HomeMy WebLinkAbout0970 ResolutionRESOLUTION NO. 970
A RESOLUTION ACCEPTING THE WORK DONE BY G. GREGORY
CONSTRUCTION COMPANY UNDER JOB NO. 74-05, MARIE
STREET SANITARY SEWER
WHEREAS, the work done by G. Gregory Construction Company, under Job No.
74-05, Marie Street Sanitary Sewer has been duly examined by the City Engineer
and the City Engineer having found that the work on said project has been com-
pleted in accordance with the plans and specifications of said project, and it
appears that the City should now accept the same and concur in the Enaineer's
recommendation, NOW THEREFORE;
THE CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, DO RESOLVE AS FOLLOWS:
Section 1. That the City Council concurs in the Engineer's recommendations
and finds that work done under Job No. 74-05, Marie Street Sanitary Sewer has been
completed in accordance with the plans and specifications of said project, and
therefore, the City Council should accept the same.
Section 2. That the said City of Pasco does now accept the work done by
G. Gregory Construction Company, on Job No. 74-05, Marie Street Sanitary Sewer
as the same has been completed by said contractor in accordance with the plans
and specifications of said project.
Section 3. That the Department of Labor and Industries and the Washington
State Tax Commission be notified of the acceptance of this,work.
PASSED BY THE CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, this
21
day of
January, 1975
DONAL D. LINT N, PAYOR
ATTEST -
LEO E. OLNEY, DIRECTOR 0 FINANC
AND EX -OFFICIO CITY CLERK.
APPROVED AS TO FORM:
PRICK T. ROACH, CITY ATTORNEY
v � I
•
January 14, 1975
MEMORANDUM TO: Mayor and City Councilmen
f;_
ATTENTION: Harry D. Kinzer, City Manager -0-
FROM: James S. Ajax, City Engineer
SUBJECT:
Marie Street Sanitary Sewer
Project No. 74-05
Contractor G. Gregory Construction Company
Work on the subject project is note complete and in apparent compliance with
the plans and specifications. The original contract amount was $6,973.58.
Final contract amounted to $6,926.85. This reduction was due to a slight
reduction in quantities.
RECOMMENDATION: It is the staff's recommendation that the
work be accepted.
•