HomeMy WebLinkAboutAllStar Construction Group G1-ST-36-13-02 Change Order No 2CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 2
Project No: G1 -ST -36-13-02 Project Title: Court St ADA - 2012 Curb Ramps
Contractor: AIIStar Construction Group, Inc.
Description of Change: Left Turn Arrows at 4 locations
Detail as Appropriate: 4 left turn arrows required at 22nd & Court (EB & WB), 14th & Court
SALES TAX @ 8.6%:
Total:
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 18,108.80
Subtotal $ 896.00
Sales tax @ 8.6% N/A
Sales tax @ 8.6% N/A
Total $ 18,108.80
Total 896.00
Total Change Orders To Date $ 19,004.80
New Contract Amount $ 690,189.22
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ....................................................
YES NO
42
42
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED T uD ACCEPTED:
11-7-14
CONTRACTO Date
t:- byl..ti-(Pt %r /7 �/�i--
CITYENGINE R Date f
A,
PR JECT MANAGER Date
Rene Lopez
From:
Kent McCue
Sent:
Thursday, May 08, 2014 9:47 AM
To:
Rene Lopez
Subject:
RE: 4 LT turn arrows court street ADA
Approved.........
Kent McCue, Construction Manager
City of Pasco
525 North Third Avenue
Pasco, WA. 99301
O 509-545-3444
F 509-543-5728
C 509-521-0272
From: Rene Lopez
Sent: Thursday, May 08, 2014 7:11 AM
To: Kent McCue
Subject: FW: 4 LT turn arrows court street ADA
FYI
From: Bruce Emory (mailto:allstrinc(d)frontier.com]
Sent: Wednesday, May 07, 2014 2:45 PM
To: Rene Lopez
Subject: Fwd: 4 LT turn arrows court street ADA
Hi Rene, costing for arrows below $ 200.00 ea plus 12% OH&P or $224.00 ea, let me know if you want to proceed
thanks, Bruce
2.Znr% Av'k �- Co.ar-� 5�, 1 ecsi 6,,,.,� 1 uc.ed 6al,�•
-------- Original Message -------- ti4\ AJe .1- S; j� t k to 6o ^,�)
Subject:4 LT turn arrows
Date:Wed, 7 May 2014 21:06:39 +0000
�rJ��
From:Frank Artz <Frank@striperite.com>
To:allstrinc(a)frontier.com <allstrinc@frontier.com>
CC:Rene Lopez <LOPEZR@pasco-wa.eov>
Hi guys, it looks like the Court Street ADA Crosswalk Upgrade project will require 4 each left turn arrows per Ramon and
Rene. This is a special order I don't have in stock and will require mobbing back out and getting it done. We are at $ 200
dollars each to supply and install and will need approval via e-mail from Kent to proceed on the order. Thanks Guys!
FRANK ARTZ
Division Manager
TRIPE RETE
Inc.