RESOLUTION NO. 4413
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING THE CITY MANAGER TO EXECUTE AMENDMENT NO. 5
FOR THE PROFESSIONAL SERVICES AGREEMENT WITH RH2
ENGINEERING, INC. FOR THE PROCESS WATER REUSE FACILITY
(PWRF) PRETREATMENT IMPROVEMENTS PHASE 2: WINTER STORAGE
CAPACITY.
WHEREAS, the City of Pasco (City) RH2 Engineering, Inc. entered into a Professional
Services Agreement on August 10, 2021, to provide Engineering services with respect to the
Process Water Reuse Facility (PWRF) Improvements project; and
WHEREAS, the City and RH2 Engineering, Inc. entered into Amendment No. 1 on May
9, 2022, to add additional professional engineering (design) services for additional winter storage;
and
WHEREAS, the City and RH2 Engineering, Inc. entered into Amendment No. 2 on July
12, 2022, to add additional professional engineering services required for the acquisition of
additional land from the United States Bureau of Reclamation (USBR); and
WHEREAS, the City and RH2 Engineering, Inc. entered into Amendment No. 3 on
August 26, 2022, to add additional professional engineering services for cultural and
environmental field work and associated reporting for an additional 160-acre parcel owned by the
USBR, and additional permitting support to facilitate the acquisition process being administered
by the USBR to meet funding requirements; and
WHEREAS, the City and RH2 Engineering, Inc. entered into Amendment No. 4 on
January 6, 2023, to add additional professional engineering services for supporting the future
operations of the facility by interconnecting ponds, coordinating work between the multiple
ongoing phases of the project at the PWRF site, funding assistance, and limited construction
support; and
WHEREAS, the City Council of the City of Pasco, Washington, has after due
consideration, determined that it is in the best interest of the City of Pasco to enter into Amendment
No. 5 to allow RH2 Engineering, Inc. to provide additional professional engineering services
during construction including construction contract administration, and project management duties
in compliance with the Federal regulations of the Clean Water State Revolving Fund (CWSRF)
loan.
DocuSign Envelope ID: CFBF8E9F-F420-42C8-B6AB-7388ED2BE739
Resolution - PWRF Phase 2 Amend No. 5 w/ RH2 Agreement - 2
Version 10.25.23
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PASCO, WASHINGTON:
That the City Council of the City of Pasco approves the terms and conditions of
Amendment No. 5 between the City of Pasco and RH2 Engineering, Inc. as attached hereto and
incorporated herein as Exhibit A.
Be It Further Resolved, that the City Manager of the City of Pasco, Washington, is hereby
authorized, empowered, and directed to execute said Amendment No. 5 on behalf of the City of
Pasco; and to make minor substantive changes as necessary to execute the Agreement.
Be It Further Resolved, that this Resolution will take effect immediately.
PASSED by the City Council of the City of Pasco, Washington, on this 16th day of January,
2024.
_____________________________
Pete Serrano
Mayor
ATTEST: APPROVED AS TO FORM:
_____________________________ ___________________________
Debra Barham, CMC Kerr Ferguson Law, PLLC
City Clerk City Attorneys
DocuSign Envelope ID: CFBF8E9F-F420-42C8-B6AB-7388ED2BE739
Amendment No. 5 to RH2 Engineering, Inc. PSA
Process Water Reuse Facility Pretreatment Improvements – Phase 2: Winter Storage Page 1
AMENDMENT NUMBER 5 to
PROFESSIONAL SERVICES AGREEMENT
Process Water Reuse Facility Pretreatment Improvements – Phase 2: Winter Storage
PROJECT No. 21298
AGREEMENT NO. 21-039
WHEREAS, the City and RH2 Engineering, Inc., entered into a Professional Services
Agreement on August 10, 2021, to provide engineering services with respect to the Process Water
Reuse Facility (PWRF) Improvements project; and
WHEREAS, as the Phase 2 project progressed, RH2 Engineering and City Staff have
identified additional need for winter storage capacity; and
WHEREAS, the City and RH2 Engineering, Inc. entered into Amendment No. 1 on May
9, 2022, to add additional professional engineering (design) services for additional winter storage ;
and
WHEREAS, the City and RH2 Engineering, Inc. entered into Amendment No. 2 on July
12, 2022, to add additional professional engineering services required for the acquisition of
additional land from the United States Bureau of Reclamation (USBR); and
WHEREAS, the City and RH2 Engineering, Inc. entered into Amendment No. 3 on
August 26, 2022, to add additional professional engineering services for cultural and
environmental field work and associated reporting for an additional 160-acre parcel owned by the
USBR, and additional permitting support to facilitate the acquisition process being administered
by the USBR to meet funding requirements; and
WHEREAS, the City and RH2 Engineering, Inc. entered into Amendment No. 4 on
January 6, 2023, to add additional professional engineering services for supporting the future
operations of the facility by interconnecting ponds, coordinating work between the multiple
ongoing phases of the project at the PWRF site, funding assistance, and limited construction
support; and
WHEREAS, the City Council of the City of Pasco, Washington, has after due
consideration, determined that it is in the best interest of the City of Pasco to enter into Amendment
No. 5 to allow RH2 Engineering, Inc. to provide additional professional engineering services
during construction including construction contract administration, and project management duties
in compliance with the Federal regulations of the Clean Water State Revolving Fund (CWSRF)
loan.
