RESOLUTION NO. 4740
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING THE CITY MANAGER TO EXECUTE AMENDMENT 1 TO
THE PROFESSIONAL SERVICES AGREEMENT WITH RH2 ENGINEERING
INC. FOR THE MAITLAND LIFT STATION AND 9TH & WASHINGTON LIFT
STATION IMPROVEMENT PROJECTS.
WHEREAS, the City of Pasco (City) entered a Professional Services, Hourly Fee
Consultant Agreement approved by the City Manager on September 29th, 2025, to provide a
technical memorandum that summarized the condition of both the Maitland Sewer Lift Station and
the 9th & Washington Sewer Lift Station; and
WHEREAS, an amendment has been proposed to the project to complete design and to
add services during bidding and construction after staff review of the condition assessment
provided from the original PSA; and
WHEREAS, the City Council of the City of Pasco, Washington, has after due
consideration, determined that it is in the best interest of the City of Pasco to enter into Amendment
1 with RH2 Engineering, Inc. for providing an additional $294,419 for Design and Construction
Management Support Services for said projects_.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF PASCO, WASHINGTON:
That the City Council of the City of Pasco approves the terms and conditions of the PSA
Amendment 1 between the City of Pasco and RH2 Engineering, Inc. as attached hereto and
incorporated herein as Exhibit A.
Be It Further Resolved, that the City Manager of the City of Pasco, Washington, is hereby
authorized, empowered, and directed to execute said PSA Amendment 1on behalf of the City of
Pasco.
Be It Further Resolved, that this Resolution shall take effect immediately.
Resolution – Amend. 1 Maitland Lift Station and 9th & Washington Improvements - 2
PASSED by the City Council of the City of Pasco, Washington, on this 4th day of May,
2026.
Charles Grimm
Mayor
ATTEST: APPROVED AS TO FORM:
_____________________________ ___________________________
Krystle Shanks Ogden Murphy Wallace, PLLC
Deputy City Clerk City Attorney
1
3/23/2026 1:18:01 PM J:\Data\PSC\00-BusDev\2026 Maitland Lift Station and 9th and Washington Lift Station Improvements\PSA_SOW_Maitland LS and 9th & WA LS Improvements
PH2.docx
EXHIBIT A
Scope of Work
City of Pasco
Maitland Lift Station and 9th & Washington Lift Station Improvements
Phase 2
March 2026
Background
The City of Pasco’s (City) Maitland Lift Station and 9th & Washington Lift Station pump all wastewater
from the collection system to the City-owned wastewater treatment plant. Both of these lift stations
are critical to the City’s wastewater system, and both facilities support significant portions of the
City’s service area. The City retained RH2 Engineering, Inc., (RH2) in 2025 to perform a condition
assessment of the wet wells and to prioritize the design and construction of improvements at each
facility.
This Scope of Work is for Phase 2 of this project, which includes bid-ready design, services during
bidding, and services during construction.
General Assumptions
The following assumptions were made when preparing this Scope of Work:
• RH2 will rely upon the accuracy and completeness of information, data, and materials
generated or produced by the City or others in relation to this Scope of Work. RH2 assumes
that the entity providing such information to RH2 is either the owner of such information or
has obtained written authorization from the owner to distribute said information.
• Deliverables will be submitted in electronic format (PDF) unless otherwise noted.
• The proposed improvements include equipment replacements or connections to existing
infrastructure that can be field fit by a contractor. A survey is not anticipated to be necessary
to adequately design the proposed improvements.
• A single set of plans and specifications will be prepared that includes the improvements for
both the Maitland Lift Station site and the 9th & Washington Lift Station site. The Engineer’s
opinion of probable construction cost (OPCC) and schedule of values will include a separate
bid schedule for each site. The improvements at each site are shown as separate tasks in this
agreement for contractor bidding and City budgetary tracking purposes.
• Meetings will take place at Pasco City Hall, and RH2 will prepare and transmit meeting
agendas and minutes unless otherwise noted. Review meetings for the Maitland LS and 9th
and Washington LS will be combined into single meetings for each review milestone.
