HomeMy WebLinkAbout4347 Resolution - Lewis Street Overpass Change Orders 18-21RESOLUTION NO.4347
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDERS
NO. 18 - 21 TO THE CONSTRUCTION CONTRACT WITH CASCADE
BRIDGE, LLC. FOR THE LEWIS STREET OVERPASS PROJECT.
WHEREAS, the City of Pasco (City) and Cascade Bridge, LLC. entered into a
Construction Contract on March 1, 2021, to provide for the construction of the Lewis Street
Overpass Project; and
WHEREAS, this project involves the construction of a new 562-foot, 4-span, pre -stressed
concrete overpass, over the BNSF Railway yard and a new 63-foot, voided slab overpass over First
Avenue, along with roadway improvements, backfllling, partial structure removal, retaining wall
construction, earthwork, paving with HMA, landscaping, storm drainage, illumination, water
mains, sanitary sewer, and other associated work; and
WHEREAS, the City and Cascade Bridge, LLC. executed Change Order Nos. 1 - 11 to
provide for additional work not included in the original contract; and
WHEREAS, previously approved Change Order Nos. 1 - 6 were authorized under the
authority provided to the City Manager and the Public Works Director; and
WHEREAS, Change Order No. 7 was approved by Council on October 3, 2022; and
WHEREAS, Change Order Nos. 8 - 11 were approved by Council on November 21, 2022;
and
WHEREAS, Change Order Nos. 12 — 17 were approved by Council on April 17, 2023;
and
WHEREAS, the $1,223,967.32 amount of Change Order Nos. 18 - 21, added to the
cumulative sum of previously approved change orders, exceeds the estimated budget and requires
Council's approval of a Budget Amendment.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PASCO, WASHINGTON:
That Change Order Nos. 18 - 21 to Cascade Bridge, LLC. are hereby approved by City
Council.
Be It Further Resolved that the City Manager of the City of Pasco, Washington, is hereby
authorized, empowered, and directed to execute Change Order Nos. 18 - 21, a copy of which is
attached hereto, and incorporated herein by this reference as Exhibit A, on behalf of the City of
Pasco.
Resolution — Lewis Street Overpass project - CO 18 - 21 - 1
PASSED by the City Council of the City of Pasco, Washington, and approved as provided
by law on this 1st day of May 2023.
I
Blanche Barajas
Mayor
ATTEST:
IU6 C- -& k- -
Debra Barham, CMC
City Clerk
APPROVED AS TO FORM:
Resolution — Lewis Street Overpass project - CO 18 - 21 - 2
EXHIBIT A
r�
CITY OF PASCO
rliko PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 18
❑ Standard
101
❑ Unilateral
Project No: Project No: 13007 Project Title: Lewis Street Overpass
FED -AID #. STPUS-HLP-3530(006)
WSDOT: TA4087
Contractor: Cascade Bridge LLC
Reason for Change: BNSF Bridge S3 Rebar Modification
Detail as Appropriate: On the BNSF Bridge the planned S3 bars allowed for only 1/2" clearance between the bar and the
bottom of the block out of the barrier. JUB has issued a change to have Cascade Bridge
refabricate new bar so that there is a min of 2" concrete cover.
This change order covers the cost to refabricate 4,488 S3 dowel bars, and remove and replace
the 1,264 S3 bars already installed. Schedule impacts for this have not been quantified yet, and
will be addressed on a later change order if determined valid.
Schedule impacts may include additional contract time and/or additional costs associated with this
time.
Contract Bid Amount: $22,344,999.88
SALES TAX @ 8.6%:
Total: $ 22,344,999.88
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $694,532.34
Subtotal $41,160.96
Sales tax (rate varies) $17,296.43
Sales tax @ 8.9%
Total $711,828.77
Total $41,160.96
Total Change Orders To Date $752,989.73
New Contract Amount $23,097,989.61
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER NO
Contract Time Prior to this Change Order ................................. 530
Modification to Contract time by this Change Order .................... 0
Revised Total Contract Time .................................................... 530
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the
compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order.
Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the
previously executed Contract Documents shall apply to this Change Order
AGREED TO AND ACCEPTED:
CONTRACTOR
APPROVED:
APPROVED:
PROJECT MANAGER Date
APPROVED:
CONST. MANAGER Date CIP MANAGER Date PUBLIC WORKS DIRECTOR Date
Add the Following Bid Items:
Bid Item:
A181 BNSF Bridge S3 Rebar Modification 1 LS $ 41,160.96
Sales Tax 8.9%
Subtotal, Additions ..............................................
