HomeMy WebLinkAbout4441 Resolution - PWRF Phase 2 Change Order 3
Resolution - CO No. 3 for PWRF Phase 2 - 1
RESOLUTION NO. 4441
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO.
3 WITH TAPANI, INC. FOR THE PROCESS WATER REUSE FACILITY
PHASE 2 WINTER STORAGE IMPROVEMENTS PROJECT.
WHEREAS, the City of Pasco (City) and Tapani, Inc. entered into a Construction Contract
on September 11, 2023, for construction of the Process Water Reuse Facility (PWRF) Phase 2
Winter Storage Pond Improvements; and
WHEREAS, previously approved Change Order No. 1 was under the authority provided
to the Public Works Director; and
WHEREAS, previously approved Change Order No. 2 was under the authority provided
to the City Manager via Council adoption of Resolution No. 4433 on March 18, 2024; and
WHEREAS, proposed Change Order No. 3 is issued to address enhancements of various
new piping components and infrastructure to support processor connection requirements, minor
drawing updates and clarifications, in addition to structural modifications to the existing Irrigation
Pump Station (IPS) needed to accommodate tie-ins to new winter storage ponds; and
WHEREAS, the $264,488.90 amount of Change Order No. 3 added to the cumulative sum
of previously approved Change Orders, exceeds the City Manager’s authority, and thus determined
to obtain Council approval; and
WHEREAS, the City Council of the City of Pasco, Washington, has after due
consideration, determined that it is in the best interest of the City of Pasco to enter into Change
Order No. 3 with Tapani, Inc.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PASCO, WASHINGTON:
That the City Council of the City of Pasco approves the terms and conditions of Change
Order No. 3 between the City of Pasco and Tapani, Inc. as attached hereto and incorporated herein
as Exhibit A.
Be It Further Resolved, that the City Manager of the City of Pasco, Washington is hereby
authorized, empowered, and directed to execute said Change Order No. 3 on behalf of the City of
Pasco.
Be It Further Resolved, that this Resolution shall take effect immediately.
Resolution - CO No. 3 for PWRF Phase 2 - 2
PASSED by the City Council of the City of Pasco, Washington, on this 15th day of April,
2024.
_____________________________
Pete Serrano
Mayor
ATTEST: APPROVED AS TO FORM:
_____________________________ ___________________________
Debra Barham, CMC Kerr Ferguson Law, PLLC
City Clerk City Attorneys
3/19/2024
3/20/2024
Brandon Farmer
Digitally signed by Brandon Farmer
DN: C=US,
E=BrandonF@Tapani.com,
O=Tapani Inc., CN=Brandon Farmer
Date: 2024.03.20 11:17:20-07'00'3/20/2024
Exhibit A
Date:1/31/2024
Project Name:PWRF P2
Contract #
Job #242001
CPR #6
Description: Minor Plan Changes
Hours Rate Hours Rate
Foreman 72 77.60$ 18 116.41$ HRS 7,682.87$
Pipelayer 72 67.35$ 18 101.03$ HRS 6,668.06$
Backhoe (45,000 Gw & Under) 72 75.74$ 18 113.61$ HRS 7,498.31$
Loader Operator (front-end & Overhead, 4 Yds. Incl. 8 Yds.) 72 76.09$ 18 114.14$ HRS 7,533.19$
General Laborer 72 66.68$ 18 100.01$ HRS 6,600.86$
Labor Sub Total 35,983.29$
Labor Overhead & Profit 15%5,397.49$
Sick Leave 0%-$
Labor Total 41,380.79$
Equipment # Equipment Description Units Rate Unit Total
5220174 Crew Truck 90 49.23$ HRS 4,430.70$
1130110 Caterpillar 336F Excavator 90 163.74$ HRS 14,736.60$
1530060 Caterpillar 938M Loader 90 78.16$ HRS 7,034.40$
Equipment Sub Total 26,201.70$
Equipment Overhead & Profit 15%3,930.26$
Equipment Total 30,131.96$
Unit Rate Quantity Unit Total
109,220.20$ 1 LSU 109,220.20$
(33,294.09)$ 1 LSU (33,294.09)$
12,925.00$ 1 LSU 12,925.00$
300.00$ 4 EA 1,200.00$
-$
Material Sub Total 90,051.11$
Material Overhead & Profit 15%13,507.67$
Material Total 103,558.78$
