RESOLUTION NO. 4747
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
APPROVES AUTHORIZING THE CITY MANAGER TO EXECUTE
AMENDMENT NO. 4 FOR THE PROFESSIONAL SERVICES AGREEMENT
WITH RH2 ENGINEERING, INC. FOR THE DESIGN OF THE PROCESS
WATER REUSE FACILITY (PWRF) IMPROVEMENT PHASE 4:
IRRIGATION SYSTEM FARM UPGRADES PROJECT.
WHEREAS, the City of Pasco (City) and RH2 Engineering, Inc., entered into a
Professional Service Agreement on May 9th, 2023, to provide Engineering services with respect
to the PWRF Improvements project; and
WHEREAS, the City and RH2 Engineering Inc., entered into Amendment No. 1 on
November 23, 2023, to additional professional design engineering services; and
WHEREAS, the City and RH2 Engineering Inc., entered into Amendment No. 2 on
September 17, 2025, to additional professional design engineering services, services during
construction, and additional time of performance; and
WHEREAS, the City and RH2 Engineering Inc., entered into Amendment No. 3 on
January 23, 2026, to additional professional design engineering services, services during
construction, and additional time of performance; and
WHEREAS, the City Council of the City of Pasco, Washington, has after due
consideration, determined that it is in the best interest of the City to enter into Amendment No. 4
with RH2 Engineering, Inc.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PASCO, WASHINGTON:
That the City Council of the City of Pasco approves the terms and conditions of
Amendment No. 4 between the City of Pasco and RH2 Engineering, Inc. as attached hereto and
incorporated herein as Exhibit A, and
Be It Further Resolved, that the City Manager of the City of Pasco, Washington, is
hereby authorized, empowered, and directed to execute said Amendment No. 4 on behalf of the
City of Pasco, and
Be It Further Resolved, that this resolution shall take effect immediately.
Resolution - PWRF PH 4 PSA Amendment No. 4 - 2
PASSED by the City Council of the City of Pasco, Washington, on this 1st day of June,
2026.
Charles Grimm
Mayor
ATTEST: APPROVED AS TO FORM:
_____________________________ ___________________________
Krystle Shanks Ogden Murphy Wallace, PLLC
Deputy City Clerk City Attorney
RH2 Engineering, Inc. – Amendment No. 4 to PSA
PWRF Irrigation System Improvements – Project No. 23465
Version 08.15.2025 Page 1
AMENDMENT NUMBER 4 to
PROFESSIONAL SERVICES AGREEMENT
PWRF Irrigation System Improvements
PROJECT: 23465
AGREEMENT NO. 23-014
WHEREAS, the City and RH2 Engineering, Inc. entered into a Professional Services
Agreement on 5/9/2023 to provide engineering services with respect to the PWRF Irrigation
System Improvements project.
WHEREAS, the City and RH2 Engineering, Inc. entered into an Amendment No. 1 to
provide additional engineering services on 11/27/2023.
WHEREAS, the City and RH2 Engineering, Inc. entered into an Amendment No. 2 to
provide additional engineering services on 9/17/2025.
WHEREAS, the City and RH2 Engineering, Inc. entered into an Amendment No. 3 to
provide additional engineering services on 1/23/2026.
NOW, THEREFORE, this agreement is amended to allow RH2 Engineering, Inc. to
provide additional professional engineering services, and additional services during construction,
as described in Exhibit A.
1. Scope of Work:
See Exhibit A.
2. Fee:
The compensation for the work is based on a Time and Materials Basis not to exceed
the amount of $54,303.00 for a total authorization amount of $956,589.00. See
Exhibit B for full breakdown.
3. Time of performance:
No Change. The time of performance for services will be complete for the project on or
before 12/31/2026.
DATED THIS DAY______________________________.
[date of execution]
CITY OF PASCO, WASHINGTON RH2 ENGINEERING, INC.
Harold L. Stewart II, City Manager Dan Mahlum, PE – Director
1
4/23/2026 4:11:43 PM \\corp.rh2.com\projects\Project\Data\PSC\23-0092\00 Contract\A-4\A-4_SOW_PWRF Irrigation System Improvements.docx
Scope of Work
Amendment No. 4
City of Pasco
PWRF Irrigation System Improvements
Additional Work
April 2026
Background
The City of Pasco (City) has requested additional support from RH2 Engineering, Inc., (RH2) for
coordination, permitting, environmental review, and construction-phase services associated with
the Circle 14 expansion. This includes coordinating with Lad Irrigation Company, Inc., (Lad) to refine
center pivot layouts and maximize acreage; engaging with Franklin County (County) Planning staff
and facilitating interagency coordination meetings to confirm permitting pathways; and preparing
and processing required permit applications, including land use, road approach, underground
plumbing, and commercial/industrial structure permits. Effort also includes development and
preparation of a State Environmental Policy Act (SEPA) Checklist, coordination with the City, and
responses to agency comments from the Washington State Department of Ecology (Ecology),
Washington Department of Fish and Wildlife (WDFW), and the County. In addition, RH2 and Valley
Science and Engineering, Inc., (Valley) have provided ongoing review of technical submittals and RH2
has participated in weekly construction meetings to support project delivery. These efforts extend
beyond the original scope of work and are necessary to advance the project through permitting and
construction.
