HomeMy WebLinkAbout3186 Resolution RESOLUTION NO. 41 Z
A RESOLUTION ACCEPTING WORK PERFORMED BY VALMONT
NORTHWEST UNDER CONTRACT FOR THE PROCESS WATER REUSE FACILITY
IRRIGATION PIVOT, PROJECT#09-7-02.
WHEREAS, the work performed by VALMONT NORTHWEST, under contract for the
Process Water Reuse Facility Irrigation Pivot, Project #09-7-02, has been examined by
Engineering and has been found to be in apparent compliance with the applicable project
specifications and drawings, and
WHEREAS, it is Engineering recommendation that the City of Pasco formally accept the
contractor's work and the project as complete; NOW,THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO,that the
City Council concurs with Engineering's recommendation and thereby accepts the work
performed by Valmont Northwest, under contract for the Process Water Reuse Facility Irrigation
Pivot, Project #09-7-02, as being completed in apparent conformance with the project
specifications and drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington
State Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 8th day of September, 2009.
Joyc is