HomeMy WebLinkAbout3554 ResolutionRESOLUTION NO. 355-'4
A RESOLUTION ACCEPTING WORK PERFORMED BY PREMIER
EXCAVATION, INC. UNDER CONTRACT FOR THE HERITAGE INDUSTRIAL CENTER
PRIMARY LEAD TRACK, PHASE 2 PROJECT AND THE BIG PASCO INDUSTRIAL
CENTER HUB DEVELOPMENT, PHASE 5B PROJECT.
WHEREAS, the work performed by Premier Excavation, Inc., under contract for the
Heritage Industrial Center Primary Lead Track, Phase 2 Project and the Big Pasco Industrial
Center Hub Development, Phase 5b project has been examined by Engineering and has been
found to be in apparent compliance with the applicable project specifications and drawings, and
WHEREAS, it is Engineering recommendation that the City of Pasco formally accept the
contractor's work and the project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO, that the
City Council concurs with Engineering recommendation and thereby accepts the work performed
by Premier Excavation, Inc., under contract for the Heritage Industrial Center Primary Lead
Track, Phase 2 Project and the Big Pasco Industrial Center Hub Development, Phase 5b project,
as being completed in apparent conformance with the project specifications and drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington
State Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 2nd day of June, 2014.
Matt Watkins
Mayor
ATTEST: APPROVED AS TO FORM:
Debra L. Clark Leland B. Kerr
City Clerk City Attorney