HomeMy WebLinkAbout1038 ResolutionRESOLUTION NO. 1038
A RESOLUTION ACCEPTING THE WORK DONE BY L. W. VAIL
COMPATJY, INC., UNDER JOB NO. 75-3-09, OREGON STREET
EXTENSION.
WHEREAS, the work done by L. W. Vail Company, Inc., under Job No. 75-3-09,
Oregon Street Extension has been duly examined by the City Engineer and the City
Engineer having found that the work on said project has been completed in accor-
dance with the plans and specifications of said project, and it appears that the
City should now accept the same and concur in the Engineer's recommendation,
NOW THEREFORE;
THE CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, DO RESOLVE AS FOLLOWS:
Section 1. That the City Council concurs in the Engineer's recommendations
and finds that work done under Job No. 75-3-09, Oregon Street Extension has been
completed in accordance with the plans and specifications of said project, and
therefore, the City Council should accept the same.
Section 2. That the said City of Pasco does now accept the work, done by
L. W. Vail Company, Inc., on Job No. 75-3-09, Oregon Street Extension as the same
has been completed by said contractor in accordance with the plans and specifications
of said project.
Section 3. That the Department of Labor and Industries and the Washington
State Tax Commission be notified of the acceptance of this work.
PASSED BY THE CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, this
15
da y of
June , 1976,
f
J Tidrick, Mayor
ATT ' .
Evelyn Wells, Deputyl_City Clerk
APPROVED AS TO FORM:
Patrick T. Roach, City Attorney
June 4, 1976
MEMORANDUM TO: George D. Smith, City Manager Q
FROM: James S. Ajax, City Engineer J• S "`
SUBJECT:
Oregon Street Extension
Project No. 75-3-09
Work on the subject project is now complete and in apparent compliance
with the Plans and Specifications. The original contract was for
$42,067.00. The final project cost is $77,375.86.
STAFF RECOMMENDATION: The staff's recommendation is that the above
mentioned work be accepted.
PROJECT: Oregon Street Extension
75-3-09
DESCRIPTION
1. Common Excavation
2 Remove existing curb & gutter
3. Trench excavation (24" & 10" pipe)
4. Furnish & install 24" aluminum pipe
5. Furnish & install 10" aluminum pipe
6. Furnish & install standard manhole
Type I-48
7. Additional manhole depth
8. Base Pock (1-1/4")(6"inch)
9. Leveling Course (5/8")(3"inch)
10. Asphalt concrete, Class "B"
11. Construct new catch basin
12. Curb & gutter, type "A"
13. Curb & gutter, type "D"
14. Construct standard barricade
15. Connect to existing manhole
SEMI - FINAL Progress Payment
Work through April 23, 1976
CONTRACTOR: L. W. Vail Co., Inc.
QUANTITY
3172 C.Y.
119 L.F.
977 C.Y.
790 L.F.
205.L.F.
2 each
3 L.F.
1597 Ton
753 Ton
842 Ton
5 each
1805 L.F.
20 L.F.
50 L.F.
1 each
TOTAL EARNED
$5,456.00
60.00
3,517.00
5,649.00
738.00
790.00
120.00
4,440.00
2,334.00
12,799.00
1,025.00
4,242.00
47.00
750.00
100.00
LUMP SUM BID
CHANGE ORDER NO. 1
Furnish & Haul 10 C.Y. of rock
Build drywell
CHANGE ORDER NO. 2
Plug manhole
Orange reflectorized tape on barricade
CHANGE ORDER NO. 3
$42,067.00
$ 40.00
35.00
$ 75.00
$ 110.00
$ '220.00
Relocate catch basin $200.00
TOTAL EARNED $42,562.00
LESS 10% RETAINAGE 4,256.20
LESS .PREVIOUS PAYMENTS -0-
AMOUNT NOW DUE $38,305.80
BILL TO: Housing & Community Development Block Grant
xc: L. W. Vail Company, Inc.
Iry Kau, Public Works Director
Webster Jackson, Urban Renewal Director
Project File