NOW, THEREFORE, this Agreement is amended to allow RH2 Engineering, Inc., to
provide additional professional engineering services during construction as described on Exhibit
A.
DocuSign Envelope ID: CFBF8E9F-F420-42C8-B6AB-7388ED2BE739
Amendment No. 5 to RH2 Engineering, Inc. PSA
Process Water Reuse Facility Pretreatment Improvements – Phase 2: Winter Storage Page 2
1. Scope of Work:
See Exhibit A
2. Fee:
The compensation for the work is based on a Time and Materials Basis not to exceed the
amount of $1,357,001.00 for a total authorization amount of $3,532,601.00. See Exhibit
B.
3. Time of performance:
The services shall be complete for the project on or before December 31, 2024.
DATED THIS _____ DAY OF _____________________________, 2024.
CITY OF PASCO, WASHINGTON CONSULTANT
Adam R. Lincoln, City Manager, RH2 Engineering, Inc. Paul Cross, PE -
Principal
DocuSign Envelope ID: CFBF8E9F-F420-42C8-B6AB-7388ED2BE739
1
12/13/2023 11:36:41 AM \\CORP.RH2.COM\DFS\PROJECTS\DATA\PSC\21-0236\00 CONTRACT\A-5\AMEND NO. 5_SOW_PWRF PH 2 SDC-REGULAR.DOCX
EXHIBIT A
Scope of Work
Amendment No. 5
City of Pasco
Process Water Reuse Facility Improvements – Winter Storage
Regular Services During Construction
December 2023
Background
The City of Pasco (City) has requested that RH2 Engineering, Inc., (RH2) provide regular construction
observation and contract administration services for the Process Water Reuse Facility (PWRF)
Improvements – Phase 2: Winter Storage Project. This Amendment is additive to Contract
Amendment No. 4 for limited services during construction (SDC). It is anticipated the project will start
in December 2023 and be finalized in May 2025 based on allotted working days for the contractor.
Task 8 – Services During Construction (Regular)
Objective: Provide engineering services, construction contract administration, and project
management during the construction phase of the project. This Task is additive to Contract
Amendment No. 4, Task 8.
Approach:
Provide project administration services during construction, including staff scheduling,
recordkeeping and filing, and project invoicing. Provide monthly billing invoices, including a
detailed breakdown of RH2 staff hours. Include a summary of expenditures, percentage
complete, and budget remaining. Coordinate with the City’s project manager on a regular
basis to discuss project and task status.
Manage RH2 ShareFile site for uploading and managing project documents.
Review and track contractor Statements of Intent to Pay Prevailing Wages and Certified
Payrolls. Perform wage rate interviews with contractor’s employees.
Prepare and distribute meeting agendas/minutes for weekly on-site construction meetings
Monitor burrowing owl activity on the U.S. Department of Reclamation’ (Reclamation) and
SE Reclamation parcels and coordinate with the Washington Department of Fish and Wildlife
on burrow abandonment or owl relocation. It is anticipated that trail cameras will be used to
monitor owl burrows during December.
Attend weekly on-site construction meetings.
Provide daily correspondence and coordination with City, contractor, and agencies.
