HomeMy WebLinkAboutT Bailey, Inc - Zone 3 Reservoir Storage DBIA Contract - Change Order No. 3Phase 1 Contract Change Order City of Pasco PO Box 2931626 N. V Ave. Pasco, WA. 99301 PHASE 1 CHANGE ORDER T Bailey, Inc. 9628 South Marchs Point Rd. Anacortes, WA 98221 Project Name: Zone 3 Reservoir Storage Tank Change Order#: 3 Net change by previous authorized Chane Orders Description of Change Change in Change in COR# $6,399,163.69 Contract Time Phase 1 NTE a Early construction work listed below and further described in 52 working days $3,402,098.04 Exhibit A*. Mobilization, implement TESC (Temporary Erosion and Sediment Control), install construction entrance and access driveway, clear and grub both tank and lay down sites, rough grade of both tank and lay down sites, tank foundation subgrade, install tank foundation and ring wall, install mechanical improvements beneath proposed floor slab including ringwall penetrations, install all electrical and control conduit beneath proposed floor slab including rinciwall penetrations b Raw Steel Advanced Acquisition further described in Exhibit A* 10 working days $2,000,000.00 *The amount of this Change Order includes Design -Builder's Fee Percentage as well as a contingency to account for underground changed conditions for work associated with Exhibit A, and escalation in price of materials from the date of Exhibit A. Any savings in the Phase 1 Not to Exceed Amount shall accrue to Owner. Notwithstanding Section 6.2.3 of the Design -Build Agreement, the Cost of the Work included in this Change Order shall be excluded from the Cost of the Work when calculating the Lump Sum Fee. Original Phase 1 Not to Exceed Amount $388,691.76 Net change by previous authorized Chane Orders $608,373.89 Total net [check one] X Increase! ❑ Decrease in the Phase 1 NTE by this Change Order $5,402,098.04 New Phase 1 NTE including this Change Order $6,399,163.69 The new Contract Time including this Change Order is: New Phase 1 Completion -bate February 15, 2023 New Interim Milestone Dates: The changes in the Phase 1 Not to Exceed Amount and Contract Time identified in this Change Order include all costs and time extensions associated with performing the changes set forth herein. City of Pas By: ture Printed Pame Title: Date: Design -Builder By: Signature Gene Tanaka Printed Name Title: President _ Date: smim Y City of Pasco September 2022 Zone 3 Reservoir Phase 1: Change Order 3 EXHIBIT Q Description of Change Authorization to proceed with the initial phase of construction concurrent with the final negotiation of the GMP and execution of the Phase 2 contract. This change order provides TBI an opportunity to potentially complete the reservoir foundation and ring wall installation prior to winter weather occurring (based on historical weather records). It is intended that costs and tasks associated with this change order be