HomeMy WebLinkAbout4523 Resolution - WWTP Ph 1 Change Order 10 ApprovalResolution - CO No. 10 for WWTP Phase 1 - 1
RESOLUTION NO. 4523
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO.
10 WITH CLEARWATER CONSTRUCTION & MANAGEMENT, LLC FOR
THE WASTEWATER TREATMENT PLANT PHASE 1 IMPROVEMENTS
PROJECT.
WHEREAS, the City of Pasco (City) and Clearwater Construction & Management, LLC
(Clearwater) entered into a Construction Contract on June 18, 2021, for construction of the
Wastewater Treatment Plant (WWTP) Phase 1 Improvements; and
WHEREAS, previously approved Change Orders No. 1 and No. 2 were under the authority
provided to the Public Works Director; and
WHEREAS, previously approved Change Orders No. 3 through No. 7 were under the
authority provided to the City Manager; and
WHEREAS, previously approved Change Order No. 8 was under the authority provided
to the Public Works Director; and
WHEREAS, previously approved Change Order No. 9 was under the authority provided
to the City Manager; and
WHEREAS, proposed Change Order No. 10 is issued to address various facility
modifications required to extend operational service life of the existing wastewater treatment
system and infrastructure in addition to other modifications needed to address unforeseen site
conditions at an aging operating treatment facility construction site; and
WHEREAS, the $150,008.07 amount of Change Order No. 10 added to the cumulative
sum of previously approved Change Orders, exceeds the City Manager’s authority, and thus
determined to obtain Council approval; and
WHEREAS, the City Council of the City of Pasco, Washington, has after due
consideration, determined that it is in the best interest of the City to enter into Change Order No.
10 with Clearwater.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PASCO, WASHINGTON:
That the City Council of the City of Pasco approves the terms and conditions of Change
Order No. 10 between the City of Pasco and Clearwater as attached hereto and incorporated herein
as Exhibit A.
Resolution - CO No. 10 for WWTP Phase 1 - 2
Be It Further Resolved, that the City Manager of the City of Pasco, Washington, is hereby
authorized to execute said Change Order No. 10 on behalf of the City of Pasco.
Be It Further Resolved, that this resolution shall take effect immediately.
PASSED by the City Council of the City of Pasco, Washington, on this 18th day of
November, 2024.
_____________________________
Pete Serrano
Mayor
ATTEST: APPROVED AS TO FORM:
_____________________________ ___________________________
Debra Barham, MMC Kerr Ferguson Law, PLLC
City Clerk City Attorneys
Exhibit A
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
February 20, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 001 – Existing Duct Bank at Blower Building
Engineer’s Decision
Paul,
We have reviewed your credit proposal for CPR 001 – Existing Duct Bank at Blower Building. We
have found your submitted credit proposal to be acceptable, however, we have made one
correction. A credit for 1.5% Insurance and Bond costs was not included. This creates an
adjustment of $327.25 which increases the total amount of the credit to $22,143.98 ($21,816.73 +
$327.25.)
A total credit of $22,143.98 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
327.25
$ 22,143.98
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
March 27, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 003 – Blower Building Drain Revision
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 003 – Blower Building Drain Revision. We have
found your submitted cost proposal to be acceptable.
A total cost of $7,140.79 and a total of 2 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
May 10, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 017 – HACH Sensor Cable Temporary Connection
Engineer’s Decision
Paul,
We have reviewed your cost and credit proposals for CPR 017 – HACH Sensor Cable
Temporary Connection. We have found your submitted overall credit proposal of
$18,862.13 to be acceptable.
Additional working days requested for this change were negotiated as a part of Change
Order No. 07.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
January 31, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 21 – 2-inch LPA Valves
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 021 – 2-inch LPA Valves. We have found your
submitted cost proposal to be acceptable.
A total cost of $2,872.69 ($2,637.92 + $234.77 Sales Tax) and 0 calendar days will be included in a
forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
February 20, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 023 – LPA Pipe Support Modification
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 023 – LPA Pipe Support Modification. We have
found your submitted cost proposal to be acceptable.
A total cost of $2,553.36 and a total of 2 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
April 3, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 24b – Modification to Asphalt Area
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 024b – Modification to Asphalt Area. We have
found your submitted cost proposal to be acceptable.
A total cost of $32,688.53 and a total of 6 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
CPR 024B
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
April 3, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 027 – PW Valves
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 027 – PW Valves. We have found your submitted
cost proposal to be acceptable.
