HomeMy WebLinkAbout4471 Resolution - Lewis St Overpass Project Change Orders Nos. 37- 52
Resolution – CO Nos. 37-52 for Lewis St Overpass - 1
RESOLUTION NO. 4471
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER
NOS. 37-52 TO THE CONSTRUCTION CONTRACT WITH CASCADE
BRIDGE, LLC, FOR THE LEWIS STREET OVERPASS PROJECT.
WHEREAS, the City of Pasco, Washington, and Cascade Bridge, LLC entered into a
Construction contract on March 1, 2021, for construction of the Lewis Street Overpass Project;
and
WHEREAS, this project involves the construction of a new 562-foot, 4-span, pre-stressed
Concrete overpass, over the BNSF Railway yard, and a new 63-foot, voided slab, overpass over
First Avenue. Along with roadway improvements, backfilling, partial structure removal, retaining
wall construction, earthwork, paving with HMA, landscaping, storm drainage, illumination, water
mains, sanitary sewer, and other associated work; and
WHEREAS, the City of Pasco, Washington, and Cascade Bridge, LLC executed Change
Order Nos. 1 through 36 to provide for additional work not included in the original contract; and
WHEREAS, proposed Change Orders Nos. 37 through 52 involve additional work related
to: railroad screening gap, saw-cutting salvaged barrier, various minor change items, striping
removal, irrigation controller substitution, project escalation costs, adjusting catch basins, water
joint casing epoxy, security fencing, and a negotiated change order to resolve outstanding issues
for a total of $2,706,397.19; and
WHEREAS, the City Council of the City of Pasco, Washington, has after due
consideration, determined that it is in the best interest of the City of Pasco to enter into Change
Order Nos. 37-52 with Cascade Bridge, LLC.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PASCO, WASHINGTON:
That the City Council of the City of Pasco approves the terms and conditions of the Change
Order Nos. 37-52 between the City of Pasco and Cascade Bridge, LLC as attached hereto and
incorporated herein as Exhibit A.
Be It Further Resolved, that the City Manager of the City of Pasco, Washington, is hereby
authorized, empowered, and directed to execute said Change Order Nos. 37-52 on behalf of the
City of Pasco.
Be It Further Resolved, that this Resolution shall take effect immediately.
Resolution – CO Nos. 37-52 for Lewis St Overpass - 2
PASSED by the City Council of the City of Pasco, Washington, on this 22nd day of July,
2024.
_____________________________
Pete Serrano
Mayor
ATTEST: APPROVED AS TO FORM:
_____________________________ ___________________________
Debra Barham, CMC Kerr Ferguson Law, PLLC
City Clerk City Attorneys