HomeMy WebLinkAbout3087 Resolution RESOLUTION NO.
A RESOLUTION ACCEPTING WORK PERFORMED BY GOODMAN &
MEHLENBACHER, INC. UNDER CONTRACT FOR THE 2007 WEST PASCO SEWER
EXTENSION-PHASE I, PROJECT#07-1-01.
WHEREAS, the work performed by GOODMAN & MEHLENBACHER, INC., under
contract for the 2007 West Pasco Sewer Extension-Phase I, Project #07-1-01, has been
examined by Engineering and has been found to be in apparent compliance with the applicable
project specifications and drawings, and
WHEREAS, it is Engineering recommendation that the City of Pasco formally accept the
contractor's work and the project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO, that the
City Council concurs with Engineering recommendation and thereby accepts the work performed
by GOODMAN & MEHLENBACHER, INC., under contract for the 2007 West Pasco Sewer
Extension-Phase I, Project #07-1-01, as being completed in apparent conformance with the
project specifications and drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington
State Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 7th day of July, 2008.
eov ci,
Joyc is
May
ATTEST: APPROVED AS TO FORM:
Sandy L. nworthy Leland B. Kerr