
19
day of
April
ATTEST:
Leo E. Olney,`Director of Fi i ce
and Ex -Officio City Clerk
APPROVED AS TO FORM:
Vk T. Roach, City Attorney
1977.
Jan Tldiick, Mayor