HomeMy WebLinkAbout3026 Resolution RESOLUTION NO. JO�
A RESOLUTION ACCEPTING WORK PERFORMED BY
SHARPE & PRESZLER, INC. UNDER CONTRACT FOR THE MAIN
AVENUE STORM WATER PHASE II PROJECT, PROJECT#07-8-01.
WHEREAS, the work performed by SHARPE & PRESZLER, INC., under contract
for the Main Avenue Storm Water Phase II Project, Project #07-8-01, has been examined by
the engineering division and has been found to be in apparent compliance with the
applicable project specifications and drawings, and
WHEREAS, it is the engineering division's recommendation that the City of Pasco
formally accept the contractor's work and the project as complete; NOW,THEREFORE,
THE CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, DO
RESOLVE AS FOLLOWS:
Section 1: That the City Council concurs with the engineering division's
recommendation and thereby accepts the work performed by Sharpe & Preszler, Inc. under
contract for the Main Avenue Storm Water Phase 11 Project, Project #07-8-01, as being
completed in apparent conformance with the project specifications and drawings, and
Section 2: That the City Clerk is hereby directed to notify the Washington State
Department of Revenue of this acceptance, and
Section 3: That the final payment of retainage being withheld pursuant to applicable
laws, regulations and administrative determination shall be released upon satisfaction of
same and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 21 st day of May, 2007.
<:�u U a4nt