City of Pasco Exhibit A
Maitland Lift Station and 9th & Washington Lift Station Improvements – Phase 2 Scope of Work
2
3/23/2026 1:18:01 PM J:\Data\PSC\00-BusDev\2026 Maitland Lift Station and 9th and Washington Lift Station Improvements\PSA_SOW_Maitland LS and 9th & WA LS Improvements
PH2.docx
Phase 2 – Bid-Ready Design, Services During Bidding, and Services During
Construction
Task 1 – Maitland Lift Station Improvements
Objective: Design improvements at the Maitland Lift Station site consistent with the list of
improvements presented at the March 12, 2026, meeting between the City and RH2, including the
following:
• Replace the isolation and check valves in the dry pit.
• Add a new Pump No. 4 and motor.
• Install a force main bypass tap and access structure.
• Replace the flow meter.
• Replace the pump packing water supply line between the pumps and the reduced pressure
backflow assembly hotbox.
Approach:
Attend one (1) site visit with City staff.
Prepare an existing site and utility plan with available topographic and utility information,
including information included on the facility record drawings (previously provided to RH2).
Prepare a proposed site and utility plan identifying the proposed site and mechanical
improvements.
Model the downstream force main to confirm the proposed design point of the proposed
Pump No. 4.
Prepare a detail for the proposed mechanical improvements within the dry pit.
Prepare electrical engineering plans related to the installation of the proposed Pump No. 4.
Prepare plan set cover, general notes, mechanical details, and related plan sheets as
applicable.
Prepare 60-percent design plans and an OPCC for City review. Attend one (1) meeting with
the City to review the 60-percent deliverables. Prepare meeting agenda and minutes.
Prepare technical specifications in RH2’s standard format and front-end bidding documents
using the City’s standard forms.
Incorporate the City’s 60-percent review comments into the design plans. Prepare 90-percent
design plans, specifications, and OPCC for City review. Attend one (1) meeting with the City
to review the 90-percent deliverables. Prepare meeting agenda and minutes.
Incorporate the City’s 90-percent review comments and prepare bid-ready plans, front-end
documents, technical specifications, and OPCC.
City of Pasco Exhibit A
Maitland Lift Station and 9th & Washington Lift Station Improvements – Phase 2 Scope of Work
3
3/23/2026 1:18:01 PM J:\Data\PSC\00-BusDev\2026 Maitland Lift Station and 9th and Washington Lift Station Improvements\PSA_SOW_Maitland LS and 9th & WA LS Improvements
PH2.docx
Provide direction and coordination to the RH2 project team. Coordinate technical disciplines
as described herein and implement quality assurance and quality control (QA/QC) reviews.
Provide project management services, including RH2 staffing, invoice review, budget tracking,
and file management. Provide monthly status updates. Coordinate with City staff regarding
schedule and progress.
Assumptions:
• No permits will be needed for the improvements.
• It is assumed that the City’s current hydraulic sewer model is in RH2’s possession.
Provided by City:
• Attendance at one (1) site visit.
• 60-percent review comments and attendance at one (1) review meeting.
• 90-percent review comments and attendance at one (1) review meeting.
RH2 Deliverables:
• Attendance at one (1) site visit.
• 60-percent design plans and OPCC.
• Attendance at 60-percent design review meeting and meeting agenda and minutes.
• 90-percent design plans, specifications, and OPCC.
• Attendance at 90-percent design review meeting and meeting agenda and minutes.
• Bid-ready plans, specifications, and OPCC.
• Monthly invoices.
Task 2 – 9th & Washington Lift Station Improvements
Objective: Design improvements at the 9th & Washington Lift Station site consistent with the list of
improvements presented at the March 12, 2026, meeting between the City and RH2, including the
following:
• Improve the concrete wet well liner per Alternative No. 3 of the Condition Assessment
Technical Memorandum (February 26, 2026) prepared by RH2.
• Replace Pump No. 3, motor, variable frequency drive, and mechanical spools.
