HomeMy WebLinkAboutAllStar Construction Group G1-ST-36-13-02 Change Order No 4CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 4
Project No: G1 -ST -36-13-02 Project Title: Court St ADA - 2012 Curb Ramps
Contractor: AIIStar Construction Group, Inc.
Description of Change: Misc. City Requested Changes
Detail as Appropriate: See Attached
Contract Bid Amount: $ 671,184.42
SALES TAX @ 8.6%: N/A
Total: $ 671,184.42
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 19,386.70
Subtotal $ 799.48
Sales tax @ 8.6% (CO #3) $ 32.84
Sales tax @ 8.6% N/A
Total $ 19,419.54
Total $ 799.48
Total Change Orders To Date $ 20,219.02
New Contract Amount $ 691,403.44
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
YES NO
60
0
60
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGRE D AND ACCEPTED:
11-7-14
CONT CTOR Date
APPROVED:
CL--Tr�/ 7(za� r F
CITY ENGINEER1NEER Date /
PROVED: ll
PROJECT MANAGER Date
4
Memo 1-' '.l
Engineering
TO: Mike Pawlak, City Engineer
FROM: David Tanner, Senior Civil Engineer
DATE: November 3, 2014
RE: Court Street ADA Project- Change Order 4
Misc. City Requested Changes
Please review and approve the attached change order, and supporting documentation
for Misc. City Requested Changes for the amount of 799.48 plus applicable tax. See
below for an itemized list of the approved changes:
NW 14th & Court — Replace existing catch basin ring and cover to accommodate
new ADA ramp
SW 14th & Court — Replace existing catch basin ring and cover to accommodate
new ADA ramp
NW 22nd & Court — Grout two pole bases to accommodate new ADA ramp.