A total cost of $14,031.43 and a total of 4 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
CPR 027
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
February 2, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 28 – Drying Bed PS Reconnection
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 028 – Drying Bed PS Reconnection. We have found
your submitted cost proposal to be acceptable.
A total cost of $814.72 ($748.14 + $66.58 Sales Tax) and 0 calendar days will be included in a
forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
March 8, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 029 – Electrical Duct Bank Encasement
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 029 – Electrical Duct Bank Encasement. We have
found your submitted cost proposal to be acceptable.
A total cost of $14,822.61 and a total of 3 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
February 20, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 030 – Bypass Breakdown Put on Hold
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 030 – Bypass Breakdown Put on Hold. We have
found your submitted cost proposal to be acceptable.
A total cost of $3,712.24 and a total of 6 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
February 20, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 031 – Bypass Operations to TV Existing RCP Line
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 031 – Bypass Operations to TV Existing RCP Line. We
have found your submitted cost proposal to be acceptable.
A total cost of $2,108.08 and a total of 1 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
April 9, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 032 – Additional Retaining Wall
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 032 – Additional Retaining Wall. We have found
your submitted cost proposal to be acceptable.
A total cost of $11,057.60 and a total of 3 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
CPR 032
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
October 4, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
CPR 033 – Chain Wheel
Engineer’s Decision
Paul,
We have reviewed your cost proposal for CPR 033 – Chain Wheel. We have found your submitted
cost proposal to be acceptable.
A total cost of $1,583.86 and a total of 0 working days will be included in a forthcoming Change
Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
Change Order Request #: 57 Date:9/11/2024
Reason For Change:
Change Directed By:
Delay's Caused By Change
Labor:673.90$
673.90$
Material:683.02$
-$
683.02$
Equipment:
-$
Subcontracts:
Other Costs:
-$
Total Costs:1,356.92$
Labor O&P 15% 101.09$
Material O&P 15% 102.45$
Equipment O&P 15% -$
Subcontractor O&P 5% -$
Total Markup 203.54$
Total With Markup 1,560.46$
Tax at 8.90%
Insurance and Bond at 1.50% 23.41$ 23.41$
1,583.86$
Date:
Date:
Clearwater Construction & Management, LLC
Project: 19072 WWTP Phase 1- Pasco
Description of Change: Change butterfly valve handwheel to chain wheel in RAS basement
This BF valve operator was shown as a hand wheel but it is too high off floor to be
TOTAL LABOR
Buy new chain wheel for butterfly valve
City of Pasco
yes
2 Carpenters x 5 hours x $67.39
TOTAL MATERIAL
TOTAL EQUIPMENT
TOTAL SUBCONTRACTS
Notes:
Signed: Clearwater Construction ________________________________________
Signed: Owners Representative ____________________________________________
To be added to Invoice
Total Amount This Change Order Request:
Additional Working Days Required:
Victoria Fragione 10/3/24
CPR 033
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
April 3, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
WCD 002 – Baffle Wall Elevation Change
Engineer’s Decision
Paul,
We have reviewed your cost proposal for WCD 002 – Baffle Wall Elevation Change. We have found
your submitted cost proposal to be acceptable.
A total cost of $20,438.34 and a total of 0 working days will be included in a forthcoming Change
Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
WCD 002
Ecology Project Manager
2/23/2022
Approved by Dianna WashingtonVia Email 2/18/2022
2/23/2022
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
February 2, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
WCD 004 – NPW Yard Piping
Engineer’s Decision
Paul,
We have reviewed your cost proposal for WCD 004 – NPW Yard Piping. We have found your
submitted cost proposal to be acceptable.
Additional working days requested for this change were negotiated as a part of Change Order No.
07.
A total cost of $10,723.53 ($9,847.13 + $876.40) will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
10/18/2022
Environmental Engineer
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
February 2, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
WCD 005 – Combined Footing
Engineer’s Decision
Paul,
We have reviewed your cost proposal for WCD 005 – Combined Footing. We have found your
submitted cost proposal to be acceptable.
Additional working days requested for this change were negotiated as a part of Change Order No.
07.
A total cost of $6,568.80 ($6,031.96 + $536.84) will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
April 3, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
WCD 006 – 4-inch Dropleg Connection
Engineer’s Decision
Paul,
We have reviewed your cost proposal for WCD 006 – Dropleg Connection. We have found your
submitted cost proposal to be acceptable.