Task 15 – Services During Construction (Limited)
Objective: Provide limited engineering services during construction to support the City. As the
engineer of record, coordinate with the City, its designated utilities, and special inspector to respond
to technical questions and issues. Services will include reviewing all technical submittals, responding
to requests for information (RFIs), performing on-site observations, and assisting with change
proposals and change orders.
Approach:
Coordinate with Lad on adjusting the center pivot location and lengths to accommodate the
new parcel and maximize acreage.
Coordinate with County Planning staff to review proposed project improvements and
establish the appropriate County permitting pathway. Schedule and facilitate one (1) virtual
meeting with City, County, and RH2 staff to discuss the improvements and anticipated
permitting process for the Circle 14 expansion.
EXHIBIT A
Resolution Exhibit A
City of Pasco Exhibit A
PWRF Irrigation System Improvements Scope of Work
Additional Work Amendment No. 4
2
4/23/2026 4:11:43 PM \\corp.rh2.com\projects\Project\Data\PSC\23-0092\00 Contract\A-4\A-4_SOW_PWRF Irrigation System Improvements.docx
Prepare and submit a general land use application, a road approach permit, an underground
plumbing permit, and commercial/industrial structure permits for the Circle 14 expansion to
the County.
Prepare SEPA Checklist for the Circle 14 expansion and provide a draft to the City for review
and comment. Finalize the SEPA Checklist with City comments and submit to the County for
SEPA determination and publication. Respond to SEPA comments from Ecology, WDFW, and
the County.
Review technical submittals for the project.
Attend weekly construction meetings with the City throughout the duration of construction.
Assumptions:
•Weekly construction meetings will be via Microsoft Teams or other virtual meeting platform.
•RH2 will not prepare any agendas for the weekly construction meetings.
•RH2 and Valley will increase submittal reviews from limited reviews to full technical submittal
reviews.
•It is anticipated that the City will be the lead inspector, lead construction contract
administration, and be responsible for day-to-day activities.
•RH2 is not responsible for site safety, or for determining means and methods, or directing the
contractor in their work.
RH2 Deliverables:
•General land use, road approach, underground plumbing, and commercial/industrial
structure permit applications.
•SEPA Checklist and agency responses.
•Applicable technical submittal and RFI responses in electronic PDF.
Project Schedule
RH2 is prepared to commence with the work upon written authorization from the City. The revised
project design is anticipated to be completed in December 2026. Construction is anticipated from
January 2026 through December 2026.
Resolution Exhibit A
Fee Estimate
Amendment No. 4
City of Pasco
PWRF Irrigation System Improvements
Apr-26
Description
Total
Hours Total RH2
Labor
Total Subconsultant Total Expense Total Cost
Task 15 Services During Construction (Limited)197 46,247$ 6,900$ 1,156$ 54,303$
Subtotal Title Tasks --$ -$ -$ -$
PROJECT TOTAL 197 46,247$ 6,900$ 1,156$ 54,303$
\\corp.rh2.com\projects\Project\Data\PSC\23-0092\00 Contract\A-4\A-4_FEE_PWRF Irrigation System Improvements 4/23/2026 4:08 PM
EXHIBIT B
Resolution Exhibit A
RATE LIST RATE UNIT
Professional I $179 $/hr
Professional II $196 $/hr
Professional III $217 $/hr
Professional IV $240 $/hr
Professional V $256 $/hr
Professional VI $274 $/hr
Professional VII $298 $/hr
Professional VIII $324 $/hr
Professional IX $328 $/hr
Technician I $138 $/hr
Technician II $152 $/hr
Technician III $172 $/hr
Technician IV $186 $/hr
Technician V $205 $/hr
Technician VI $224 $/hr
Technician VII $243 $/hr
Technician VIII $254 $/hr
Administrative I $93 $/hr
Administrative II $108 $/hr
Administrative III $127 $/hr
Administrative IV $151 $/hr
Administrative V $178 $/hr
CAD/GIS System $27.50 $/hr
CAD Plots - Half Size $2.50 price per plot
CAD Plots - Full Size $10.00 price per plot
CAD Plots - Large $25.00 price per plot
Copies (bw) 8.5" X 11"$0.09 price per copy
Copies (bw) 8.5" X 14"$0.14 price per copy
Copies (bw) 11" X 17"$0.20 price per copy
Copies (color) 8.5" X 11"$0.90 price per copy
Copies (color) 8.5" X 14"$1.20 price per copy
Copies (color) 11" X 17"$2.00 price per copy
Technology Charge 2.50%% of Direct Labor
Night Work 10.00%% of Direct Labor
Mileage $0.7250
price per mile
(or Current IRS Rate)
Subconsultants 15%Cost +
Outside Services at cost
RH2 ENGINEERING, INC.
2026 SCHEDULE OF RATES AND CHARGES
Rates listed are adjusted annually.
Resolution Exhibit A