• Install a force main bypass access structure.
• Install lateral bracing for four (4) pump discharge pipes.
• Rehabilitate the concrete support for Pumps Nos. 1 and 4.
City of Pasco Exhibit A
Maitland Lift Station and 9th & Washington Lift Station Improvements – Phase 2 Scope of Work
4
3/23/2026 1:18:01 PM J:\Data\PSC\00-BusDev\2026 Maitland Lift Station and 9th and Washington Lift Station Improvements\PSA_SOW_Maitland LS and 9th & WA LS Improvements
PH2.docx
Approach:
Attend one (1) site visit with City staff.
Prepare an existing site and utility plan with available topographic and utility information,
including information included on the facility record drawings (previously provided to RH2).
Prepare a proposed site and utility plan identifying the proposed site , mechanical, and
structural improvements.
Prepare details for the proposed mechanical, structural, and electrical improvements within
the dry well structure.
Prepare structural engineering details and plan sheets for the wet well improvements.
Prepare electrical engineering plans related to the replacement of the Pump No. 3 and its
related equipment.
Prepare plan set cover, general notes, mechanical details, and related plan sheets as
applicable.
Prepare 60-percent design plans and an OPCC for City review. Attend one (1) meeting with
the City to review the 60-percent deliverables. Prepare meeting agenda and minutes.
Prepare technical specifications in RH2’s standard format and front-end bidding documents
using the City’s standards forms.
Incorporate the City’s 60-percent review comments. Prepare 90-percent design plans,
specifications, and OPCC for City review. Attend one (1) meeting with the City to review the
90-percent deliverables. Prepare meeting agenda and minutes.
Incorporate the City’s 90-percent review comments and prepare bid-ready plans, front-end
documents, technical specifications, and OPCC.
Provide direction and coordination to the RH2 project team. Coordinate technical disciplines
as described herein and implement QA/QC reviews.
Provide project management services, including RH2 staffing, invoice review, budget tracking,
and file management. Provide monthly status updates. Coordinate with City staff regarding
schedule and progress.
Assumptions:
• No permits will be needed for the improvements.
Provided by City:
• Attendance at one (1) site visit.
• 60-percent review comments and attendance at one (1) review meeting.
• 90-percent review comments and attendance at one (1) review meeting.
City of Pasco Exhibit A
Maitland Lift Station and 9th & Washington Lift Station Improvements – Phase 2 Scope of Work
5
3/23/2026 1:18:01 PM J:\Data\PSC\00-BusDev\2026 Maitland Lift Station and 9th and Washington Lift Station Improvements\PSA_SOW_Maitland LS and 9th & WA LS Improvements
PH2.docx
RH2 Deliverables:
• Attendance at one (1) site visit.
• 60-percent design plans and OPCC.
• Attendance at 60-percent design review meeting and meeting agenda and minutes.
• 90-percent design plans, specifications, and OPCC.
• Attendance at 90-percent design review meeting and meeting agenda and minutes.
• Bid-ready plans, specifications, and OPCC.
• Monthly invoices.
Task 3 – Services During Bidding
Objective: Assist the City with the bidding and award process for the construction of the
improvements. It is assumed that the City will advertise the project and be the main point of contact
for bidders. RH2 will refer all interested bidders with questions to the City.
Approach:
Respond to contractor or supplier technical questions during bidding . It is assumed that the
City will respond to procedural questions.
Attend a pre-bid walkthrough at each lift station site with the City and prospective
contractors.
Prepare up to two (2) addenda to clarify, revise, or change the construction plans, technical
specifications, or project conditions during the bidding process.
Create electronic conformed for construction contract documents for the contractor. No hard
copies will be produced by RH2.
Provide project management services, including RH2 staffing, invoice review, budget tracking,
and file management. Provide monthly status updates. Coordinate with City staff regarding
schedule and progress.
Assumptions:
• The City will be responsible for drafting and submitting the advertisement to the appropriate
publications and paying all associated fees directly. The bid documents will be distributed by
an online plan center and no hard copies will be provided to bidders.
