HomeMy WebLinkAbout3011 Resolution RESOLUTION NO.3 3
A RESOLUTION ACCEPTING WORK PERFORMED BY SHARPE & PRESZLER,
INC. UNDER CONTRACT FOR THE ROAD A/C WATERLINE REPLACEMENT PROJECT,
PROJECT# 06-2-03.
WHEREAS, the work performed by SHARPE & PRESZLER, INC., under
contract for the A/C Waterline Replacement Project, Project #06-2-03, has been
examined by the engineering division and has been found to be in apparent compliance
with the applicable project specifications and drawings, and
WHEREAS, it is the engineering division's recommendation that the City of
Pasco formally accept the contractor's work and the project as complete; NOW,
THEREFORE,
THE CITY COUNCIL OF THE CITY OF PASCO, WASHINGTON, DO
RESOLVE AS FOLLOWS:
Section 1: That the City Council concurs with the engineering division's
recommendation and thereby accepts the work performed by Sharpe & Preszler, Inc. under
contract for the A/C Waterline Replacement Project, Project #06-2-03, as being completed in
apparent conformance with the project specifications and drawings, and
Section 2: That the City Clerk is hereby directed to notify the Washington State
Department of Revenue of this acceptance, and
Section 3: That the final payment of retainage being withheld pursuant to applicable laws,
regulations and administrative determination shall be released upon satisfaction of same and verification
thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 20th day of February,2007.
iOoe on
ATTEST: APPROVED AS TO FORM:
CcJ
Sandy L. Vriworthy Leland B. Kerr
Deputy City Clerk City Attorney