HomeMy WebLinkAbout3028 Resolution RESOLUTION NO. 30,)-g
A RESOLUTION ACCEPTING WORK PERFORMED BY APOLLO, INC., UNDER
CONTRACT FOR THE PRIMARY DIGESTER FACILITIES PROJECT#05-1-09
WHEREAS, the work performed by Apollo, Inc., under contract for the Primary Digester
Facilities Project #05-1-09, has been examined by Engineering and has been found to be in
apparent compliance with the applicable project specifications and drawings, and
WHEREAS, it is Engineering recommendation that the City of Pasco formally
accept the contractor's work and the project as complete; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO, that the
City Council concurs with Engineering recommendation and thereby accepts the work performed
by Apollo Inc., under contract for the Primary Digester Facilities Project #05-1-09, as being
completed in apparent conformance with the project specifications and drawings, and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington
State Department of Revenue of this acceptance, and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 4th day of June, 2007.
Joyc is
May
ATTEST: APPROVED AS TO FORM:
Sandy L. K=rvorthy Leland B. Kerr
Deputy City Clerk City Attorney