deducted from the Phase 2 contract and the GMP. Work included in this change order is as follows. • Mobilization • TESC • Construction entrance and construction access driveway installation • Tank site and PSD site clearing and grubbing • Tank site and PSD site construction grading (final grading to be accomplished within Phase 2 contract) • Tank foundation subgrade installation • Tank foundation and ring wall installation • Mechanical improvements penetrating the ringwall and beneath the proposed floor slab • Electrical and control conduit installation penetrating the ringwall and beneath the proposed floor slab • Advance acquisition of Raw Steel for tank fabrication. Items specifically not included with this change order include, but are not limited to, the following. • Tank floor slab • Tank shell and coating • Off-site utilities • Road 90 and otherwise permanent tank site access • Tank site pond excavation or rock • Tank site and PSD site finished grading • Mechanical and electrical improvements on-site or within the tank (unless specifically identified as being included). • Tank site paving, fencing, restoration, or other site improvements unless identified as being included. NOTE: this change order is not intended to include items not specifically identified in the provided itemization of work. Any remaining items will be included in the GMP Phase 2 agreement. 9/8/2022 11:19 AM\\EPSILON\Engineering\Engineering Working Folder\+Proj-Water\21252 - Zone 3 Reservoir Storage\05-Construction Phase\Change Orders\CO #3 Early Site Development\CO3 Description.docx City of Pasco September 2022 Zone 3 Reservoir Phase 1: Change Order 3 Bid Item Work Brea kdown A summary of the work included in the pricing for each bid item is as follows. Item 1. Mobilize labor and equipment for the initial work. Includes PM, insurances, bond, and B&0 tax associated with this initial work. Item 2. Install all TESC. 5% of TESC not included related to costs for TESC upkeep and removal and the conclusion of the project. Item 3. None. Item 4. Tank site clearing and grubbing, and excess grading on the PSD site. Item 5. Foundation excavation (not including pond excavation or quarry spalls). Item 6. Backfill excavation with crushed rock and prepare foundation subgrade. Item 7. None. Item 8. None. Item 9. PSD clearing, grubbing, and grading. Item 10. None. Item 11. None. Item 12. None. Item 13. Foundation and ringwall. Floor slab not included. Item 14. Raw steel advanced purchase. Item 15. Mechanical penetrations through ringwall and beneath floor slab. Item 16. None. Item 17. Electrical and control conduits through ringwall and beneath floor slab. Item 18. None. Item 19. None. Item 20. None. Item 21. None. 9/8/2022 11:19 AM\\EPSILON\Engineering\Engineering Working Folder\+Proj-Water\21252 - Zone 3 Reservoir Storage\05-Construction Phase\Change Orders\CO #3 Early Site Development\CO3 