A total cost of $3,169.92 and a total of 0 working days will be included in a forthcoming Change
Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
WCD 006
$2,715.71
$407.36
$3,123.07
$ 46.85
$3,169.92
Ecology Engineer
1/3/2023
Ecology Project Manager
1/3/2023
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
February 2, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
WCD 009 – Sensor Box Relocation
Engineer’s Decision
Paul,
We have reviewed your cost proposal for WCD 009 – Sensor Box Relocation. We have found your
submitted cost proposal to be acceptable.
Additional working days requested for this change were negotiated as a part of Change Order No.
07.
A total cost of $11,647.30 ($10,695.41 + $951.89) will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
Ecology Engineer
1/17/2023
Ecology Project Manager
1/17/2023
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
February 21, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
WCD 013 – RAS Probe Piping
Engineer’s Decision
Paul,
We have reviewed your cost proposal for WCD 013 – RAS Probe Piping. We have found your
submitted cost proposal to be acceptable.
Note that on your summary sheet you are listing and calculating markup for total equipment when
it should have been categorized under materials. The markup for equipment and materials are the
same, therefore, it did not adjust the total amount of the cost proposal.
A total cost of $12,965.00 and a total of 2 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
2
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
Total Material
Material O&P
4/13/2023
Ecology Engineer
ERO Ecology Project Manager
4/14/2023
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
March 27, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
WCD 014 – Non Potable Waterline Valves
Engineer’s Decision
Paul,
We have reviewed your cost proposal for WCD 014 – Non Potable Waterline Valves. We have
found your submitted cost proposal to be acceptable.
A total cost of $10,427.45 and a total of 3 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
April 3, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
WCD 015 – Demo Pipe and Gate Valve
Engineer’s Decision
Paul,
We have reviewed your cost proposal for WCD 015 – Demo Pipe and Gate Valve. We have found
your submitted cost proposal to be acceptable.
A total cost of $11,512.93 and a total of 6 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
WCD 015
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
April 9, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
WCD 016 – Flow Meter Vault Davit Socket
Engineer’s Decision
Paul,
We have reviewed your cost proposal for WCD 016 – Flow Meter Vault Davit Socket. We have
found your submitted cost proposal to be acceptable.
A total cost of $1,737.88 and a total of 0 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
February 21, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
WCD 017 – 4-inch Plug Valve on SL
Engineer’s Decision
Paul,
We have reviewed your cost proposal for WCD 017 – 4-inch Plug Valve on SL. We have found your
submitted cost proposal to be acceptable.
A total cost of $4,004.55 and a total of 2 working days to the Substantial Completion date as
defined by Change Order No. 7 will be included in a forthcoming Change Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco
Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
Ecology Engineer
12/01/2023
Ecology Project Manager
12/4/2023
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
August 15, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
Phase 2A CPR 024 – Phase 1 Scum Line Removal
Engineer’s Decision
Paul,
Attached is the Engineer’s Decision for work done by Apollo Construction to complete work that
was shown to be completed in Phase 1. This cost from Phase 2 is applied as a credit to Phase 1.
A total credit of $2,668.30 is included in this Change Order No. 10.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
HDR 835 North Post Street, Suite 101 , Spokane , WA 99201-2126
(509) 343-8500
July 25, 2024
Apollo, Inc.
1133 West Columbia Drive
Kennewick, WA 99336
Attn: Dan Sjule
Re: City of Pasco 21237A WWTP Improvements Phase 2 Project
CPR 024 – Phase I Scum Line Removal
Engineer’s Decision
Dan,
We have reviewed your cost proposal for CPR 024 – Phase I Scum Line Removal. We have found
your submitted cost proposal to be acceptable.