Unit Rate Quantity Unit Total
650.00$ 1 LSU 650.00$
Survey - MGS - Additional Survey 1,500.00$ 1 LSU 1,500.00$
7,093.80$ 1 LSU 7,093.80$
26,658.87$ 1 LSU 26,658.87$
Straight Line - Filing Fees (Estimated) 300.00$ 1 LSU 300.00$
900.00$ 4 EA 3,600.00$
Sub Contractors Sub Total 39,802.67$
Subcontractor Overhead & Profit 15%5,970.40$
Subcontractor Total 45,773.07$
Unit Rate Quantity Unit Total
525.00$ 1 Day 525.00$
-$
Other Sub Total 525.00$
Other Overhead & Profit 15%78.75$
Stipulations Other Total 603.75$
Sub Total 221,448.34$
Accepted by: General Liability Insurance 0.0000%-$
Bond 0.0% -$
Date:Total Amount 221,448.34$
10
This Change increases the time to complete the project by: Day(s)
This proposal is based on the usual cost elements such as labor, material, and normal markups and does not include all costs for additional changes in the sequence of work,
delays, disruptions, rescheduling, extended overhead, overtime (unless specified), acceleration, and/or impact costs; and the right is expressly reserved to make claim for any
and all (if any) of these related items prior to final completion of this contract. Please consider this language official "notice" as defined in subcontract and/or main contract.
Force Account/ Change Order Worksheet
Description
Please see the attached CPR document for a full detail of what is covered in this scope.
Material Description
Pipe - HD Fowler
Pipe - HD Fowler (Meter Vault DI Material Credit)
Precast - Inland
Bollard - No Quote (Tapani Fabricated)
LABOR
EQUIPMENT
Overtime
Class
MATERIAL
OTHER
Straight Time
Fusion Machine + Datalogger + De-beader Rental
Name/Description Unit Total
Straight Lline - Core Manholes
SUBCONTRACTORS
Subcontractor Description
Survey - MGS - Update CAD Files
Structural - Tapani Structures (Includes Meter Box Coating from CIC)
Electrical - Silverline
Corporate Office
PO Box 1900
Battle Ground, WA 98604
360.687.1148
Bid No: Q539440 Page 1 of 2
Quote #:Q539440
Bid Date:1/12/2024
Line Qty UoM Description Unit Price Extended Price
CARV CHANGES
2 4 EA 4" X 12" BRASS NIPPLE 177.97 711.88
3 4 EA 4" BRASS TEE 196.55 786.20
4 24 EA 4" X 4" BRASS NIPPLE SCH40 66.67 1,600.08
5 8 EA 4" BRASS ELBOW 90 DEGREE 144.15 1,153.20
6 8 EA 4" BRASS BALL VALVE THREADED NO-LEAD 359.89 2,879.12
7 4 EA
4" COMBINATION/UNIVERSAL SEWAGE AIR RELEASE Valve, Crispin Model
US40-US, 4" NPT Inlet & Outlet, 3/16" AVO, Cast Iron Body, Stainless Steel
Trim, Buna-N Seating, Steel Bolting, Lined and Coated with 8 +/-4 mils DFT of
Two Part Liquid Epoxy, 20-150 PSI Working Pressure
2,650.00 10,600.00
8 80 FT 12" SCH 40 IPS SOLVENT WELD PVC PIPE 20' LENGTH 22.47 1,797.60
9 12 EA 12" SCH 40 PVC 90 ELBOW SXS 867.61 10,411.32
1 SHEET C305,C307,C309,C310 CHANGES
CARV CHANGES Subtotal 29,939.40
HDPE REDUCERS
10 C316 CHANGES
11 2 EA 12" X 10" REDUCER HDPE DR11 X DR13.5 122.03 244.06
HDPE REDUCERS Subtotal 244.06
FLOW METER VAULT CHANGES
12 C318, C325 CHANGES
13 3 EA 12" X 3' LONG SS SPOOLS DOMESTIC 10,000.00 30,000.00
14 3 EA
12" DJ400-12 DISMANTLING JOINT CLASS D FLANGE, EPOXY COAT, STD B&N,
AIS DOMESTIC
4,000.00 12,000.00
15 1 SEE ATTACHED EMAIL FOR QUNAITYS OF MATERIAL DELETED
FLOW METER VAULT CHANGES Subtotal 42,000.00
FLOW METER VAULT ADDED
16 C319,C324 CHANGES
17 1 EA 12" X 3' LONG SS SPOOLS DOMESTIC 10,000.00 10,000.00
18 1 EA
12" DJ400-12 DISMANTLING JOINT CLASS D FLANGE, EPOXY COAT, STD B&N,
AIS DOMESTIC
4,000.00 4,000.00
19 1 EA
12" 800 SERIES FLANGED PLUG VALVE WITH AUMA ELECTRIC ACTUATOR
(480VAC/3-PH/60HZ) FOR OPEN/CLOSE SERVICE, MODEL #KG12845, AIS
COMPLIANT
11,500.00 11,500.00
Estimator:Aidan Keser
Job Name:PWRF CHANGE REQUEST 6
Location:PASCO, WA
Customer:TAPANI UNDERGROUND INC
See additional Pages for deduct
and restock fee.