Description.docx City of Pasco Zone 3 Reservoir Cost Breakdown September 2022 Phase 1: Change Order 3 Item Description MOB, DEMOB, CLEAN UP TEMP EROSION AND SEDIMENTATION CONTROL TRENCH SAFETY AND SHORING SITE WORK EXCAVATION BACKFILL Change Order #3 % of Adjusted Overall Contingency Work for CO #3 19 95 1 $262,200 2 $147,250 3 $ - 4 $148,750 $315,000 35 $35,000 5 90 $90,000 6 $427,500 _ 95 $142,500 7 CRUSHED ROCK $ - 8 SITE UTILITIES $ - 9 OFFSITE IMPROVEMENTS $268,650 27 $ 54,000 10 CONNECTION TO EXISTING WATER MAIN $ - 11 CATHODIC PROTECTION $ - 12 SHOP DRAWING PREP & RESERVOIR COMPONENTS STRUCTURAL CALCULATION RESERVOIR FOUNDATION $ - 13 $1,116,955 97 $48,500 14 RESERVOIR STRUCTURE AND APPURTENANCES $ - 15 RESERVOIR MECHANICAL RESERVOIR FINISHES $30,000 30 $6,000 16 $ - 17 ELECTRICAL $31,500 15 $6,000 18 AUTOMATIC CONTROL $ - 19 CONSTRUCTION RECORDS AND O&M MANUALS $ - 20 TESTING, STARTUP AND TRAINING $ - 21 MINOR CHANGE $ - SUBTOTAL of COST ITEMS $2,747,805.00 $382,000.00 WSST @ 8.7% $239,059.04 $33,234.00 TOTAL w/ WSST INCLUDED $2,986,864.04 $415,234.00 CONTINGENCY $415,234.00 TOTAL COST w/ CONTINGENCY for CO#3 $3,402,098.04 9/8/2022 11:19 AM\\EPSILON\Engineering\Engineering Working Folder\+Proj-Water\21252 - Zone 3 Reservoir Storage\05-Construction Phase\Change Orders\CO 83 Early Site Development\CO3 Description.docx City of Pasco Zone 3 Reservoir Advanced Acquisition Details September 2022 Phase 1: Change Order 3 The tank project includes over 2.6 million pounds of steel, with 1,733,755 pounds of steel in the shell alone, most of which is custom fabricated by the contractor from raw steel. This change order #3 allows for the purchase of the entirety of the steel for the shell of the tank. The purchase is anticipated to include, but is not limited to, material for the fabrication of shell, shafts, center column, roof, floor and floor support reinforcing. Current benchmark price for raw steel is $0.92 per pound. A contingency of 8% for price escalation has been included in the total amount requested for authorization, given the current volatility of the steel market. 9/8/2022 11:19 AM\\EPSILON\Engineering\Engineering Working Folder\+Proj-Water\21252 -Zone 3 Reservoir Storage\05-Construction Phase\Change Orders\CO 83 Early Site Development\CO3 Description.docx City of Pasco Zone 3 Reservoir September 2022 Phase 1: Change Order 3 RESERVOIR COURSES Shell Course grass weight (lb) purchase price S8 23A59.00 21,582.25 S7 43,896.00 40, 384.32 56 58,154.00 53,501.68 S5 79,702.00 73, 325.84 S4 101,238.00 $ 93,138.96 S3 122,774.00 $ 112,952.08 S2 144,311.00 $ 132,766.12 S1 1.29,505.00 $ 113,147.316 subtotal 703,042.001 646,798,64 si atk 69,836.00 $ 64,249.12 - f 69,836.00 $ 64,249.12 .;F, ES 69,836.00 $ 64,249.1.2 SH 5 87,295.00 $ 80,312.32 SH 4 87,296.00 $ 80,31.2.32 SH 3 101,545.00 $ 93,697.40 SH 2 101,845.00 $ 93,697.40 SH 1 101,845.00 $ 