HomeMy WebLinkAbout3164 Resolution RESOLUTION NO.
A RESOLUTION ACCEPTING WORK BY PATIO COVERS
UNLIMITED, UNDER CONTRACT FOR THE BASEBALL STADIUM
PATIO AREA IMPROVEMENTS PROJECT.
WHEREAS, the work performed by Patio Covers Unlimited under
contract for the Baseball Stadium Patio Area Improvements Project has been
examined by Administrative and Community Services and been found to be in
apparent compliance with the applicable project specifications and drawings,
and
WHEREAS, it is Administrative and Community Services'
recommendation that the City of Pasco formally accept the contractor's work
and the project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO:
That the City Council concurs with Administrative and Community
Services' recommendation and thereby accepts the work performed by Patio
Covers Unlimited under contract for the Baseball Stadium Patio Area
Improvements Project as being completed in apparent conformance with the
project specifications and drawings, and
Be it further resolved that the City Clerk is hereby directed to notify the
Washington State Department of Revenue of this acceptance, and
Be it further resolved that the final payment of retainage being withheld
pursuant to applicable laws, regulations and administrative determination
shall be released upon satisfaction of same and verification thereof by the
Administrative and Community Services Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 15th day of June,
2009.
(ym.LG aj4zv,�
Joyce s , Mayor
ATTEST: APPROVED AS TO FORM:
De ra Clark, City Cler Leland B. Kerr, City Attorney