HomeMy WebLinkAbout3018 Resolution RESOLUTION NO. \�
A RESOLUTION ACCEPTING WORK PERFORMED BY INSITUFORM
TECHNOLOGIES, INC. UNDER CONTRACT FOR THE 2006 SEWER LINING PROJECT,
PROJECT # 06-1-04.
WHEREAS, the work performed by INSITUFORM TECHNOLOGIES, INC., under
contract for the 2006 Sewer Lining Project, Project #06-1-04, has been examined by the
engineering division and has been found to be in apparent compliance with the applicable project
specifications and drawings, and
WHEREAS, it is the engineering division's recommendation that the City of Pasco
formally accept the contractor's work and the project as complete; NOW, THEREFORE,
THE CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, DO
RESOLVE AS FOLLOWS:
Section 1: That the City Council concurs with the engineering division's
recommendation and thereby accepts the work performed by Insituform Technologies, Inc. under
contract for the 2006 Sewer Lining Project, Project #06-1-04, as being completed in apparent
conformance with the project specifications and drawings, and
Section 2: That the City Clerk is hereby directed to notify the Washington State
Department of Revenue of this acceptance, and
Section 3: That the final payment of retainage being withheld pursuant to applicable
laws, regulations and administrative determination shall be released upon satisfaction of same
and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 2nd day of April, 2007.
Joyc is
Ma
ATTEST: APP AS TO FORM:
Sandy L. K nworthy Leland B. Kerr
Deputy City Clerk City Attorney