93,697.40 sub total 689,635.00 1 $ 634,464.20 Other cw poneiits 71134 -form _43,249.00 $ 136,389.08 = :of 65,181.00 $ 61,270.14 sub total 213,430.00 $ 197,659.22 Floor support reinforcing Flange plates 164,721.00 $ 151,543.32 Gusset Plates 156,825.00 $ 1.44,279.00 Subtotal 321,546.100 $ 295,,822.32 TOTAL $ 1,774,744.38 $ 2,000,000.00 Total Authorization $ 1,926,r000A0 Availablefor Purchase order 74P00.00 Fee (3.7%) $ 151,255.52 Contingency 8% 9/8/2022 11:19 AM\\EPSILON\Engineering\Engineering Working Folder\+Proj-Water\21252 - Zone 3 Reservoir Storage\05-Construction Phase\Change Orders\CO k3 Early Site Development\CO3 Description.doa City of Pasco Zone 3 Reservoir Plan Set September 2022 Phase 1: Change Order 3 Work included in this change order has been outlined using green linework in the attached 60 percent plan set. 9/8/2022 11:19 AM\\EPSILON\Engineering\Engineering Working Folder\+Proj-Water\21252 -Zone 3 Reservoir Storage\05-Construction Phase\Change Orders\CO N3 Early Site Development\CO3 Description.docx n n �� �ymzo O ii foo gniAo c o o A m� T a� m9y °zz,n 'ma Ho p D N N 0 m. o O Esic m, m W m m O m O a _I O z 0 m Oi G Xp z .4% 0 z m 0 w mn X ^ 'm� V / '^ M O♦ _0 X ■ ■ 00^ YI X m Cl)cn C m v m G1 z 00 C F v CD mm � m m C v � N 'n Z N cn g m .4% 0 z m 0 w mn X ^ 'm� V / '^ M O♦ _0 X ■ ■ 00^ YI X m Cl)cn C m v m G1 z 00 C F v CD mm � m m C v � N 'n Z N 2 8 gsmi c Im o� 9�0> �0 111. io m�yg8 Ag a o y o Fl, - -;$ -_ ��maH=� gA €iog$€€ f��o Kms oaA msQy Sia os gf?„ro o s'y m m oso aFc� Num g 'i A" y o9Rmgm9o� m oyyao� g �a g aooA g - H$`_' ` HHTH� 11F Pmy o ^ m a€��mAm� -H H;am z$ fig= smgR. a smog 9= a eg mA _ 1aoA �_ �gss =A =ossgAa -" pm 6 FR os� m z m s A zAo --^Nm_ _� mgr of N g Ng��=�o agoo g m m = o�g o D go ooh a o m s ^ m T m m ^ N N Z O $ H �o x^ =m� m �;� o N�� o$S^�' s Z5 m sm� g9 AmA a^gmmo =f9� ate^ g m z PHI � A o " moo " =em "„ $m :�F o�m`�o gAmmo9ogHo�;m�=a �HAR =g �• _� �� 9gm ==as os o R. m o$;3m=m=.�� 'a^m m�A ��=m^" w KP" as o na g o54 =tom"�= �m imp= _^ Syo most mac m� Rz 1. foiigy$ n`=' m 8. to m mm 2 > � $G o os` -'$o gm�HsmS� mo o= o yAA=� m C7 m A mgg Q m co ��3m �mya fo ego �y moAm y m y�y rD O G) z IM ca Z n oho=�=o m= oma y=T 'UHM O -cni c §6V oZ ZN g HE n � w�m ���� sp �o � � N `� �AmD N f� y om g nc fT ms Z jz Nm � mA gm am m m� z 7a oho y 30 3Fo Og P�m �m o s mm Ate`_ m m A= a9 m m om �� H S gra no m fn zT AA m 0 a 8 m rn x��€ s ss yms mm s m H���g�� sm>a"ooyoo ^>o9N>��As mem mm�om ¢ c y�oNA€� os;�� ��a m Aye r r N ��oA - cnmg$ �g AON ohmo ria oNo tgyaa =ao m 'n _ �° o g$ ��116 n �g�= &ms ^m sm2a �o =m " m$_ s �cA9s=_�s m $mo -m mg I m� =pga� Hmfmoom=�= n m� g z� mss II H a _ g po og ;o=_� m�yw Z gg �' III r ^� m� ;� g$0 7 mRa m $ O _ _ o mks- N€ -n�� �9H-g N 0 9�om�o m sAmo�� m; 9 neo o og msr o pg _ ME y oo9 _ $ 2ma �^ = 9=m �- o H -off AS - { CITY OF PASCO Ira[Spe,xn ner°: LiR-0fFNOOxG REVISIONS P— ZONE 3 RESERVOIR 0)0)PROGRESSIVE DESIGN BUILD GENERAL NOTES AND INFO `��� m '§ ] m m § § 0 r r1 i 0 0 /�|�I� m §m §�)§ ) ! . Q CITY oPAsO y) REVISION$ ■ . ZONE NE3RESERVOIR PRO D 2 wse DESIGN BUILD ABBREVIATIONS » !m :c [> |k 0 m n ¥ 0 0 cn . WA . LM sock w r= ; v N m a ? fU)8 U)_.