A total cost of $2,668.30 and a total of 0 calendar days will be included in a forthcoming Change
Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco Heath Bateman – City of Pasco
Kent McCue – City of Pasco Todd Marden – City of Pasco
Mary Scalise – HDR Mike Soucie – HDR
Troy Gibbs – HDR Craig Anderson – Consor
Mark Cummings – Consor Diana Washington – Ecology
Greg Dobb – Ecology
Change Proposal Request Summary APR No:032
Project: City of Pasco WWTP Improvements Phase 2A Contract Reference Phase 1
Apollo Inc.Date:07/11/24
Removal of Phase 1 SCUM Line
Description Labor Mat Equip.Subcont. Total Supp Total Total
Removal of Phase 1 SCUM Line 1,638.35$ -$ 609.56$ 387.45$ -$ 2,635.36$
SUBTOTAL COST >2,635.36$
Insurance Premium .5% - Changed Work >13.18$
Bond Premium .75% - Changed Work >19.77$
TOTAL LUMP SUM COST >2,668.30$
Print Date: 7/30/2024 Page 1 of 3 P198 APR-032R1 Removal of Phase 1 SCUM Line.xlsx
Change Proposal Request APR No:032
Project: City of Pasco WWTP Improvements Phase 2A Contract Reference Phase 1
Apollo Inc.Date:7/11/24
Removal of Phase 1 SCUM Line
Description Qty U of M Rate Labor Unit Rate Mat Unit Rate Equip.Subcont. Total Total
Project Manager 1.0 HR 90.00$ 90.00$ 90.00$
Project Superintendent - Josh Prock 1.0 HR 80.00$ 80.00$ 80.00$
Operators - Key Personnel
Operator Foreman - Chris Armour 5.5 HR 62.60$ 344.30$ 344.30$
Laborers
Foreman - Rick Grnya 7.5 HR 67.38$ 505.35$ 505.35$
Pipelayer - Wilmer Leal 7.5 HR 54.00$ 405.00$ 405.00$
Excavator - CAT 303
+ Operator HR 61.39$ -$ -$
+ Operating Costs 7.5 HRLY 25.26$ 189.45$ 189.45$
Loader - John Deere 524
+ Operator (N/A included in labor above)0.0 HR 61.73$ -$ -$
+ Operating Costs 6.5 HRLY 52.40$ 340.60$ 340.60$
DAY -$ -$ -$
LS -$ -$
-$ -$
LS -$ -$ -$
Misc. Items LS -$ -$ -$
Disposal Fees LS -$ -$ -$
Apollo - Subtotal Direct Costs >1,424.65$ -$ 530.05$ 1,954.70$
Markup on Self-Performed Labor, Mat'ls &
Equipment >15.0%213.70$ -$ 79.51$ 293.21$
Plateau CRM - Archaeological Monitor 1 369.00$ 369.00$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
Subtotal Subcontractors Costs >369.00$ 369.00$
Markup on Subcontractor Costs >5.0%18.45$ 18.45$
Special Consultants -$ -$
Temporary Facilities at the Site LS -$ -$
LS -$ -$ -$
Subtotal Supplementary Costs >-$ -$ -$
Markup on Supplementary Costs >0.0
Contractor - Total Direct Costs w/Markup >2,635.36$
Insurance Premium .5% - Changed Work >13.18$
Bond Premium .75% - Changed Work >19.77$
TOTAL LUMP SUM COST >2,668.30$
SUPPLEMENTAL COSTS
SUBCONTRACTOR COSTS
APOLLO - PROJECT SUPERVISION COSTS
APOLLO - CRAFT LABOR COSTS
APOLLO - OPERATED EQUIPMENT
APOLLO - OTHER EQUIPMENT COSTS
APOLLO - MATERIAL COSTS
Page 2 of 3
hdrinc.com
835 North Post Street, Suite 101, Spokane , WA 99201-2126
(509) 343-8500
August 15, 2024
Clearwater Construction & Management LLC
5711 W Garden Springs Road
Spokane, WA 99224
Attn: Paul Clary
Re: City of Pasco 19072 WWTP Improvements Phase 1
Phase 2A CPR 025 – Phase 1 Demo Work
Engineer’s Decision
Paul,
Attached is the Engineer’s Decision for work done by Apollo Construction to complete work that
was shown to be completed in Phase 1. This cost from Phase 2 is applied as a credit to Phase 1.
A total credit of $2,492.26 is included in this Change Order No. 10.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Kent McCue – City of Pasco
Heath Bateman – City of Pasco
Todd Marden – City of Pasco
Troy Gibbs – HDR
Mike Soucie – HDR
Mary Scalise – HDR
Craig Anderson – Consor
Mark Cummings – Consor
Diana Washington – Ecology
Greg Dobb – Ecology
hdrinc.com
HDR 835 North Post Street, Suite 101 , Spokane , WA 99201-2126
(509) 343-8500
July 25, 2024
Apollo, Inc.
1133 West Columbia Drive
Kennewick, WA 99336
Attn: Dan Sjule
Re: City of Pasco 21237A WWTP Improvements Phase 2 Project
CPR 025 – Phase I Demo Work to Remove of Drying Bed Lift Station
Engineer’s Decision
Dan,
We have reviewed your cost proposal for CPR 025 – Phase I Demo Work to Remove of Drying Bed
Lift Station. We have found your submitted cost proposal to be acceptable.
