HomeMy WebLinkAbout3198 Resolution RESOLUTION NO. -�
A RESOLUTION ACCEPTLNG WORK PERFORMED BY MAHAFFEY
ENTERPRISES, INC., UNDER CONTRACT FOR THE 2009 SEWER LINE EXTENSION -
WHIPPLE AVENUE,PROJECT 909-1-02.
WHEREAS, the work performed by MAHAFFEY ENTERPRISES,INC., under contract
for the 2009 Sewer Line Extension-Whipple Avenue, Project #09-1-02, has been examined by
Engineering and has been found to be in apparent compliance with the applicable project
specifications and drawings,and
WHEREAS, it is Engineering recommendation that the City of Pasco formally accept the
contractor's work and the project as complete: NOW,THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO,that the
City Council concurs with Engineering recommendation and thereby accepts the work performed
by Mahaffey Enterprises, Inc., under contract for the 2009 Sewer Line Extension - Whipple
Avenue, Project #09-1-02, as being completed in apparent conformance with the project
specifications and drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington
State Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being xNithheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 16th day of November, 2009.
Jov Ols
Ma &
ATTEST: APPROVED AS TO FORM:
Debra L. Clark, CMC Leland B. Ken-
City Clerk City Attorney