� ;At _e Al i. ---- i RW 90 °" �° CITY OF PASCO g� RMSIOMS FAW ZONE 9 R PROGRESSWE DESIGN 8 SITE ACCESS PLAN 0 0 }r4 L -j �{ ! � | § I � \ � � |(� ( 2� I ,! /\ §, ,!■; CITY OF PAs o | _,_ ■ ZME,RESERVOIR / [,(REVISIONS PROGRESSIVE DESIGN BUILD ) EXISTING OVERALL ■t PLAN ® ' � �%\ r � ��\ !t4 m M !~2 c q -j �{ ! � | § I � \ � � |(� ( 2� I ,! /\ §, ,!■; CITY OF PAs o | _,_ ■ ZME,RESERVOIR / [,(REVISIONS PROGRESSIVE DESIGN BUILD ) EXISTING OVERALL ■t PLAN ® ' � I y.� s h a 7 Q 0 g CITY OF PASCO .re.m unr ao-rz s.oe,ma.mea«�>Eremv� A L REVISIONS P"40 ZONE 3 RESERVOIR PROGRESSIVE DESIGN BUILD WATER MAIN PLAN AND PROFILE 1 qL M t F i rE ti Io a I m r 1 2 I I m m�o ZoP y.� s h a 7 Q 0 g CITY OF PASCO .re.m unr ao-rz s.oe,ma.mea«�>Eremv� A L REVISIONS P"40 ZONE 3 RESERVOIR PROGRESSIVE DESIGN BUILD WATER MAIN PLAN AND PROFILE 1 =IT o I 8 9 I g � � I I a i m z a 2 mm0 ion £oma I w avoe 0 1 L h a wR^• �.,� CITY OF PASCO `LT wrt Sq B,SR n,uw. L3RAWAlEAPLWG REVISIONS F �L ZONE 3 RESERVOIR IN PROGRESSIVE DESIGN BUILDag�; WATER MAIN PLAN AND PROFILE 2 n ar 4m p n a ;N a 1 I I, I I I b �I I� i I M i I I y�or sod � ao� y I I � I I n a I `s osavou z a 0 a CITY OF PASCO REVISIONS aoN€ 3 RESERVOIR � y PROGRESSIVE DESIGN BUILD�� I - WATER MAIN PLAN AND PROFILE 3 ;N a 1 I I, �I I� I I N I `s osavou z a 0 a CITY OF PASCO REVISIONS aoN€ 3 RESERVOIR � y PROGRESSIVE DESIGN BUILD�� I - WATER MAIN PLAN AND PROFILE 3 0 Z - �, — _ CZ of Pasco y d2 mss, ar iuow.reemw �p lvnm ZONE 3 RESERVOIR A M •., REVISIONS PROGRESSIVE DESIGN 8 ILD ` WATER MAIN PLAN AND PROFILE 4,r r Ik X I SII I I g I IIv I I I II - I m _� . D 4 m Us 'D; r �Im I l' I I 0 Z - �, — _ CZ of Pasco y d2 mss, ar iuow.reemw �p lvnm ZONE 3 RESERVOIR A M •., REVISIONS PROGRESSIVE DESIGN 8 ILD ` WATER MAIN PLAN AND PROFILE 4,r r eo REVISIONS Qm z O 0 0 z; 0 z —1 m U) d z O 0 z ( z CITY OF P— CO ZONE 3 RESERVOIR _ WATER MAIN CONNECTION DETAILS I w p m= dw"YR1F dxdx SBpB3013.,a� .��-��om CITY OF PASCO n gg xeva YILF x drt &pB,AII newer. T1R-0CYNBDMC $a " REVISIONS ZONE RESERVOIR ap' m•.,,• Ad �•..,,gp 'y PROGRESSIVE DESIGN BUILD CONSTRUCTION GRADING PLAN CITY oPAs 2� § REVISIONS ■ , m�awsnaR §,.PROGRESSIVE DESIGN BUILD CONSTRUCTION GRADING Sto S * ~ ® * REVISIONS W Flike ZONE 3 RESERVOIR PROPOSED OVERALL SITE PLAN e G e + f � j , 1 _ 00 M C m a oo r �m { m T �. 5 'NI 6—M 1 � � I i3 r _�•. 