Provide additional part-time construction observation services. The intent of the on-site
observation is to observe the quality and compliance of the work with the construction
DocuSign Envelope ID: CFBF8E9F-F420-42C8-B6AB-7388ED2BE739
City of Pasco Exhibit A
PWRF Improvements – Winter Storage Scope of Work
Regular SDC Amendment No. 5
2
12/13/2023 11:36:41 AM \\CORP.RH2.COM\DFS\PROJECTS\DATA\PSC\21-0236\00 CONTRACT\A-5\AMEND NO. 5_SOW_PWRF PH 2 SDC-REGULAR.DOCX
contract plans and specifications. The Fee Estimate is additive to Contract Amendment No. 4,
subtask 8.6 and reflects approximately twenty-four (24) hours per week of on-site
observations by an RH2 representative for the duration of the construction period (assumed
to be eighty-eight (88) weeks). Notify the contractor and the City of work that has been
observed to have not been completed in accordance with the plans and specifications and
discuss rectification. Review pay requests from the contractor and forward approved pay
requests to the City for processing. Prepare progress reports, including construction contract
time remaining statements and weekly statements of working days.
Subcontract with a testing agency to provide electronic leak detection services for the
103 million gallon (MG), 106 MG, and 120 MG lagoons using the water puddle testing
method.
Attend final contractor inspection with City staff and prepare a punchlist.
Prepare a letter recommending project acceptance and project closeout documents following
completion of construction.
Assumptions:
• Contract Amendment No. 4, subtask 8.8 originally assumed sixteen (16) hours of part-time
construction observation services for fifty-two (52) weeks. Additional hours and duration have
been included in subtask 8.17 to account for RH2 providing regular SDC services and the
contract being longer than originally anticipated.
• Trail cameras and burrowing owl traps will be used for subtask 8.15. Rental costs for the trail
cameras and material costs for burrowing owl traps will be billed to the project.
• A UTV will be used for subtask 8.18 to access the site. RH2 will provide an accompanying
invoice for the UTV rental with RH2’s monthly billing.
• Subtask 8.19 will require RH2 to issue a change proposal for the PWRF Phase 2 contractor
(Tapani, Inc.) to provide a water truck, up to 500 feet of hose, 5,000 gallons per day of City or
well water, and one (1) to two (2) laborers to assist with handling and operation of the hoses
and water truck for the testing agency performing the electronic leak detection service. The
leak detection survey may take up to twenty (20) working days.
Provided by City:
• Attendance at weekly construction meetings.
RH2 Deliverables:
• Attendance at weekly construction meetings, agenda, and meeting minutes in electronic PDF.
• Written responses to pay requests in electronic PDF.
• Part-time construction observation.
DocuSign Envelope ID: CFBF8E9F-F420-42C8-B6AB-7388ED2BE739
City of Pasco Exhibit A
PWRF Improvements – Winter Storage Scope of Work
Regular SDC Amendment No. 5
3
12/13/2023 11:36:41 AM \\CORP.RH2.COM\DFS\PROJECTS\DATA\PSC\21-0236\00 CONTRACT\A-5\AMEND NO. 5_SOW_PWRF PH 2 SDC-REGULAR.DOCX
• Progress reports, observation reports, construction contract time remaining statements, and
weekly statements of working days in electronic PDF.
• Electronic leak detection survey report.
