HomeMy WebLinkAbout3520 ResolutionRESOLUTION NO. �7(-)
A RESOLUTION ACCEPTING WORK PERFORMED BY MICHELS
CORPORATION UNDER CONTRACT FOR THE 2013 SEWER RE- LINING PROJECT,
PROJECT NOS. C7- SE- 2R -13 -03 AND C7- SE- 24- 12 -20.
WHEREAS, the work performed by Michels Corporation under contract for the 2013
Sewer Re- Lining Project, Project Nos. C7- SE- 2R -13 -03 and C7- SE- 2R- 12 -20, has been
examined by the Public Works Operations Division and has been found to be in apparent
compliance with the applicable project specifications and drawings, and
WHEREAS, it is Public Works Operations Division recommendation that the City of
Pasco formally accept the contractor's work and the project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO, that the
City Council concurs with Public Works Operations Division recommendation and thereby
accepts the work performed by Michels Corporation under contract for the 2013 Sewer Re-
Lining Project, Project Nos. C7- SE- 2R -13 -03 and C7- SE- 2R- 12 -20, as being completed in
apparent conformance with the project specifications and drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington
State Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 4th day of November 2013.
Matt Watkins
Mayor
ATTEST:
ra L. C ar
City Clerk
APPROVED AS TO FORM:
Leland B. Kerr
City Attorney