1 6 { W 7Jn `- 71 REVISIONS W Flike ZONE 3 RESERVOIR PROPOSED OVERALL SITE PLAN e G e 0 0 N -. m -0 o y mm v rn m93V 9 gt�W�� m$ mo CITY OF PA51G0 n; arras uar• Rmac sye,mu REVISIONS aSIONS mic ONS �-` l4rtn ZONE 3 RESERVOIR m"�., m'•• m PROGRESSIVE DESIGN BUILD PROPOSED SITE AND UTILITY PLAN � - A r m93V 9 gt�W�� m$ mo CITY OF PA51G0 n; arras uar• Rmac sye,mu REVISIONS aSIONS mic ONS �-` l4rtn ZONE 3 RESERVOIR m"�., m'•• m PROGRESSIVE DESIGN BUILD PROPOSED SITE AND UTILITY PLAN CITY OF PASCO REVISIONS ZONE 3 RESERVOIR ®p+ '.. ®d •.,, � m PROGRESSIVE DESIGN BUILD PROPOSED SITE SECTION I all 'P.MH! _I o in av � t���giricill_���1 ��,��� s�� v . Fiwl..�• "' i N � !iW �yomP o y l-11JIfi1��uH1LJ3i`i z y ��� r 1 31iElEi I.-1.::: o i : n f.,_._ C. o oh 9 n �my� m r n€H A� F 7C � '9g m9 _A oy m m �y A ma '=Bye m scsp cE87 ogigo at r_ o �mc mm» � Ap � i5 F; m cm =o _Em 1 / m o� g~� igm � a � o=: 0 9� C WHH UN � m vi3m$ H v T 0 o 0 o �o - m m im m m m Rg H -M � Km og11A F—ccl-mil, ��___ o' omc�i CITY OF PASCO po ., nwva Y0.F nmwa Sp B, 3M3 nera LVtOCN10DWG REVISIONS ZONE 3 RESERVOIR ®P' m•' �° m••a N PROGRESSIVE DESIGN BUILD- ; 'd STANDARD DETAILS 1 I� WP Px Aga A ;gmlog 119 X11 oAzmymm=m. Ao mr �sR=o�m.lmy m gFoNm�m o of o=x a€>82"-, �,m3gSIKm� r T 9i Hun TH 8—H i�8 m - mo -o 1 mqg Fog CC gC�ECaF -o - i3 M ioc m�A i5� ys m� S 8N zs Fm mfr _ m f i i� �'� Pz$mps vg' m N= raNY s�� `� fm m Fabg�_ y� �ys9g Aa z Ell*m fvm z, y;o 0o g $�o 8 8 e mp �xs m ogo oAg o0 0 - yzR� o$`m'g _ mm e �HmoF �io io A g f m m goo 2661 �`7ms6 � o $o amy =y= m� U0 m m m nozN3�.`,�n F��om Fz o�� R,Sogpa =z9a =gym �N Ei---: m�oym��H ms ���mm pgm "$fm rg >o �3z_ $ mem� p m Rv=p p3 oa '-SSng $oy nam o�� 8_ _ogooy. Zx z -moo a og zonmxo��zb N_z8 p _g o4 ymn'=n�?mgf� pg ^vo �m m$?Ao�xcm� r�� 5m _R ioo�s�$oa v a Yiii -� isvmi^9�it momo��o z9 I 1. - �D Foo�,mS2sm mR rg z om ja=i Tp= ny Eg v 0 Es €A91, mg yi oAo $m z z9 =mg omLL i s s 3 0 3 gg Es a^ a� CITY OF PASCO nRa., REVISIONS ZONE 3 RESERVOIR ?ROGRESSIVE DESIGN BUILD 9 'Ilk I1 GENERAL STRUCTURAL NOTES {\ `a afA 3gz�o�„<,3zm p=99 �'�2 pU?NN- $`a g�3a � zb 33.�., C m gn�8a�� =c mpax oo aAo- - C o a �s �� zz o bs;in za 3A i3sa ��a3go o�o�ti yso z�xn,'S'iy P £z_vz z9� mTz ?�T� arj ins v � im nop ^' �� o� Eo �� z � �a �in3 ofNn' 3- o c p z�x o� RoQ o� qi_ $i ip�_ a ons 23�' �� m o z � - omn � p a aA p z nti� �qsg> i;-ti3pOo ��' 33.�., C m gn�8a�� 9 - C ops �s i ci O .caA za mTz ?�T� arj ins v � m �� o� Eo �� z � �a �in3 ofNn' 3- zGiemNg c p z�x o� RoQ o� qi_ $i $�z a ons 23�' m v�nr- � p �qsg> V 90S'JMO / EZ W1HS I"L9 m#8Of SNoismaN N011dINOS3p 3.Ltlp AH I A3Y mal\uo4-13 31il ottmwa ?!=ad Lc,saa =9 ZZ -1-6 j ML I y 100!wd Zuel 95MOIS L!anlasaa E auoZ :103rOUd H.3% X-10.06 cased:N1 vio1S!10 zzoxs �v0 � cal :�e arx0 zeu♦ ova ru :� raMvaO 'PtiTpw9'zIMIRl w �wwwn wnw vo.m..'P.pe wa a r wee.c owww'wwn� ni Www �m Mww n wm�wrn w p e„ u d?'