DocuSign Envelope ID: CFBF8E9F-F420-42C8-B6AB-7388ED2BE739
EXHIBIT B
Fee Estimate
Amendment No. 5
City of Pasco
PWRF Improvements Phase 2 - Winter Storage
Services During Construction
Dec-23
Description
Total
Hours
Total Labor Total
Subconsultant
Total Expense Total Cost
Task 8 Services During Construction (Regular)5356 1,084,953$ 218,500$ 53,548$ 1,357,001$
PROJECT TOTAL 5356 1,084,953$ 218,500$ 53,548$ 1,357,001$
\\corp.rh2.com\dfs\Projects\Data\PSC\21-0236\00 Contract\A-5\Amend No. 5_FEE_PWRF PH 2 SDC-Regular 12/19/2023 9:22 AM
DocuSign Envelope ID: CFBF8E9F-F420-42C8-B6AB-7388ED2BE739
RATE LIST RATE UNIT
Professional I $169 $/hr
Professional II $184 $/hr
Professional III $207 $/hr
Professional IV $226 $/hr
Professional V $240 $/hr
Professional VI $259 $/hr
Professional VII $280 $/hr
Professional VIII $293 $/hr
Professional IX $311 $/hr
Technician I $130 $/hr
Technician II $144 $/hr
Technician III $162 $/hr
Technician IV $177 $/hr
Technician V $192 $/hr
Technician VI $211 $/hr
Technician VII $229 $/hr
Technician VIII $239 $/hr
Control Specialist I $170 $/hr
Control Specialist II $185 $/hr
Control Specialist III $208 $/hr
Control Specialist IV $227 $/hr
Control Specialist V $240 $/hr
Control Specialist VI $259 $/hr
Control Specialist VII $276 $/hr
Control Specialist VIII $289 $/hr
Control Specialist IX $289 $/hr
Control Technician I $130 $/hr
Control Technician II $144 $/hr
Control Technician III $165 $/hr
Control Technician IV $177 $/hr
Control Technician V $192 $/hr
Control Technician VI $211 $/hr
Control Technician VII $229 $/hr
Control Technician VIII $239 $/hr
Administrative I $87 $/hr
Administrative II $102 $/hr
Administrative III $120 $/hr
Administrative IV $144 $/hr
Administrative V $168 $/hr
CAD/GIS System $27.50 $/hr
CAD Plots - Half Size $2.50 price per plot
CAD Plots - Full Size $10.00 price per plot
CAD Plots - Large $25.00 price per plot
Copies (bw) 8.5" X 11"$0.09 price per copy
Copies (bw) 8.5" X 14"$0.14 price per copy
Copies (bw) 11" X 17"$0.20 price per copy
Copies (color) 8.5" X 11"$0.90 price per copy
Copies (color) 8.5" X 14"$1.20 price per copy
Copies (color) 11" X 17"$2.00 price per copy
Technology Charge 2.50%% of Direct Labor
Night Work 10.00%% of Direct Labor
Mileage $0.6550
price per mile
(or Current IRS Rate)
Subconsultants 15%Cost +
Outside Services at cost
EXHIBIT C
RH2 ENGINEERING, INC.
2024 SCHEDULE OF RATES AND CHARGES
Rates listed are adjusted annually.
DocuSign Envelope ID: CFBF8E9F-F420-42C8-B6AB-7388ED2BE739
EQUIPMENT RATE UNIT
Pressure Data Logger 30$ $/Day
120$ $/Week
360$ $/Month
Set of 2 Hose Monster Assemblies 50$ $/Day
200$ $/Week
600$ $/Month
Set of 6 Pressure Data Loggers 180$ $/Day
720$ $/Week
2,160$ $/Month
Set of 2 Hose Monster Assemblies w/ 6 Pressure Data Loggers 230$ $/Day
920$ $/Week
2,760$ $/Month
Set of 2 Hose Monster Assemblies w/ 9 Pressure Data Loggers 320$ $/Day
1,280$ $/Week
3,840$ $/Month
EQUIPMENT RATE UNIT
Coco-80 w/ 4 Accelerometers 80$ $/Pump
320$ $/Day
960$ $/Week
ITIG-II Model C w/ test probes 90$ $/Pump
360$ $/Day
1,080$ $/Week
ITIG-II and Power Pack w/ test probes 190$ $/Pump
760$ $/Day
2,280$ $/Week
PowerSight 3500 w/ test probes 15$ $/Pump
60$ $/Day
180$ $/Week
FLIR E8 WIFI Thermal Camera 15$ $/Pump
60$ $/Day
180$ $/Week
EQUIPMENT RATE UNIT
Articulating Boroscope 200$ $/Day
Thru-Coat Thickness Gauge 200$ $/Day
Dry Film Thickness Gauge 50$ $/Day
Wenner 4-Pin Method 200$ $/Day
AWWA Soil Testing 150$ $/Sample
135$ $/Day
Rectifier 540$ $/Week
1,620$ $/Month
EQUIPMENT RATE UNIT
Drone with Operator at Professional Rate not Inlcuded 50$ $/Hr
100$ $/Day
400$ $/Week
Trail Camera 55$ $/Month
SPECIAL EQUIPMENT - DRONES AND CAMERAS
CORROSION EQUIPMENT
RH2 EQUIPMENT RENTAL RATES
SYSTEM FLOW AND PRESSURE TESTING EQUIPMENT
SPECIAL EQUIPMENT - PUMP AND MOTOR TESTING