CONTRACT CHANGE ORDER NO. 2
Project No: M3- OV- 3R -14 -01 Project Title: 2014 Overlays
Contractor: Inland Asphalt Co.
Description of Change: Additional pavement striping on Broadmoor South of Sandifur
Detail as Appropriate: Additional striping was required on Broadmoor south of Sandifur as the limits
was
Contract Bid Amount: $ 599,599.99
SALES TAX @ 8.6 %: N/A
Total: $ 599,599.99
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $ 21,586.00
Subtotal $ 868.00
Sales tax @ 8.6% N/A
Sales tax @ 8.6% N/A
Total $ 21,586.00
Total $ 868.00
Total Change Orders To Date $ 22,454.00
New Contract Amount
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .. ...............................
Modification to Contract time by this Change Order ....................
revised Total Contract Time ..................... ...............................
$ 622,053.99
YES NO
44
1
45
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED: APPROVED: