ADJOURNED MEETING: COUNCIL CHAITBER FEBRUARY 2 1944.
CALL TO ORDER: Meeting called to order at eight -fifteen oclock Honorable Illayor E. S. Johnston
presiding.
ROLL CALL By Clerk found all councilmen and the City Attorney present.
OPENING 07 BIDS ON SEWER PROJECT:
Bids were opened and read by I,Tr. Zeidilhack, with the Consulting Engineers,
13 bids were received; The Sewer Cormnittee and IIIc. Zeidlhack adjourned to the Water
office to figure on the Aids, the meeting was again called to order on their return
and the.bids read as follows in numerical order lowest bid first.
Name Location
Total
Total
_ ________ __
Wet _Well ____
D_ryItiIell_
B. H. Sheldon Spoiane Vdashington
$59,291.55
$599977.55
Valley Construction Co. Seattle Washington
$697590.55
$701090.50
Thornburn & Logozo Seattle Washington
$78,9,)6.5o
$78.9-16.50
Macri & Company Seattle, Washington
$889176.85
$907176.85
Leonard & Slate Co. Portland, Ore.
$89,76.50
$909486.50
Matt Tilalaspina Seattle, Washington
$9'9025.50
$9','55..50
Cascade Construction Co. Seattle, Washington
$9'7245.60
$9?9770.60
L. Coluccio Company Seattle, Washington
$109962.50
$110112'.50
Sound Construction Co. Seattle, Washington
$1111"58.75
$111,958.75
TAT. P. Munter Seattle, Washington
$1211749.70
$1211749.'0
H. M. Buchanan Layton Utah
$1307767.00
$101767.00
Geo. Abraham Portland Ore.
$15893392.00
$1581892.00
Halverson Construction CO. Salem, Ore.
$168,363.20
$1681754.20
f Tlotion made by Marshall seconded by Linderman
that Mr. Zeidlhack
take the
four lowest bids to Portland Ore., decisi6nn of the
award to be
made by the consultant
engineers motion carried so ordered.
I
i
BOND AUTHORIZATION:
In discussing the bond issue IsTr. I. -Terrill suggested
the authorization
of an
over-all issue in the amount of $00,000.00 to cover
the seven units
and disposal
plantencluded in the original plan motion made by
issue $00,000.00
Booth seconded
Baker to authorize
an of (Three hundred thousand) motion
carried
so ordered.
To cover cost of bid on construction worexpenses
Rodkey by Lindermar��`$125,000.00 h11ndred-twenty.
involved a motion
was mad e'3Yththoriz:ed
seconded :(one.
_five
thousand)/ or e
present issue motion carried'�so ordered. That the
East Side and
Owens Addition be
surveyed was agreeded upon motion made by Marshall
seconded by?Baker
that the Com-
mittee in charge make a survey and bring in recommendations
motion
carried so ordered.
ADJOURNMENT:
IMTotion made by Baker seconded by Booth that the meeting adjourn to next re-
gular meeting night Tuesday March 7th 1944 motion carried so ordered.
ATTESTED:
yCity Clerk
Passed and approved thisday of March 1944.
TTayor
City Clerk