HomeMy WebLinkAboutSierra Electric Change Order No 10 C2-11-16-STR Rd 68 Improvements Ph 2CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 10
Project No: C2-11-16-STR Project Title: Rd 68 Improvements, Ph 2
Contractor: Sierra Electric
Description of Change: Relocate irrigation main and valves on Burden Blvd.
Detail as Appropriate: See Attached
Contract Bid Amount: $ 1,201,687.00
SALES TAX @ 8.6%: N/A
Total: $ 1,201,687.00
PREVIOUS CHANGE ORDERS
CURRENT CHANGE ORDER
Subtotal $ (4,065.47)
Subtotal $ 4,122.00
Sales tax @ 8.6% N/A
Sales tax @ 8.6% N/A
Total $ (4,065.47)
Total $ 4,122.00
Total Change Orders To Date $ 56.53
New Contract Amount $ 1,201,743.53
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................. 163
Modification to Contract time by this Change Order .................... 5
revised Total Contract Time .................................................... 168
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:APPROVED: /
CONTRACTOR Date cANA ER at
APPROVED: APPROVED:
sig
CITYENGNWD6te PUBLIC WORKS Date
DIRECTOR
Memo
Public Works Department
Engineering Division
To: Mike Pawlak, P.E., City Engineer
CC: Kent McCue, Construction Manager
Rene Lopez, Construction Inspector
Brenda Timpany, Admin Assistant 1
From: Kate Thompson, P.E., Civil Engineer
Date: November 19, 2014
Re: Change Order#10, Road 68 Improvements Phase 2 and Interconnect Rd 68 Signals
Change Order No. 10 reflects the revisions to the Road 68 Improvements Phase 2 Project listed below. This
change order was requested by the City.
1) During construction of the revisions to the existing center medians on Burden Blvd the sub-
contractor ran into issues with the existing irrigation main and valves in several locations. This
required the sub -contractor to have to relocate irrigation main and valves. The contract documents
didn't include a provision for revision to the irrigation system beyond relocating existing sprinkler
heads. This required the subcontractor to need to obtain additional supplies and took more
manpower to complete the work.
The Following Table shows the costs associated with Change Order #10.
NO.
DESCRIPTION
UNIT
BID UNIT
QUANTITY
TOTAL
PRICE
1
1 Additional Irrigation S tem Repairs
LS
$4,122.00
1 1
$4,122.00
TOTAL CHANGE ORDER #10
1 $4,122.00
The total quantity of work completed was difficult to quantify. Based on the work observed (as shown by the
inspector's IDRs and site photos) the Construction Manager felt the price submitted was appropriate. The
fact that this was unexpected work was also considered in the acceptance of the price.
0 Page 1