^W TOp Wrygaw+L'�W r+Mtllp Nwa� pIPrOY� aW gluN'a+D BIW uo YWNad �qIW WN PaIaPN X41 - ww',(epeBl'— E69£-£6Z(09£):XVd Aii1/NIN113t1d :el!S4eM Z890•E6Z (090 :Hd IZZ86 VM'�llmeW �+�Na1SS 'PN lu!od 4weW S SZ96 nolvnlaovd ( Asa* d XOnvE L 431dLLi139 ZZOZ! C% SlID19P 6urdrd — Jot Mai UOIIDna13 silolap 6urdrd alow Jo7 -SbUNDJ0 ZH& al Ja1a& J2M01 J2�D� 00SDd sbuim ZH& of Ja1a& 0 0 � ,OS'9l S ^ala s7/09 d£ -l6 0 0 I G uIDJO r9 ZH& Jed siogouy o o AD uD`y }ap y }aa ad 1911n0.PJ �0£ ,6L' X „01 7d = ,JZ -,O ,1 X ,01 7d =,06-0 6rJ17DdS .0 -,Of lD 9-0.4Dld lsa&-Pfl /M (Jos -PDI Puo Pa6po) �IapPD7 JOUNX3 ,0-,06 X /,9f 7ul-Zl- (PD& A ULollog PadollDOS 91Wd U104109 .911' mu/ „9l !DS-PD7 / +a13 7 ,09'995 ql!M J9PPD7 - i I i I A MOlp9AO 71 v I � y Jalawo!0 9Plsul ,0-106 O'Z JgS uo 0'Z Ns uo � el algDl aaS fid algal aaS YDYS -YUDl '67 ,0-,0Z IIaM laM JaluaO I DI YOS Off JOPP07 Joualul uwnlo0 JaluaO- - go7DH ,Z6 ,et 6u111 Jap{!0 JZ/l1 +a13 7 ,09'995 - alDO PUD #DJPUDH swoag wo)log i I A MOlp9AO 71 v 2 � y Jalawo!0 9Plsul ,0-106 0 0'Z Ns uo o if elgDl aaS M dagS 4UDl o lana? 11ML-" ,00£99 +a13 00'699 -A�� al6uy car& -6 go7DH loo& PUD s n/d sJalulDd UUOJ7Dld J008JaluaO loo& DJ UD Ja Ua ' Sl #DJPUDH 100&-1 f P H l O Z }aQ S)aIJD& 91XZ11A X Zd ,0-,07 `igl!M 7d 1-8.91/f S1!D1a0 JOJ 0'S 1115 aaS MA Joo& 0,9f D K ryCrpOpm�m— z 0 m NZA C7 z7 (n (n !n � �{_ D K m➢➢r*i K DDD n � Z .Ti IT70 "' N w� 0 m cyn rn v m n (n (n p c � � p r! i ➢DzDUlmcn W zi 0 ^ 1, CC ppD .. N 3 7J m O � � (n Rl m fel ITI < D � to ;G � � (� fJ � D N� 0 0 0 0 0 ? �F rn U D D0 C CVn_ I� mOr Oo� A O�n�c--'�-o>o��o D H O U W CD � �.. -mmNm�z.. UU CVii VVi � V V W W 4 W �_ 4 N N CD � Wm z m�v-°i m � �m00�� cn�� o V V � D � � CD N U) OZ (n II �U7m 7J f�'I ti7C -o SSS s �D �D7� I TI o Z ri = a a � z � c mmmo J cn O >y (D � n ➢ r c�ii cD!'.�� CD D z � I m co M, , OZ K� o f � m a' N D Z Z O N � U1 S D W HCDCD S O z w Q b °z CD rD�ym 0 o N � y oD� m� Q 3 i m Dm:D m n � -(1 -1 to f1? Dm: O� a o c g ;" m o - F� o�DUG `m ^pc p11a N grq v S � N ori o� 3 z�N 8 y D Y N N =m' uv $3 x F$ 3' g 0 s� :g o �s X x D K ryCrpOpm�m— (n � C7 z7 (n (n !n � �{_ D K m➢➢r*i K DDD n � Z .Ti IT70 "' N w� 0 m cyn rn v m 0 (n (n p c � � p r! i ➢DzDUlmcn W zi ;03 N ^ 1, CC ppD .. D 3 7J m O � � (n Rl m fel ITI < D � to ;G � � (� fJ � D N� 0 0 0 0 0 ? �F rn U D D0 C CVn_ I� mOr Oo� A O�n�c--'�-o>o��o D O N CD � �.. -mmNm�z.. mw.. V V W W 4 W �_ 4 � CD � Wm z m�v-°i m � D K ryCrpOpm�m— (n � C7 z7 (n (n !n � �{_ D K m➢➢r*i K DDD n � Z .Ti IT70 "' N w� 0 m cyn rn v m 0 (n (n p c � � p r! i ➢DzDUlmcn W zi ;03 N ^ 1, CC ppD .. D 3 7J m O � � (n Rl m fel ITI < D � to ;G � � (� fJ � D N� 0 0 0 0 0 ? �F rn U D D0 C CVn_ I� mOr Oo� A O�n�c--'�-o>o��o D O N CD � �.. -mmNm�z.. mw.. V V W W 4 W �_ 4 � CD � Wm z m�v-°i � �m00�� cn�� o S D � � N U) OZ (n II �U7m 7J f�'I ti7C -o SSS -a �D �D7� I TI o Z ri = O m"DLo z � c mmmo J cn O d (D D K ryCrpOpm�m— (n � C7 z7 (n (n !n � �{_ D K m➢➢r*i K DDD n � Z .Ti IT70 "' N w� 0 m cyn rn v m 0 (n (n p c � � p r! i ➢DzDUlmcn W zi ti N LU CC ppD .. D 3 7J m O � � (n Rl m fel ITI < D � to ;G � � (� fJ � D N� 0 0 0 0 0 ? 