HomeMy WebLinkAboutSierra Electric Change Order No 2 C2-11-16-STR Rd 68 Improvements Ph 2CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 2
Project No: C2-11-16-STR Project Title: Rd 68 Improvements, Ph 2
Contractor: Sierra Electric
Description of Change: Contract Time Adjustment
8
Detail as Appropriate: No cost change order adding working days to the contract for a total
of 1 working days. Completion date of October 24, 2014.
�e3
Contract Bid Amount: $ 1,201,687.00
SALES TAX @ 8.6%: N/A
Total: $ 1,201,687.00
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 20,240.00
Subtotal
Sales tax @ 8.6% N/A
Sales tax @ 8.6% N/A
Total $ (20,240.00)
Total $
Total Change Orders To Date $ (20,240.00)
New Contract Amount $ 1,181,447.00
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ................................. 130
Modification to Contract time by this Change Order ....................
revised Total Contract Time .................................................... —�g58 Icor 8
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
I -o
CONT N
CTOR Date
APPR
CITY ENGINEER Da e
APPROVED:
APPROVED:
BLI WO Da
DIRECTOR
o) L1 9 )
Memo
Public Works Department
Engineering Division
To: Mike Pawlak, P.E., City Engineer
CC: Kent McCue, Construction Manager
Rene Lopez, Construction Inspector
Brenda Timpany, Admin Assistant 1
From: Kate Thompson, P.E., Civil Engineer
Date: September 15, 2014
Re: Change Order #2, Road 68 Improvements Phase 2 and Interconnect Rd 68 Signals
Change Order No. 2 reflects the revisions to the Road 68 Improvements Phase 2 Project and Interconnect Rd
68 Signals listed below. This change order was requested by the Contractor.
1) The contract documents originally included 40 working days for the ordering and delivery of all the
signal and illumination equipment necessary for the project. Originally, the signal equipment was
scheduled to arrive on or about June 16, 2014. Due to issues beyond the contractor's control
(manufacturing and material availability) the actual date of arrival for the signal equipment was
August 19, 2014. This was 42 working days later than originally scheduled. Per Section 1-08.3 of
the project special provisions all work pertaining to the signal system, including pre-emption and
interconnect on Rd 68 must be installed, tested, accepted and operational prior to commencing any
civil work on Rd 68 in order to not impede or restrict emergency response. Due to the last delivery of
the signal items, the contractor was not able to begin the signal work until August 201h, 2014 (the day
after the arrival of the material) and was able to complete the necessary signal work by September 9,
2014. The installation took 7 less days than anticipated. Since they had to have the signal system
operational prior to beginning the civil work on Rd 68, they were not able to begin the construction of
the concrete curb medians along Rd 68 until September 10, 2014.
In addition to the delay form the late arrival of the signal equipment the City requested that the
concrete median down Rd 68 be constructed in three segments. The City requested this change in
the construction to reduce the traffic impacts to the public due to the installation of the medians. This
requirement will make the median installation take longer than originally anticipated. Due to this it is
not possible for the contractor to complete the project within the 130 Working Days per the contract
documents. The contractor is requesting an additional 2Kworking days be added to the contract.
"IF tq
This change order will add Nor�g days to the contract for a total of Conking Days. There is no cost
associated with this change order. The additional days puts the new completion date on October 24, 2014.
0 Page 1
S ER.RA
ELECTRIC, INC.
September 11, 2014
City of Pasco
PO Box 293
•s
Pasco, WA 99301 -�
Attention: Katherine Thompson..
Re: Road 68 Improvements Phase 2 (Request for Additional Time)
Katherine:
As you know the project completion date is September 16th. At this point, I am requesting additional
time due to the late arrival of the required equipment. The contract required us to complete the
Opticom installation before beginning any of the work on road 68 which also meant we had to have the
cabinet changes made as well. The equipment required to complete this work was originally scheduled
to arrive on or about June 161h at which time we were scheduled to begin. The actual date of arrival was
on August 19`h due to various reasons with the manufacturing process and material availability. This is
42 days later than scheduled. We began the installation the very next day on the 20" and completed
the required work on September 91h. As it turns out this is 7 days quicker than we had originally
anticipated. This made up a very small portion of the time we have lost. There is no physical way for us
to complete the project by the 16th of September. I am not requesting the entire 42 days to be added to
our contract, however, I am requesting the 28 days that we had originally scheduled for the Road 68
work, plus 5 days for the time we will lose by splitting that work into 3 sections as we discussed, to limit
the congestion for the traveling public. This puts the completion date at October 241h, 2014. We
appreciate your consideration in this matter and will, of course do everything we can to shorten the
requested completion date. .`.
Sincerely,
Mitch Murphy
President