HomeMy WebLinkAbout4494 Resolution - CO. 7 with Nelson Construction for I-182 & Broadmoor InterchangeResolution – I-182 & Broadmoor Interchange CO No.7 - 1
RESOLUTION NO. 4494
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO.
7 WITH NELSON CONSTRUCTION CORP. FOR THE I-182 & BROADMOOR
BLVD. INTERCHANGE.
WHEREAS, the City of Pasco (City), and Nelson Construction Corp. entered into a
Construction Contract on June 30, 2023, for construction of the I-182 & Broadmoor Blvd.
Interchange Project; and
WHEREAS, I-182 & Broadmoor Blvd. Interchange Project addressed the need for a
deceleration lane on Eastbound I-182 offramp, a new loop ramp connecting to Northbound
Broadmoor Boulevard, a roundabout at the Eastbound Terminal of Broadmoor Boulevard, active
transportation improvements, and other work; and
WHEREAS, previously approved Change Orders No. 1 – No. 4 was under the authority
provided to the Public Works Director; and
WHEREAS, Change Order No. 5 and No. 6 were both approved by City Council and
executed on April 17, 2024, and July 8, 2024, respectively; and
WHEREAS, Change Order No. 7 addresses multiple changes to the contract that were
either the result of unforeseen site conditions, modifications identified during construction, or
additional requirements placed on the contract by the Washington State Department of
Transportation (WSDOT); and
WHEREAS, the $91,428.00 amount of Change Order No. 7 added to the cumulative sum
of the previously approved Change Orders, exceeds the City Manager’s authority, and thus
determined to obtain Council Approval; and
WHEREAS, the City Council of the City of Pasco, Washington, has after due
consideration, determined that it is in the best interest of the City to enter into Change Order No.
7 with Nelson Construction Corp.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PASCO, WASHINGTON:
That the City Council of the City of Pasco approves the terms and conditions of Change
Order No. 7 between the City of Pasco and Nelson Construction Corp. as attached hereto and
incorporated in Exhibit A.
Be It Further Resolved, that the City Manager of the City of Pasco, Washington, is hereby
authorized, empowered, and directed to execute said Change Order No. 7 on behalf of the City of
Pasco.
Resolution – I-182 & Broadmoor Interchange CO No.7 - 2
Be It Further Resolved, that this Resolution shall take effect immediately.
PASSED by the City Council of the City of Pasco, Washington, on this 16th day of
September, 2024.
_____________________________
Pete Serrano
Mayor
ATTEST: APPROVED AS TO FORM:
_____________________________ ___________________________
Debra Barham, MMC Kerr Ferguson Law, PLLC
City Clerk City Attorneys
Project No:21-292 I-182 and Broadmoor Boulevard Interchange
Contractor:
Description of Change:
Detail as Appropriate:
Item Cost Totals
107 1,600.00$
108 5,000.00$
109 5,000.00$
110 50,000.00$
111 4,588.00$
112 13,160.00$
113 10,580.00$
114 1,500.00$
Contract Bid Amount:6,144,660.00$
SALES TAX @ 8.9%:546,874.74$
Total:6,691,534.74$
Subtotal including tax Subtotal
No tax
Total Total
Total Change Orders To Date 625,131.68$
New Contract Amount
YES NO
APPROVED:
CONTRACTOR Date Date
APPROVED:
Date Date
APPROVED:
Structural Excavation Class B Include Haul & shoring, Lump Sum
91,428.00$
APPROVED:
7,316,666.42$
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order…………………………..360
Modification to Contract Time by this Change Order………………
PREVIOUS CHANGE ORDERS TOTAL CURRENT CHANGE ORDER
Project Weed and Pest Control, Force Acount
Third Party Damage, Force Account
Detectable Warning Surface, 124 SF @$37.00/SF
Luminaire Pole Grading Costs, Lum Sum
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 7
Project Title:
Nelson Construction Corp.
Items not included in the original contract, or modifications identified during construction.
This C. O. adds the following items. Payment method for each new item will be as listed. For details of each
item see page two of this document. The following items are required for the project's success and by
WSDOT.
PROJECT MANAGER
APPROVED:
Revised Total Contract Time…………………………………………360
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation
for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed
that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents
shall apply to this Change Order.
AGREED TO AND ACCEPTED:
Additional Surveying/partnering, lump sum
Description and Payment Method
Bridge inlet grate type change out 4 each, Lump Sum
Testing Storm Sewer Pipe,Lump Sum
0
533,703.68$ 91,428.00$
533,703.68$
CONSTRUCTION MANAGER DEPUTY PW DIRECTOR-ENGINEERING
Page 1 of 2
Date Date
107
108
109
110
111
112
113
114
Additional surveying for deceleration ramp east bound/partnering, lump sum
PUBLIC WORKS DIRECTOR CITY MANAGER
In Change order #6 the cost of surveying for the correction of the grades and concrete widths on the EB off ramp deleration taper was not
included in the lump sum amount. This lunp sum amount was negotiated as a partnering opportunity.
Bridge inlet grate type change out 4 each, Lump sum
Grate tops on inlets located at the four corners of the overcrossing bridge are not ADA compliant. This change order replaces existing
welded covers with duel vaned Grates and frames. All work will be in accordance with the contract documants. A lump sum payment will
be made for the installation of 4 vaned grates and frames.
Project weed and pest control, Force Acount
Wsdot requires weeding and pest control be accomplished prior to seeding and mulchimg of areas to be seeded. This item accommodates
that requirement. All work will be in accordance with the contract documents.
Third Party Damage, Force Account
WSDOT specifications require an item to pay for damage caused by third parties. This item accommodates that requirement. Information
for this item is contained in the contract documents.
Contract Plans Set Resolutions, Lump Sum
WSDOT Specifications required an item to pay for excavating and shoring for the placement of storm sewer pipe. This Lump Sum amount is
to compensate the contractor for the Structure excavation and for shoring of the storm sewers trenches. All work is to be in accordance
with the contract documents. A lump sum payment will be made for all storm sewer sytem excavation and shoring of trenches associated
with CB1 - CB6 and the culvert in the origninal bid contract documents.
Detectable Warning Surface, Square Foot
WSDOT specifications pays for Detectable Warning Surface (DWS) separatly when placed in a sidewalk that is not part of an ADA ramp.
There are multiple locations on the project with this situation. This item accommodates that requirement. All work for this item will be in
accordance with the contract documents..
Testing Storm Sewer Pipe,Lump Sum
WSDOT Specifications require storm sewer pipe be tested. This item accommodates that requirement. All work will be in accordance with
the 2023 WSDOT standard specifications, considered part of this contract. Paymant will be a lump sum amount for up to 1060 LF of storm
sewer pipe. A lump sum payment will be made for the testing of all storm sewer pipes installed on the project.
Luminaire Pole Grading Costs, Lump Sum
The plans were ambiguous as to the need for the embankment around the luminaire poles . WSDOT required this embankment to create a
safe break away base. Material was paid through existing items however added labor and equipment was requied to place this material
after the inital embankment was built. This item compensates the contractor for that added cost.
Page 2 of 2