Total this Change Order ............•••••..••...•.•••••.••••.......•••• $ 41,160.96
EXHIBIT A
CITY OF PASCO
IdSCO PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 19
❑ Standard
❑ Unilateral
Project No: Project No: 13007 Project Title: Lewis Street
FED -AID #: STPUS-HLP-3530(006)
WSDOT: TA4087
Contractor: Cascade Bridge LLC
Reason for Change: SEW Subsurface Delay
Detail as Appropriate: When excavating for Structural Earth Walls 1, 2, 3, 4, 7 and 8, the Contractor discovered:
unstable soil, foundation walls from the previous structure, tunnels and stair cases, abandoned fuel
tanks, and significant amounts of debris. Upon consulting with JUB and GPI (Geotech firm), the
City approved Cascade Bridge to proceed on force account to remove debris and improve the
subgrade in the area below the walls.
The City has agreed to extend the contract time 60 days due to these issues, with 57 days being
compensable.
Contract Bid Amount:
SALES TAX @ 8.6%:
Total:
$22,344,999.88
$ 22,344,999.88
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $735,693.30
Subtotal $848,788.71
Sales tax (rate varies) $17,296.43
Sales tax @ 8.9%
Total $752,989.73
Total $848,788.71
Total Change Orders To Date
New Contract Amount
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
Revised Total Contract Time .................................................
$1,601,778.44
$23,946,778.32
YES
530
60
590
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the
compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order.
Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the
previously executed Contract Documents shall apply to this Change Order.
AGREED TO AND ACCEPTED:
CONTRACTOR Date
APPROVED:
PROJECT MANAGER Date
APPROVED: APPROVED:
EXHIBIT A
CONST. MANAGER Date CIP MANAGER Date PUBLIC WORKS DIRECTOR Date
Add the Following Bid Items:
Bid Item:
A182 SEW Subsurface Delay 1 LS $ 848,788.71
Sales Tax 8.9%
Subtotal, Additions ......••..••..••...........• ..•.....
Total this Change Order ............................ ................. $ 848,788.71
EXHIBIT A
Project No
CITY OF PASCO
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO.20
❑ Standard
❑ Unilateral
Project No: 13007 Project Title: Lewis Street Ove
FED -AID #: STPUS-HLP-3530(006)
WSDOT: TA4087
Contractor: Cascade Bridge LLC
Reason for Change: Modification to Girder Sweep Means and Methods
Detail as Appropriate: BNSF stated that they will not allow a girder with a horizontal sweep out of tolerance to be set and
remediated after placement. To reduce the risk of a girder being out of tolerance at time of
placement, Cascade Bridge modified their means and methods planned at bid time to include pre -
measuring the girder sweeps before the track window, to ensure all girders were in tolerance. This
change order covers the cost of the pre -measurement of the girder sweeps; the cost and time was
tracked as force account.
Contract Bid Amount:
SALES TAX @ 8.6%:
Total:
$22,344,999.88
$ 22,344,999.88
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $1,584,482.01
Subtotal $77,192.65
Sales tax (rate varies) $17,296.43
Sales tax @ 8.9%
Total $1,601,778.44
Total $77,192.65
Total Change Orders To Date $1,678,971.09
New Contract Amount $24,023,970.97
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order .................................
Modification to Contract time by this Change Order ....................
Revised Total Contract Time ....................................................
590
590
NO
It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the
compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order.
Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the
previously executed Contract Documents shall apply to this Change Order.
AGREED TO AND ACCEPTED:
CONTRACTOR Date
APPROVED:
APPROVED:
PROJECT MANAGER Date
APPROVED:
CONST. MANAGER Date CIP MANAGER Date PUBLIC WORKS DIRECTOR Date
Add the Following Bid Items:
Bid Item:
A183 Modification to Girder Sweep Means and Me
Sales Tax 8.9%
Subtotal, Additions .............................. ................
Total this Change Order -••••-.......• ............••• ..I....... •••
EXHIBIT A
LS $ 77,192.65
$ 77,192.65
EXHIBIT A
CITY OF PASCO
Va-,A 3 PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 21
r 19,, Standard
IEl Unilateral
Project No: Projed NO: 13007 Project Title: Lewis Street
FED -AID C STPUS44LP-3530(006)
WSDOT: TA4087
Contractor: Cascade Midge LLC
Reason for Change: Modified Approach Slab - Sleeper Slab and Stn Seal
Detall as Appropriate: This change order eliminates the planned expansion joint at the BNSF Bridge (25-foot) approach
slabs, and replaces them with 20-foot approach slabs, sleeper slabs, strip seals, and Conduit
defiedion fittings to better accommodate the expansion and contraction of decorative steel and
handrail on the BNSF Bridge.