A total cost of $2,492.26 and a total of 0 calendar days will be included in a forthcoming Change
Order.
Sincerely,
HDR Engineering, Inc.
Todd Jensen, PE, CCM
Construction Manager
cc: Brittany Whitfield – City of Pasco Heath Bateman – City of Pasco
Kent McCue – City of Pasco Todd Marden – City of Pasco
Mary Scalise – HDR Mike Soucie – HDR
Troy Gibbs – HDR Craig Anderson – Consor
Mark Cummings – Consor Diana Washington – Ecology
Greg Dobb – Ecology
Change Proposal Request Summary APR No:025 R1
Project: City of Pasco WWTP Improvements Phase 2A Contract Reference N/A
Apollo Inc.Date:07/24/24
Phase 1 Demo Work to Remove Drying Best Lift Station
Description Labor Mat Equip.Subcont. Total Supp Total Total
Item 1 1,257.46$ 524.40$ 421.34$ 258.30$ -$ 2,461.49$
SUBTOTAL COST >2,461.49$
Insurance Premium .5% - Changed Work >12.31$
Bond Premium .75% - Changed Work >18.46$
TOTAL LUMP SUM COST >2,492.26$
Print Date: 7/24/2024 Page 1 of 2P198 APR-025 Rev 1 Phase 1 Demo Work to Remove Drying Bed Lift Station.xlsx
Change Proposal Request APR No:025 R1
Project: City of Pasco WWTP Improvements Phase 2A Contract Reference N/A
Apollo Inc.Date:7/24/24
Phase 1 Demo Work to Remove Drying Best Lift Station
Description Qty U of M Rate Labor Unit Rate Mat Unit Rate Equip.Subcont. Total Total
Project Manager 1.0 HR 90.00$ 90.00$ 90.00$
Project Superintendent 2.0 HR 80.00$ 160.00$ 160.00$
Yard Piping / Site Earthwork Super HR 80.00$ -$ -$
Operators - Key Personnel
Operator Foreman - Chris Armour 5.5 HR 62.60$ 344.30$ 344.30$
Laborers
Foreman - Rick Grnya 3.0 HR 67.38$ 202.14$ 202.14$
Pipelayer - Wilmer Leal 5.5 HR 54.00$ 297.00$ 297.00$
Pipefitter - Laborer HR 100.36$ -$ -$
Excavator - CAT 312C
+ Operator HR 61.73$ -$ -$
+ Operating Costs 1.0 HRLY 89.28$ 89.28$ 89.28$
Excavator - CAT 330 C
+ Operator HR 61.73$ -$ -$
+ Operating Costs 1.0 HRLY 104.53$ 104.53$ 104.53$
Forklift - CAT TH83
+ Operator HR 60.22$ -$ -$
+ Operating Costs 1.0 HRLY 128.15$ 128.15$ 128.15$
Loader - CAT 936
+ Operator HR 61.73$ -$ -$
+ Operating Costs 1.0 HRLY 44.42$ 44.42$ 44.42$
LS -$ -$
LS -$ -$
-$ -$
CDF 1.0 LS 456.00$ 456.00$ 456.00$
LS -$ -$ -$
Misc. Items LS -$ -$ -$
Disposal Fees LS -$ -$ -$
Apollo - Subtotal Direct Costs >1,093.44$ 456.00$ 366.38$ 1,915.82$
Markup on Self-Performed Labor, Mat'ls &
Equipment >15.0%164.02$ 68.40$ 54.96$ 287.37$
Plateua CRM
Cultural Resource Monitoring
Moira Riggs
3 HR 82.00$ 246.00$
-$ -$
Subtotal Subcontractors Costs >82.00$ 246.00$
Markup on Subcontractor Costs >5.0%4.10$ 12.30$
Special Consultants -$ -$
Temporary Facilities at the Site LS -$ -$
LS -$ -$ -$
Subtotal Supplementary Costs >-$ -$ -$
Markup on Supplementary Costs >0.0
Contractor - Total Direct Costs w/Markup >2,461.49$
Insurance Premium .5% - Changed Work >12.31$
Bond Premium .75% - Changed Work >18.46$
TOTAL LUMP SUM COST >2,492.26$
SUPPLEMENTAL COSTS
SUBCONTRACTOR COSTS
APOLLO - PROJECT SUPERVISION COSTS
APOLLO - CRAFT LABOR COSTS
APOLLO - OPERATED EQUIPMENT
APOLLO - OTHER EQUIPMENT COSTS
APOLLO - MATERIAL COSTS
Page 2 of 2