HomeMy WebLinkAbout0840 Resolutiona
1
84o
RESOLUTION NO.
A RESOLUTION ACCEPTING THE WORK DUNE BY A. V. DEBLASIO
CONSTRUCTION UNDER JOB NO. 70-05 CHASE AVENUE STORM SEWER
(L.I.D. 82).
WHEREAS, the work done by A. V. UeBlasio Construction under
Job No. 70-05, Chase Avenue storm sewer (L.I.U. 82) has been duly
examined by the City Engineer and the City Engineer having found that
the work on said project has been completed in accordance with the plans
and specifications of said project, and it appears that the City should
now accept the same and concur in the Engineer's recommendation, now therefore;
THE CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, DOES RESOLVE
AS FOLLOWS:
Section 1. That the City Council concurs in the Engineer's
recommendations and finds that work done under Job No. 70-05, Chase
Avenue storm sewer (L.I.D. 82) has been completed in accordance with
the plans and specifications of said project, and therefore, the
City Council should accept the same.
Section 2. That the said City of Pasco does now accept the work
done by A. V. UeBlasio Construction on Job No. 70-05, Chase Avenue storm
sewer (L.I.D. 82) as the same has been completed by said contractor in
accordance with the plans and specifications of said project.
Section 3. That the Department of Labor and Industries and the
Washington State Tax Commission be notified of the acceptance of this
work.
PASSED BY THE CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, this
day of January 1971.