Bid No: Q539440 Page 2 of 2
20 1 EA STARTUP AND TRAINING 4,000.00 4,000.00
21 2 EA 12" SDR 11 FLANGE ADAPTER IPS HDPE MOLDED BUTT FUSION 113.69 227.38
22 2 EA 12" SK-35-P CF-3M (T-316-L) CASTING BACKING FLANGE 2,093.98 4,187.96
23 6 EA
12" CORTEN BOLT & NUT KIT FLOUROPOLYMER COATED, HDPE FLG X DI FLG
12 EA 7/8" X 5-1/2", DOMESTIC
120.00 720.00
24 6 EA 12" 1/8" FULL FACE GASKET, NEOPRENE, 150#10.48 62.88
25 2 EA
12" ADJ SADDLE SUPPORT ZINC PLATED SIZE FOR DIP #S92 STANDON 200.00 400.00
26 2 EA 2" X 24" SCH 40 GALVANIZED NIPPLE DOMESTIC A53 ERW 90.97 181.94
27 1 EA 1" X CLOSE SCH 40 GALVANIZED NIPPLE DOMESTIC A53 ERW 4.61 4.61
28 1 EA
1" DIELECTRIC UNION BRASS X GALV STEEL LEAD FREE 9876 WATTS 79.85 79.85
29 1 EA 1" X 1/4" SCH 40 GALVANIZED BUSHING DOMESTIC 11.57 11.57
30 3 EA 1/4" X 3" SCH 40 BRASS NIPPLE IMPORT 2.06 6.18
31 1 EA 1/4" BRASS BALL VALVE THREADED 9.05 9.05
32 1 EA 1/4" BRASS TEE IMPORT 4.11 4.11
33 13 EA LINK-SEAL LS-475-S EPDM & 316SS FASTENERS 25.57 332.41
FLOW METER VAULT ADDED Subtotal 35,727.94
CHANGES
34 C342,C348,C349,C358 CHANGES
35 4 EA 8" X 2" HDPE DR7 TEE 450.00 1,800.00
36 8 EA 2" SDR 11 FLANGE ADAPTER IPS HDPE MOLDED BUTT FUSION 9.68 77.44
37 8 EA 2" SS BACKING RING 316 142.00 1,136.00
38 1 EA
2" MILLIKEN PLUG VALVE, 125# FLANGED, DI Body, Epoxy Seat, Buna Plug,
316 SS Bearings, PTFE Grit Seals, 8 Mils Epoxy Coating, Lever Operated.
611AE1L
350.00 350.00
39 200 FT 2" SDR 11 IPS HDPE PIPE 100' COIL 3.50 700.00
CHANGES Subtotal 4,063.44
CHANGES
40 C346,C347 CHANGES
41 2 EA
8" 45 ELBOW IPS HDPE MOLDED BUTT FUSION, 335 PSI DESIGN PRESSURE 200.00 400.00
42 1 EA 8" X 2" HDPE DR7 TEE
43 2 EA 2" SDR 11 FLANGE ADAPTER IPS HDPE MOLDED BUTT FUSION 9.68 19.36
44 2 EA 2" SS BACKING RING 316 142.00 284.00
45 1 EA
2" MILLIKEN PLUG VALVE, 125# FLANGED, DI Body, Epoxy Seat, Buna Plug,
316 SS Bearings, PTFE Grit Seals, 8 Mils Epoxy Coating, Lever Operated.
611AE1L
350.00 350.00
46 100 FT 2" SDR 11 IPS HDPE PIPE 100' COIL 1.92 192.00
47 1 PLEASE SEE EMAIL FOR DELETED ITEMS
CHANGES Subtotal 1,245.36
Approximate Grand Total 113,220.20
-4,000.00
$109,220.20
Confirmed with Fowler on 2/5/2024 that we can take this off if all the plug valves can go
through startup and testing at the same time and Tapani said they can. Remove $4,000 Item.