• The City will take the lead role during bidding, will receive all bidder questions, and will record
them for forwarding to RH2 at the City’s discretion.
• If warranted, the City will attend and manage a pre-bid meeting. RH2 will not attend.
• The City will conduct the bid opening. It is assumed that RH2 will not attend.
• The City will prepare and distribute the bid tabulation.
City of Pasco Exhibit A
Maitland Lift Station and 9th & Washington Lift Station Improvements – Phase 2 Scope of Work
6
3/23/2026 1:18:01 PM J:\Data\PSC\00-BusDev\2026 Maitland Lift Station and 9th and Washington Lift Station Improvements\PSA_SOW_Maitland LS and 9th & WA LS Improvements
PH2.docx
• The City will review insurance documents in the bid package(s) and be responsible for
construction contract execution.
Provided by City:
• Bid advertisement and payment of fees directly.
• Receive and record bidder questions.
• Conduct the bid opening and distribute the bid tabulation.
• Construction contract execution.
RH2 Deliverables:
• Responses to contractor or supplier questions via telephone or email.
• Attendance at pre-bid walkthroughs.
• Up to two (2) addenda.
• Conformed for construction contract documents.
Task 4 – Services During Construction (Limited)
Objective: Provide professional services to the City during construction of the improvements.
Approach:
Attend one (1) pre-construction conference and prepare and distribute the meeting
invitations, agenda, and minutes.
Consult with the City on construction costs, scheduling, and constructability issues. Review
shop drawings and catalog submittals of items requested in the technical specifications.
Provide a written response to the contractor and the City accepting or rej ecting each shop
drawing and reviewed catalog submittal. Review written requests for information (RFIs) and
change order proposals, and provide written responses to the contractor and the City.
Provide part-time on-site construction observations as directed by the City. This subtask
assumes that RH2 will provide up to two hundred thirty-four (234) hours of support, estimated
as follows: ten (10) hours of scheduling, coordination, and administration of RH2 staff and
resources; eighty (80) hours of submittal review; four (4) hours of resubmittal review; twenty
(20) hours of combined RFI and change order reviews; one hundred (100) hours of part-time
on-site observation as requested/directed by the City; and twenty (20) hours of additional
phone, email, meeting, or other related communication and support. It is assumed that the
City will lead all construction contract administration, including processing contractor pay
requests, coordinating special materials testing, and providing full-time inspection.
Assist with startup, testing, and project closeout. Coordinate with the contractor, the City,
and manufacturer’s representatives of the proposed equipment for the scheduled testing and
startup activities. Review testing protocols developed by the contractor and manufacturer’s
representatives, and review of the tests and corrections. Document activities during startup
City of Pasco Exhibit A
Maitland Lift Station and 9th & Washington Lift Station Improvements – Phase 2 Scope of Work
7
3/23/2026 1:18:01 PM J:\Data\PSC\00-BusDev\2026 Maitland Lift Station and 9th and Washington Lift Station Improvements\PSA_SOW_Maitland LS and 9th & WA LS Improvements
PH2.docx
and coordinate with the contractor per their compliance with the plans and specifications.
Notify the contractor and the City of work that has not been completed by the contractor and
discuss contractor rectification. Attend a final on-site walkthrough with City staff and prepare
an email documenting the facility testing status and punchlist items. The City will prepare and
submit construction completion documentation to regulatory agencies.
Prepare record drawings representative of the as-constructed project. Record drawings will
be completed based upon contractor markups to the conformed for construction drawings.
Provide record drawings for City records.
Provide project management services, including RH2 staffing, invoice review, budget tracking,
and file management. Provide monthly status updates. Coordinate with City staff regarding
schedule and progress.
Assumptions:
• RH2 is not responsible for site safety, or for determining means and methods or directing
others in the performance of this Scope of Work.
Provided by City:
• Attendance at pre-construction conference and final walkthrough.
• Construction contract administration, including pay requests and special materials testing.
