Loading...
HomeMy WebLinkAboutSierra Electric Change Order No 10 C2-11-16-STR Rd 68 Improvements Ph 2CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 10 Project No: C2-11-16-STR Project Title: Rd 68 Improvements, Ph 2 Contractor: Sierra Electric Description of Change: Relocate irrigation main and valves on Burden Blvd. Detail as Appropriate: See Attached Contract Bid Amount: $ 1,201,687.00 SALES TAX @ 8.6%: N/A Total: $ 1,201,687.00 PREVIOUS CHANGE ORDERS CURRENT CHANGE ORDER Subtotal $ (4,065.47) Subtotal $ 4,122.00 Sales tax @ 8.6% N/A Sales tax @ 8.6% N/A Total $ (4,065.47) Total $ 4,122.00 Total Change Orders To Date $ 56.53 New Contract Amount $ 1,201,743.53 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO Contract Time Prior to this Change Order ................................. 163 Modification to Contract time by this Change Order .................... 5 revised Total Contract Time .................................................... 168 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED:APPROVED: / CONTRACTOR Date cANA ER at APPROVED: APPROVED: sig CITYENGNWD6te PUBLIC WORKS Date DIRECTOR Memo Public Works Department Engineering Division To: Mike Pawlak, P.E., City Engineer CC: Kent McCue, Construction Manager Rene Lopez, Construction Inspector Brenda Timpany, Admin Assistant 1 From: Kate Thompson, P.E., Civil Engineer Date: November 19, 2014 Re: Change Order#10, Road 68 Improvements Phase 2 and Interconnect Rd 68 Signals Change Order No. 10 reflects the revisions to the Road 68 Improvements Phase 2 Project listed below. This change order was requested by the City. 1) During construction of the revisions to the existing center medians on Burden Blvd the sub- contractor ran into issues with the existing irrigation main and valves in several locations. This required the sub -contractor to have to relocate irrigation main and valves. The contract documents didn't include a provision for revision to the irrigation system beyond relocating existing sprinkler heads. This required the subcontractor to need to obtain additional supplies and took more manpower to complete the work. The Following Table shows the costs associated with Change Order #10. NO. DESCRIPTION UNIT BID UNIT QUANTITY TOTAL PRICE 1 1 Additional Irrigation S tem Repairs LS $4,122.00 1 1 $4,122.00 TOTAL CHANGE ORDER #10 1 $4,122.00 The total quantity of work completed was difficult to quantify. Based on the work observed (as shown by the inspector's IDRs and site photos) the Construction Manager felt the price submitted was appropriate. The fact that this was unexpected work was also considered in the acceptance of the price. 0 Page 1