HomeMy WebLinkAbout2561 Resolution RESOLUTION NO. 2561
A RESOLUTION accepting work by Uribe, Inc., under contract
for Project No. 00-2-06, Sycamore Waterline.
WHEREAS, the work performed by Uribe, Inc., under contract for Project
No. 00-2-06 has been examined by Engineering and Engineering has found that all
work required by the contract has been performed in apparent compliance with the
applicable project specifications and drawings, and
WHEREAS, it is Engineering's recommendation that the City of Pasco
formally accept the contractor's work and the project as complete, Now,
THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PASCO:
That the City Council concurs with Engineering's recommendation and
thereby accepts the work performed by Uribe, Inc., under contract for Project No.
00-2-06 as being completed in apparent conformance with the project specifications
and drawings, and
Be it further resolved that the City Clerk is hereby directed to notify the
Washington State Department of Revenue of this acceptance, and
Be it further resolved that the final payment of retainage being withheld
pursuant to applicable laws, regulations and administrative determination shall be
released upon satisfaction of same and verification thereof by the Public Works
Director and Finance Manager.
PASSED by the City Council of the City of Pasco this 4"' day of December,
2000.
Michael L. Jarrison, Mayor
ATTEST: APPROVED AS TO FORM:
i
Catherine D. Seaman, Deputy City Clerk Leland B. Kerr, City Attorney