HomeMy WebLinkAboutInland Asphalt Co M3-OV-3R-14-01 2014 OverlaysCITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 4
Project No: M3 -OV -3R-14-01 Project Title: 2014 Overlays
Contractor: Inland Asphalt Co.
Description of Change: Quantity Adjustment for Final Reconciliation
Detail as Appropriate:
Contract Bid Amount: $ 599,599.99
SALES TAX @ 8.6%: N/A
Total: $ 599,599.99
PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER
Subtotal $ 33,374.00 Subtotal $ 3,882.71
Sales tax @ 8.6% N/A Sales tax @ 8.6% N/A
Total $ 33,374.00 Total $ 3,882,71
Total Change Orders To Date $ 37,256.71
New Contract Amount $ 636,856.70
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order... ..... _............_ 45
Modification to Contract time by this Change Order .................... 3
revised Total Contract Time... ...... . ................... . ................. . 48
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
�QO � l—\ e
CONTRALTO Date
APPROVED:
CI v ENGINf ER Date
PROJECT MANAGER Date
APPROVED:
(161
PUBL KS Dat
DIRECTOR