HomeMy WebLinkAboutSierra Electric Change Order No 4 C2-11-16-STR Rd 68 Improvements Ph 2Project No:
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 4
C2-11-16-STR
Project Title: Rd 68 Improvements, Ph 2
Contractor: Sierra Electric
Description of Change: Curb Paining & Raised Pavement Markers
Detail as Appropriate:
See Attached
Contract Bid Amount:
SALES TAX @ 8.6%:
Total:
$ 1,201,687.00
N/A
$ 1,201,687.00
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 21,855.82
Subtotal $ 17,400.00
Sales tax @ 8.6% N/A
Sales tax @ 8.6% N/A
Total $ (21,855.82)
Total $ 17,400.00
Total Change Orders To Date
New Contract Amount $
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
(4,455.82)
1,197,231.18
NO
158
158
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND CCEPTED:
CONT. CTOR Date
APPROVED:
' " /t • l��IJL— Ilk CITY ENGINEER ENGINEER Date
APPROVED:
APPROVED:
UB IC t
DIRECTOR
Memo
Public Works Department
Engineering Division
To: Mike Pawlak, P.E., City Engineer
CC: Kent McCue, Construction Manager
Rene Lopez, Construction Inspector
Brenda Timpany, Admin Assistant 1
From: Kate Thompson, P.E., Civil Engineer
Date: October 22, 2014
Re: Change Order #4, Road 68 Improvements Phase 2 and Interconnect Rd 68 Signals
Change Order No. 4 reflects the revisions to the Road 68 Improvements Phase 2 Project listed below. This
change order was requested by the City.
1) The original design plans did not call for any markings to be placed on or adjacent to the center
median curbing on Rd 68 or Burden Blvd. Through the course of construction it has become clear
that some form of marking is needed in order to help make the curbing more visible to traffic to
prevent people from hitting them unnecessarily. In addition, the markings will help make it clearer
which turn pocket is to be used for each direction of traffic. We elected to have the curb itself painted
in order to make it more visible.
2) The issue of visibility of the new center curb median at night was also brought up during construction.
We have decided to add raised pavement markers (RPM's) to the new curbing to help make it more
visible at night and during rain storms.
3) The addition of the curb striping and RPM's will require additional traffic control for the installation.
The Following Table shows the costs associated with Change Order #4.
NO.
DESCRIPTION
UNIT
BID UNIT
PRICE
QUANTITY
TOTAL
1
Curb Painting
LS
$4,650.00
1
$4,650.00
2
Furnish/Install RPM's
LS
$5,950.00
1
$5,950.00
3
Additional Traffic Control
LS
$5,500.00
1
$5,500.00
4
Prime Contractor Overhead
LS
$1,300
1
$1,300.00
TOTAL CHANGE ORDER #4
$17,400.00
The contractor supplied a lump sum breakdown for items 1-3 shown above, see attached. This breakdown
was used to check the unit costs for each item. The Curb Painting unit price is $1.03/LF, this price was
compared to the 1 sand A Street Railroad Crossing project completed last year which had a unit price for
Curb Painting of $1.1 51F. This was found to be a reasonable price. The RPM's have a unit price of
$7.90/EA. We checked with our Operations Division and found that this price which includes installation is
just slightly higher than the per each cost for RPM'S not including installation. This was found to be a
reasonable price for this item.
0 Page 1