Loading...
HomeMy WebLinkAboutGranite Construction - Change Order No 6 C5-ST-3R-12-02CITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 6 Project No: C5- ST- 3R -12 -02 Project Title: 2012 Overlays and 4th Ave Corridor North C2- 10- 06 -STR Contractor: Granite Construction, Inc. Description of Change: Payment for water supplied by City of Pasco - Hydrant Meter Detail as Appropriate: Water supplied for work done on Contract Bid Amount: $ 1,682,602.96 SALES TAX @ 8.6 %: $ Total: $ 1,682,602.96 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal $ 292,504.54 Subtotal $ 669.60 Sales tax @ 8.6% N/A Sales tax @ 8.6% N/A Total $ 292,504.54 Total $ 669.60 Total Change Orders To Date $ 293,174.14 Contract Adjustment (CO #5) $ (138,235.00) New Contract Amount $ 1,837,542.10 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER YES NO Contract Time Prior to this Change Order .. ............................... 86 Modification to Contract time by this Change Order .................... 0 revised Total Contract Time ..................... ............................... 86 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED. APPROVED: / O TRACTO Date JECT MANAGED D� APPROVED- CITY ENGINEER Date AP'PR VED: P J K Dat6 / DIRECTOR Memo Public Works Department Engineering Division To: Mike Pawlak, P.E., City Engineer CC: Kent McCue, Construction Manager Water Usage Will McNeal, Construction Inspector 2 Brenda Timpany, Admin Assistant 1 From: Kate Thompson, P.E., Associate Engineer 1 Date: January 2, 2014 Re: Change Order #16 2012 Overlays & 0 Avenue Corridor Change Order No. 6 reflects the revisions to the 0 Avenue Corridor and 2012 Overlays Projects listed below. After the projects were awarded there was a change in City policy regarding the billing of water meters used for dust control on City projects. Due to this the contractor began receiving bills for the water used on the project. This was not accounted for in any of the bid items for either project. The contractor used a single water meter for dust control on both projects. Since only one meter was utilized the costs will be split between the two projects. Total cost for the change order is estimated and may increase. This change order will allow for the contractor to be reimbursed for the cost of the bills from the City of Pasco for water usage plus 15% markup to cover the contractor's internal processing costs. The table below lists the estimated changes and costs associated with this change order for the 41h Avenue Corridor Project. NUMBER ITEM ESIMATED COST 1 Water Usage $291.39 2 15% Mark U $43.71 TOTAL $334.80 The table below lists the estimated changes and costs associated with this change order for the 2012 Overlays Project. NUMBER ITEM ESIMATED COST 1 Water Usage $291.39 2 15% Mark U $43.71 TOTAL $334.80 This brings the total increase to the contract $669.60. The estimated cost is based on the City of Pasco Water Bill dated 12/26/2013. This bill has been attached as a reference. • Page 1 n << Prev Bill Billing Address GRANITE CONSTRUCTION PO BOX 2738 PASCO, WA 99302 12/2612013 • Service Address FIRE HYDRANT PASCO WA 99301 Pay this Bill » Description Prev. Read Curr. Read Usage A PENALTY: 998 - 14500.07 $10. WATER -COMM 1 INCH: 1545810 1552595 67 $92.05 Total Services: $102.05 a City of Pasco 525 N 3rd Ave Pasco, WA 99301 509 -545 -3488 utilities @pasco - wa.gov Monday - Friday 8:00 AM - 5:00 PM Account Information Billing Date: 12/26/2013 Account #: 998 - 14500.07 Date Due: 0111512014 Statement Amount Due: $592.78 Balance Detail Previous Balance: $490.73 Past Due Balance: $490.73 Total Current Charges: $102.05 Total Due: $592.78 URGENT NOTICE! Our records indicate this utility bill co sins past due charges. Possi smatter has escaped your attention or payment was lost in the mail. If pa ent for past due char penalties, and fees is not received online by 10:00 p.m. on 07/0612014, then water rvice may be st e without further notice. Have your bill paid automatics ea month with Xpress Bill Pay's hassle -free Auto Pay feature. eNYOYiG.t�`ICVC�t'Yl