• Full-time inspection.
• Project closeout and construction completion documentation to regulatory agencies.
RH2 Deliverables:
• Attendance at pre-construction conference and invitation, agenda, and minutes.
• Written responses to shop drawings, RFIs, and change order proposals.
• Part-time on-site observations and observation reports.
• Attendance at startup and testing.
• Attendance at final walkthrough.
• Punchlist.
• Construction record drawings.
Project Schedule
It is anticipated that RH2 will receive notice to proceed on Phase 2 in April 2026. Based on the
following timelines, the bid-ready documents are anticipated to be completed in Q4 2026.
RH2 anticipates delivery of the 60-percent design deliverables within ten (10) weeks of receipt of the
notice to proceed.
City of Pasco Exhibit A
Maitland Lift Station and 9th & Washington Lift Station Improvements – Phase 2 Scope of Work
8
3/23/2026 1:18:01 PM J:\Data\PSC\00-BusDev\2026 Maitland Lift Station and 9th and Washington Lift Station Improvements\PSA_SOW_Maitland LS and 9th & WA LS Improvements
PH2.docx
RH2 anticipates delivery of the 90-percent design deliverables within eight (8) weeks of receipt of
the City’s 60-percent design comments.
RH2 anticipates delivery of the bid-ready deliverables within six (6) weeks of receipt of the City’s
90-percent design comments.
Design review meetings shall be held within seven (7) calendar days of RH2’s submittal of each design
milestone’s deliverables. City comments on design deliverables shall be provided within seven
(7) calendar days of receipt of said documents.
EXHIBIT B
Fee Estimate
City of Pasco
Maitland Lift Station and 9th & Washington Lift Station Improvements Phase 2
Mar-26
Description
Total ALL
Hours
Total ALL
Labor
Total RH2
Expense
Total Cost
Task 1 Maitland Lift Station Improvements 363 83,612$ 4,845$ 88,457$
Task 2 9th and Washington Lift Station Improvements 471 105,286$ 5,760$ 111,046$
Task 3 Services During Bidding 56 13,006$ 836$ 13,842$
Task 4 Services During Construction (Limited)334 75,642$ 5,433$ 81,075$
PROJECT TOTAL 1,224 277,546$ 16,873$ 294,419$
J:\Data\PSC\00-BusDev\2026 Maitland Lift Station and 9th and Washington Lift Station Improvements\PSA_FEE_Maitland LS and 9th & WA LS Improvements PH2 3/23/2026 1:35 PM
RATE LIST RATE UNIT
Professional I $179 $/hr
Professional II $196 $/hr
Professional III $217 $/hr
Professional IV $240 $/hr
Professional V $256 $/hr
Professional VI $274 $/hr
Professional VII $298 $/hr
Professional VIII $324 $/hr
Professional IX $328 $/hr
Technician I $138 $/hr
Technician II $152 $/hr
Technician III $172 $/hr
Technician IV $186 $/hr
Technician V $205 $/hr
Technician VI $224 $/hr
Technician VII $243 $/hr
Technician VIII $254 $/hr
Administrative I $93 $/hr
Administrative II $108 $/hr
Administrative III $127 $/hr
Administrative IV $151 $/hr
Administrative V $178 $/hr
CAD/GIS System $27.50 $/hr
CAD Plots - Half Size $2.50 price per plot
CAD Plots - Full Size $10.00 price per plot
CAD Plots - Large $25.00 price per plot
Copies (bw) 8.5" X 11"$0.09 price per copy
Copies (bw) 8.5" X 14"$0.14 price per copy
Copies (bw) 11" X 17"$0.20 price per copy
Copies (color) 8.5" X 11"$0.90 price per copy
Copies (color) 8.5" X 14"$1.20 price per copy
Copies (color) 11" X 17"$2.00 price per copy
Technology Charge 2.50%% of Direct Labor
Night Work 10.00%% of Direct Labor
Mileage $0.7250
price per mile
(or Current IRS Rate)
Subconsultants 15%Cost +
Outside Services at cost