HomeMy WebLinkAbout3122 Resolution RESOLUTION NO. 3\0
A RESOLUTION ACCEPTING WORK PERFORMED BY A&B ASPHALT, INC. UNDER
CONTRACT FOR THE SACAGAWEA HERITAGE TRAIL PHASE 2,PROJECT#06-6-02.
WHEREAS, the work performed by A&B ASPHATL, INC., under contract for the
Sacagawea Heritage Trail Phase 2, Project #06-6-02, has been examined by Engineering and has been
found to be in apparent compliance with the applicable project specifications and drawings, and
WHEREAS, it is Engineering recommendation that the City of Pasco formally accept the
contractor's work and the project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO, that the City
Council concurs with Engineering recommendation and thereby accepts the work performed by A&B
ASPHALT, INC., under contract for the Sacagawea Heritage Trail Phase 2, Project #06-6-02, as
being completed in apparent conformance with the project specifications and drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington State
Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction of
same and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 1 st day of December, 2008.
�f—lc�c� inS
Mayor CR3 +.e Y11\,
ATTEST: APPROVED AS TO FORM:
Sandy L. worthy Leland B. Kerr
Deputy City Clerk City Attorney