HomeMy WebLinkAbout2743 Resolution RESOLUTION NO. 2743
A RESOLUTION ACCEPTING WORK PERFORMED BY
THOMPSON MECHANICAL, UNDER CONTRACT FOR PROJECT
NO. 01-2-14, RAW WATER INTAKE PUMP IMPROVEMENTS.
WHEREAS, the work performed by Thompson Mechanical, under
contract for Project No. 01-2-14 has been examined by Engineering and
Engineering has found that all work required by the contract has been
performed in apparent compliance with the applicable project specifications
and drawings, and
WHEREAS, it is Engineering's recommendation that the City of Pasco
formally accept the contractor's work and the project as complete; Now,
THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO:
That the City Council concurs with Engineering's recommendation and
thereby accepts the work performed by Thompson Mechanical, under contract
for Project No. 01-2-14 as being completed in apparent conformance with the
project specifications and drawings, and
Be it further resolved that the City Clerk is hereby directed to notify the
Washington State Department of Revenue of this acceptance, and
Be it further resolved that the final payment of retainage being withheld
pursuant to applicable laws, regulations and administrative determination
shall be released upon satisfaction of same and verification thereof by the
Public Works Director and Finance Manager.
PASSED by the City Council of the City of Pasco, Washington, and
approved as provided by law this 5th day of May, 2003.