3 rn U D D0 C CVn_ I� mOr Oo� O�n�c--'�-o>o��o D O N N " � �.. -mmNm�z.. mw.. oo nl D O D D a m p f�Tl ➢➢ C � Wm z m�v-°i � �m00�� cn�� o D � � _ Z U) OZ (n II �U7m 7J f�'I ti7C -o SSS -a �D �D7� I TI o Z ri = O m"DLo z � c mmmo J cn O ui (D D K ryCrpOpm�m— (n � C7 z7 (n (n !n � �{_ D K m➢➢r*i K DDD rI ITI � Z .Ti IT70 Z D r''1 = Z fTt � CJ O 0 m � Z o (n (n p c � � p r! i ➢DzDUlmcn W zi CC ppD .. D r fTl 7J m O � � (n Rl m fel ITI < D � to ;G � � (� fJ � D N� D W z (-) D� c O (n � � p� O mM O C� n D D0 C CVn_ I� mOr Oo� O�n�c--'�-o>o��o D O � � �.. -mmNm�z.. mw.. oo nl D O D D a m p f�Tl ➢➢ Zll � Wm z m�v-°i �m00�� cn�� o D � � _ Z U) OZ (n II �U7m 7J f�'I ti7C -o SSS -a �D �D7� I TI o Z ri = O m"DLo z � c mmmo J cn O � n ➢ r c�ii cD!'.�� D�� D z � I m co M, , OZ o f � m D Z Z O N � U1 S D W $/ i _ ? � ~ $ k \{ \ ( t IS? _} \{ \ §z \ ? ■ ) ƒ \o k m °\ \ \` . � % Q[ $ t] $ R\ \ § e§/= \ ® - » . y ¥ $16 \� \ \ / j 4%± \ - . — — �\/ § �) 2 CD _ 2$ _ Co : !§!!;! oo,l=i ƒ_ _ ��(- | 2; no §2}| 1 % a -- ( - « •. , w ----- \ ~ § \� r -- \ 1 |) \ 2 77 y%§ | -| \ \ ! .ter 9\ j cb Q e lb » \ � «k' } ---/ \ \\ ( ! % � f \ E § } co /\ _ \\ Q \ <, * )\ a _$ /{(, ] /%f - m& 14 { \ � .� . � Min z _ §®| 2i \� \ m2 \\ i ) ! ! ;| Dot/ ; > �� $% ! �| � }" \ swa.xn l:l I Y VI'YAbUV a` 7 JML dhs":e2~�.zwnsmmu �Ik ZONE3RESERVOIR ^' ,I REVISIONS FLOOR AND FOUNDATION PLAN I /\ / WK C) r o m Hn s~ g !•.-� � � � � � � � � " _ - - _ - = - = i��\/\i\i\� //� \\ iii _ _ • : /� ®moi �/\\/0 K��m=`-.=r°'-•°:-: ��>�i/i�i\i/ice/\�/i� � MH CD gs cn ' -- 0 y o e _ 5 � o » � 'Y?;- '� = - _.: •: �<///�/i�r/ ///i /ice / /i //\ / /i - g o x � � �_ Fps .;•,'.__- _-, � s�/r/�\r/�//�//�//�% o m D _ ^• 4 � - - - - - - / //i /i� /\ � � \/\ii /iii/\ _ - CITY OF PASCO o:° g ...ffi rc a2sce.ma A..w�nxasmw •" g$ REVISIONS ff0 ZONE 3 RESERVOIR �+m•,,, �+m•,,,=� PROGRESSIVE DESIGN BUILD FOUNDATION SECTION AND DETAILS S �a � c gTsoy i � I y i �$> WR iz x ism o y g � - F-2 ag SR �9 o;g a ado 8 m S ME 7 w.«=snv '""2. sme.zore °"'.Tei CITY OF PASCO REVISIOONSNS ZONE 3 RESERVOIR ,p+ - — PROGRESSIVE DESIGN BUILD — RESERVOIR MECHANICAL PLAN AND — DETAILS I �m D �D ND N CITY OF PASCO REVISIONS a'!�tiF 3 ��SF.�VOIR -.,.,, t-"�'31ea;;�;1;ILvE� fn��;lf'aN B'IJEEC, t. RESERVOIR INLET & OUTLET SECTION f 1 (Y z Z 8 v o O m m g � � a m m D J1 O Z � x'" o g i m a 26 R/ / CITY OF PASCO wREVISIONS '�"wvl�d� we'mna`�c ZONE 3 RESERVOIR m""• m""• URESSIVE DESIGN BUILD RESERVOIR OVERFLOW AND DRAIN PIPE SECTION rt soma—i, T.— sws.0 1 --- REVISIONS m IT! cn m C O z Ag mo g ZONE 3 RESERVOIR PROGRESSIVE DESIGN BUILD x O :0 0 ,g x z mi Z I � = o m m o', f �- f �! a oil � A 'b 9 rt soma—i, T.— sws.0 1 --- REVISIONS m IT! cn m C O z Ag mo g J ZONE 3 RESERVOIR PROGRESSIVE DESIGN BUILD O :0 0 CATHODIC PROTECTION PLAN AND•+ z mi DETAILS w I m I � I n v D �L a I ro.n :,abo J �I ZONE 3 RESERVOIR PROGRESSIVE DESIGN BUILD CATHODIC PROTECTION PLAN AND•+ a•+° DETAILS w �I