HomeMy WebLinkAboutBig D's Construction Change Order No. 1 C7-SR-1A-13-02 PWRF Phase 3 Pond GradingCITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 1
Project No: C7- SR- 1A -13 -02 Project Title: PWRF Ph 3 - Pond Grading
Contractor: Big D's Construction
Description of Change: Purchase and install PVC liner for the 8MG and Equalization Pond
Detail as Appropriate: All equipment, material and labor to install liner.
Contract Bid Amount: $ 392,360.00
SALES TAX @ 8 %: $ 31,388.80
Total: $ 423,748.80
Total Change Orders To Date $ 213,713.42
New Contract Amount $ 637,462.22
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ......................... .... 40
Modification to Contract time by this Change Order ............... .. 10
revised Total Contract Time ................ .. ........ ..................... 50
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
CONTRACTOR Date^
APPROVED'
Cj y It
CifY ENGI ER Date
APPROVED:
PROJECT MANAGER Date
APPROV
Y /q liq
PUBLIC Date
DIRECTOR
as0Y
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal
Sales tax @ 8% $
Total $
Subtotal $ 197,882.80
Sales tax @ 8% $ 15,830.62
Total $ 213,713.42
Total Change Orders To Date $ 213,713.42
New Contract Amount $ 637,462.22
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO
Contract Time Prior to this Change Order ......................... .... 40
Modification to Contract time by this Change Order ............... .. 10
revised Total Contract Time ................ .. ........ ..................... 50
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being
made and that the compensation for this Change Order is full and complete and is the only compensation
due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the
present Contract Documents and that the provisions of the previously executed Contract Documents shall
apply to this Change Order.
AGREED TO AND ACCEPTED:
CONTRACTOR Date^
APPROVED'
Cj y It
CifY ENGI ER Date
APPROVED:
PROJECT MANAGER Date
APPROV
Y /q liq
PUBLIC Date
DIRECTOR
as0Y