Additional 15% restock fee for these two
items per additional email 2 pages down.
-$13,635.90 / 1.15 = -$11,857.30
-$8,643.96 / 1.15 = -$7,516.49
Last Item No Fee = -$13,920.30
Total = -$33,294.09
To: Tapani INC. ATTN: Brandon Farmer
PROJECT LOCATION: Pasco, WA. Date: 1/31/2024
BID ITEM#Total L.F. EACH
BY: Seth Holan 1/31/24
$12,925.00 TOTAL:
Clarifications/Pricing: Pricing is based on plans labeled City of Pasco - PWRF Phase 2: Winter
Storage. Pricing is based on contractor and INW Precast coming to a mutual aggreable delivery
and build schedule. Product to be delivered to "lay-down" area, off-load by contractor. Truck
time will be charged @ $165.00 an hour per truck after 1st intial hour on-site. Clear access is
required for delivery without any interuptions from other trades or work. Please see WSDOT
Spec. 1-09.3.OPT1.FR1 for fuel surcharge calculation that will be implemented by INW Precast.
Proper sub-grade preparation is critical to the performance of the precast structures. Sales Tax
not included. Inland Northwest Precast is a NPCA approved Plant.
Escalation: Pricing good through 2024 construction season at which time there will be a 5%
escalation charge added to "each" price for each subsequent year structures are needed.
(509) 226-5050
**VETERAN OWNED**
SUBJECT TO ADDITIONAL CHARGES. PRICE SUBJECT TO CHANGE ACCORDINGLY IF THERE ARE REVISIONS
ITEM DESCRIPTION TOTAL
*ABOVE QUOTE IS GOOD FOR 30 DAYS. SALES TAX NOT INCLUDED. ALL QUOTES ARE FOB JOB SITE.
OFF-LOAD BY CONTRACTOR. PRICES ABOVE ARE TRUCKLOAD QUANTITIES ONLY. PARTIAL LOADS ARE
5' x 11' x 7'8" Tall Meter Vault as depicted on sheet C-
366, detail 2. Includes 33" x 66" H-20 rated
Aluminum Hatch. 1 $12,925.00 $12,925.00
**SMALL BUSINESS**Inland Northwest Precast
5516 North Starr Rd PO Box 610
Newman Lake, WA 99025
PROJECT: City of Pasco - PWRF Phase 2 - Winter Storage -
Additional Vault
809 S Auburn St. Kennewick, Washington 99336
(509) 491-1071
January 12, 2024
RE: CPR 06 PWRF Phase 2
Review changes, updated cad files, base drawing, add new points to files. $650.00
Sincerely,
Kevin Bethje P.L.S.
Tapani also plugged in an additional $1500 ROM to survey the
additional scope as needed.
Silverline Electric LLC
4121 W Clearwater Ave
Kennewick, WA 99336
Estimate 23191656
Estimate Date 1/16/2024
Billing Address
Tapani Inc.