The original bid Item, A-055, SR Approach Slab BNSF Structure, will be Changed to "No Pay" in the
pay estimate and two new bid time will be added.
Plan sheets BG-125, BG-129, BG-131, BG-132, BG-133, and BG-134 have been reissued to reflect
this change.
Schedule Impacts for this change have not been quardified yet and wig be addressed on a later
change order if determined valid. Schedule Impacts may include additional Contract time and/or
additional costs associated with this time.
Contract Bid Amount: $22,344,999.88
SALES TAX @ 8.6%:
Total: $ 22,344,999.88
PREVIOUS CHANGE ORDER
CURRENT CHANGE ORDER
Subtotal $1.661 674.66
Subtotal $256,825.00 J
Saies tax (rate varies) $17,296.43
Sales tax {St 8.9%
Total $1,678,971A9
Total $256,825.00
Total Change Orders To Date $ 1,935,796.09
Now Contract Amount $ 24,280,795.97
IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER
Contract Time Prior to this Change Order ................................. 460
Modification to Contract time by this Change Order.. .................. 0
Revised Total Contract Time ........................ ............................ 460
im
It Is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the
compensation for this Change Order Is full and complete and Is the only compensation due or awing for this Change Order.
Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the
previously executed Contract Documents shag apply to this Change Order.
RED �Ar4/19/23
/� ZPROJECT MANAGER Date
APPROVED: APPROVED:
CONST. MANAGER Date CIP MANAGER [No PUBLIC WORKS DIRECTOR Dale
Add the Following Bid hems:
Bid Item:
A-194 BNSF Bridge - Approach and 1 LS $159,075.00
Sleeper Slab
A-185 BNSF OrMe -Strip Seal • 1 LS $ 97, 750.00
Sales Tax 6.9%
Subtotal, Ad&f10 s..............................................
Total this Change Ordtir ...... ............... .......I......."-..... $ 266,826.00
Change Order 18-21 Summary
Change Order 018 - BNSF Bridge S3 Rebar Modification $41,160.96
On the BNSF Bridge the planned S3 bars allowed for only 1/2" clearance between the bar and
the bottom of the block out of the barrier. JUB has issued a change to have Cascade Bridge
refabricate new bar so that there is a min of 2" concrete cover. This change order covers the
cost to refabricate 4,488 S3 dowel bars, and remove and replace the 1,264 S3 bars already
installed. Schedule impacts for this have not been quantified yet, and will be addressed on a
later change order if determined valid.
Change Order 019 — SEW Subsurface Delay $848,788.71
When excavating for Structural Earth Walls 1, 2, 3, 4, 7 and 8, the Contractor discovered:
unstable soil, foundation walls from the previous structure, tunnels and stair cases, abandoned
fuel tanks, and significant amounts of debris. Upon consulting with JUB and GPI (Geotech firm),
the City approved Cascade Bridge to proceed on force account to remove debris and improve
the subgrade in the area below the walls. The City has agreed to extend the contract time 60
days due to these issues, with 57 days being compensable.
Change Order 020 - Modification to Girder Sweep Means and Methods $77,192.65
BNSF stated that they will not allow a girder with a horizontal sweep out of tolerance to be set
and remediated after placement. To reduce the risk of a girder being out of tolerance at time of
placement, Cascade Bridge modified their means and methods planned at bid time to include
pre -measuring the girder sweeps before the track window, to ensure all girders were in
tolerance. This change order covers the cost of the pre -measurement of the girder sweeps; the
cost and time was tracked as force account.
Change Order 21: Modified Approach Slab — Sleeper Slab and Strip Seal $256,825.00
This is a design error. JUB realized in late 2022 that they had designed the wrong style of approach slab
for the BNSF bridge and reissued several sheets. The change reduces the length of the approach slab,
adds a sleeper slab, changes the expansion joint type, and modifies the flexible coupling in the barrier.
While the amount shows $256,825.00, this does not take into account that the original bid item for the
BNSF approach slab, A-055, will be marked as NO PAY on the estimate, as per direction from the City.