HomeMy WebLinkAbout2822 Resolution RESOLUTION NO. 2 ?,2-
A RESOLUTION ACCEPTING WORK PERFORMED BY SHOEMAKER
EXCAVATION, INC., UNDER CONTRACT FOR PROJECT NO. 03-3-02, 2003
MISCELLANEOUS STREET IMPROVEMENTS.
WHEREAS, the work performed by Shoemaker Excavation, Inc., under contract for Project
No. 03-3-02 has been examined by Engineering and Engineering has found that all work
required by the contract has been performed in apparent compliance with the applicable project
specifications and drawings, and
WHEREAS, it is Engineering's recommendation that the City of Pasco formally accept the
contractor's work and the project as complete,Now, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO:
That the City Council concurs with Engineering's recommendation and thereby accepts the
work performed by Shoemaker Excavation, Inc., under contract for Project No. 03-3-02 as being
completed in apparent conformance with the project specifications and drawings, and
Be it further resolved that the City Clerk is hereby directed to notify the Washington State
Department of Revenue of this acceptance, and
Be it further resolved that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 21" day of June 2004.
Michael L. Garrison
Mayor
ATTEST: APPROVED AS TO FORM:
Sandy L. orthy di JnAKWe rr
Deputy City Clerk City Attorney