1904 Southeast 6th Place # PO Box 1900
Battle Ground, WA 98604 USA
Job Address
PWRF - Process Water Reuse Facility
957 East Foster Wells Road
Pasco, WA 99301 USA
Description of work
Electrical and controls wiring for changes listed in CPR-06
Task #Description Quantity Your Price Total
E- 102 Rough In Labor 16.00 $136.85 $2,189.60
E-100 Material handling / Project Management 5.00 $133.98 $669.90
E-120 Rough in material 1.00 $402.50 $402.50
E-125 Added analog output card to PLC 1.00 $3,831.80 $3,831.80
Sub-Total $7,093.80
Tax $0.00
Total Due $7,093.80
Deposit/Downpayment $0.00
Thank you for choosing Silverline Electric!
I have the authority to order the above work and do so order as outlined above. It is agreed that the seller will retain title to any
equipment or material furnished until final and complete payment is made, and if settlement is not made as agreed, the seller shall
have the right to remove same and the seller will be held harmless for any damages resulting from the removal thereof. In the event of
non-payment of any amounts due, the undersigned agrees to pay reasonable interest on all delinquent monies owed and in the event
of collection agrees to pay all costs of collection including attorney fees. The Service Provider is not responsible for any cosmetic,
equipment or structural damage resulting from the repair or diagnosis of the problem.
Date:1/25/2024
Project Name:PWRF P2 Winter Storage
Contract #242001.01
Job #242001.01
C.O. #6
Description: Short Description
Hours Rate Hours Rate
General Carpenter (Foreman)8" HDPE - Concrete Anchor Wall 45 78.55$ 117.83$ HRS 3,534.94$
General Carpenter 8" HDPE - Concrete Anchor Wall 45 77.32$ 115.99$ HRS 3,479.58$
Labor Sub Total 7,014.52$
Labor Overhead & Profit 0%-$
Labor Total 7,014.52$
Equipment #Equipment Description Units Rate Unit Total
5220174 Crew Truck 45 49.23$ HRS 2,215.35$
Equipment Sub Total 2,215.35$
Equipment Overhead & Profit 0%-$
Equipment Total 2,215.35$
Unit Rate Quantity Unit Total
7,605.00$ 1 7,605.00$
-$
-$
-$
-$
Material Sub Total 7,605.00$
Material Overhead & Profit 0%-$
Material Total 7,605.00$
Unit Rate Quantity Unit Total
9,824.00$ 1 9,824.00$
-$
-$
-$
Sub Contractors Sub Total 9,824.00$
Subcontractor Overhead & Profit 0%-$
Subcontractor Total 9,824.00$
Unit Rate Quantity Unit Total
-$
-$
-$
-$
Other Sub Total -$
Other Overhead & Profit 15%-$
Stipulations Other Total -$
Sub Total 26,658.87$
Accepted by:-$
-$
Date:Total Amount 26,658.87$
This Change increases the time to complete the project by: Day(s)
This proposal is based on the usual cost elements such as labor, material, and normal markups and does not include all costs for additional changes
in the sequence of work, delays, disruptions, rescheduling, extended overhead, overtime (unless specified), acceleration, and/or impact costs; and
the right is expressly reserved to make claim for any and all (if any) of these related items prior to final completion of this contract. Please consider
this language official "notice" as defined in subcontract and/or main contract.
OTHER
Description
N/A
MATERIAL
Material Description
Misc. Formwork, Rebar, Concrete
SUBCONTRACTORS
Subcontractor Description
CIC - Vault Meter Box Coating
Total
EQUIPMENT
Class Name/Description
Straight Time Overtime
Unit
Force Account/ Change Order Worksheet
Plan Change - RH2 requestd (1) additional concrete anchor wall for 8" HDPE sewer washdown line. Along with (2) additonal concrete
anchor walls located on 12" HDPE FM line & coating of one Vault Meter Box.
LABOR
Corporate Office
PO Box 1900
Battle Ground, WA 98604
360.687.1148
See next sheet for CIC quote.