HomeMy WebLinkAboutC& E Trenching LLC - Change Order #1 Rd 100 & Maple Dr Improvments 21-999ACITY OF PASCO PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 1 Project No: 21-999A Project Title: Road 100 & Maple Dr Improvements Contractor: C&E Trenching, LLC Description of Change: RFC 01: Tree Removal Detail as Appropriate: Contract Bid Amount: $ 954,929.00 SALES TAX @ 8.7%(SCh B): $ 47,415.52 Total: $ 1,002,344.52 PREVIOUS CHANGE ORDER CURRENT CHANGE ORDER Subtotal Subtotal $ 5,324.00 Sales tax @ 8.7% $ - Sales tax @ 8.7% N/A Total $ _____:__,Total $ 5,324.00 Total Change Orders To Date $ 5,324.00 New Contract Amount $ 1,007,668.52 IS CONTRACT TIME AFFECTED BY THIS CHANGE ORDER r–Y–E--S-1 NO Contract Time Prior to this Change Order.................................60 _ Modification to Contract time by this Change Order .................... _ 10 revised Total Contract Time .................................................... 70 It is mutually agreed by both parties that this Change Order fully describes the change(s) that is (are) being made and that the compensation for this Change Order is full and complete and is the only compensation due or owing for this Change Order. Further, it is mutually agreed that this document will supplement the present Contract Documents and that the provisions of the previously executed Contract Documents shall apply to this Change Order. AGREED TO AND ACCEPTED: APPROVED: 8-18-22 CONTRACTOR Date PROJECT MANAGER Date APPROVED: PRO l , - r`4�' 4:ONST. MANAGER Date CIP MANAGER Date _ UBLI ORS Date DIRECTOR C&E Trenching LLC PO Box 3788 Pasco, WA 99302 Phone: (509) 545-6940 Fax: (509) 545-8671 To: City of Pasco PO Box 293 Pasco, WA 99301 Project: Road 100 and Maple Dr Extensio RFC No: 01 Date: 7/13/2022 Description: Cost to Remove tree's see invoices attached for cost support. Pricing assume chips from stumps can be left onsite or on the Fire station property. Please add 10 days to the contract with this Change. Subcontractor Cost $4,840.000 Mark up $484.00 The above work is subject to the same conditions as specified in the original contract unless otherwise stipulated. Upon approval the sum of $5,324.00wii1 be added to the contract price. Original Contract $954,929.00 Other Approved Change Orders $0.00 Total Contract to Date $954,929.00 This Request $5,324.00 Other Pending Requests $0.00 Total Contract plus Pending RFCs $960,253.00 8/10/22 Authorized Signature: c=m� �� Date: C&E Trenching L Authorized Signature: Date: p Irl - ity of Pasco ZZ-