1 Visit Peer Facilities 10 days Mon 11/7/22 Fri 11/18/22
2 Bridge Loan 99 days Thu 9/1/22 Tue 1/17/23
3 Interlocal Agreement 99 days Thu 9/1/22 Tue 1/17/23
4 Sales Tax Begin Sun 1/1/23
5 Finance Services Introduction 1 day Tue 12/13/22Tue 12/13/22
6 OWNERS' REPRESENATIVE 46 days Tue 11/15/22Tue 1/17/23 8,9,10,11,14
7 Concept to Board 1 day Tue 11/15/22Tue 11/15/22
8 Candidate List 8 days Tue 11/15/22Thu 11/24/22 Watkins,PW,Pasco Chamber
9 RFQ and Selection Process Detailed 21 days Tue 11/22/22Tue 12/20/22 Watkins
10 RFQ Board Review and Go-Ahead 1 day Wed 12/21/22Wed 12/21/228 Board
11 RFQ Solicitation 11 days Thu 12/22/22Thu 1/5/23 10 Watkins,Pasco Staff
12 Receive and Confirm Responses 3 days Thu 12/29/22Mon 1/2/23 11 Watkins
13 RFQ Review/Interview/Grading 1 wk Fri 1/6/23 Thu 1/12/23 11 Watkins,Board Committee,Public Works
14 Negotiation 1 wk Fri 1/13/23 Thu 1/19/23 13 Watkins
15 Board Acceptance 1 day Thu 1/12/23 Thu 1/12/23 14 Board
16 Onboarding 6 days Fri 1/13/23 Fri 1/20/23 15 Watkins
17 FINANCIAL ANALYSIS PSA 52 days Mon 11/7/22 Tue 1/17/23
18 Confirm Resource Available 25 days Mon 11/7/22 Fri 12/9/22 Steve Nolen
19 Board Approval 1 day Tue 12/13/22Tue 12/13/2218
20 Contract Prep 3 days Wed 12/14/22Fri 12/16/22 19 Watkins,Attorney
21 PSA Signing 2 days Mon 12/19/22Tue 12/20/2220 Nolen
22 Perform Contract 35 days Wed 12/21/22Tue 2/7/23 21 Nolen,Watkins,Finance
23 Presentation Review 2 days Wed 12/21/22Thu 12/22/2221 Watkins,Nolen
24 Board Presentation 1 day Tue 2/21/23 Tue 2/21/23 Nolen,Board
25 Board Executive Election 1 DAY Tue 1/17/23
26 PFD Presentation to City Council 1 DAY Mon 4/11/22 President,Watkins
27 PUBLIC OUTREACH 2 weeeks Tue 3/1/22
28 SITING 0 days?Tue 2/1/22 Tue 2/1/22
29 STATE COMMERCE REVIEW/APPROVAL 120 days Fri 4/1/22 Thu 9/15/22
30 FINANCING 90 DAYS Thu 9/1/22
31 DESIGN/CONSTRUCTION CONTACT TYPE1 wk Tue 3/1/22 Mon 3/7/22
32 CPARB Review/Approval (if Alternate)16 wks Tue 3/8/22 Mon 6/27/22 31
33 DESIGN 6 mons Sat 7/1/23 Thu 12/14/23
34 CONSTRUCTION 18 mons Mon 1/1/24 Fri 5/16/25
35 STAFFING 90 days Wed 1/1/25 Tue 5/6/25
36 RIBBON CUTTING Sun 6/1/25
Watkins
Board
Watkins,Pasco Staff
Watkins
Watkins,Board Committee,Public Works
Watkins
Board
Steve Nolen
12/13
Watkins,Attorney
Nolen
Watkins,Nolen
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Dec 11, '22 Dec 18, '22 Dec 25, '22 Jan 1, '23 Jan 8, '23 Jan 15, '23
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Aquatics Facility
Date: Wed 12/14/22
Nolen Consulting December, 2022
3907 Iverson Road
Poulsbo, Washington 98370
DRAFT
Pasco Aquatic Center – Sales Tax Generation Analysis
Proposed Scope of Work
Coordinate using phone, email and video conferencing with Pasco Public Facilities District
Executive Director Matt Watkins and needed City of Pasco departments or staff to obtain
the following information for review and analysis:
Documents/Data Source
5-year history of sales tax and other
relevant financial, demographic, data
City of Pasco
Estimates of construction and operational
costs
Ballard-King Study
Construction financing cost estimates City of Pasco
Construction and land development
permitting history and land capacity data
City of Pasco
Initial Bond Capacity information City of Pasco
Supplemental calculations for predicted
operation costs
City of Pasco
RCW 35.57 (Statute providing for .2%
sales tax for Public Facility Districts)
Revised Statutes of Washington
Update information presented in 2021 including:
Analyze potential sales tax that will be generated by 0.2 sales tax beginning January 2023, by
projecting trends within subcategories of sales tax generation, as informed by real estate
market data and state and local economic trends.
The analysis of potential sales tax generation would be compared with estimates of
construction debt service requirements plus annual operations cost estimates, to forecast
sufficiency of dedicated sales tax to fund the portion of debt service and operations that
would not be expected to be recovered by user fees.
Analysis would be expected to include the following three scenarios:
Conservative
Probable
Optimistic
Develop graphics, tables, narrative report and PowerPoint slides.
Present updated material in person or remotely at a PFD meeting as determined.
The estimate of cost for the analysis and report is $6400 (40 hours at $160 per consulting hour)
including the option of presenting in person to include reasonable travel expenses and time.
Additional work beyond this estimate would require prior authorization by the PFD’s Executive
Director.
Nolen Consulting December, 2022
3907 Iverson Road
Poulsbo, Washington 98370
Submitted by
Steve Nolen, Nolen Consulting
Owners’ Representative
Overview of Evaluating Qualification, Interview, Selection Process,
Negotiation, and Contracting
Overview
Invitations sent to potential candidates to submit Statement of
Qualifications (SOQ) demonstrating recent experience successfully
providing Project and Construction Management Services on behalf
of a PFD under traditional and alternative project delivery methods.
Responses received by Executive Director for completeness.
Selection Team
Review applications, grade, shortlist, interview, and select.
PFD Board Member (1 or 2 TBD)
PFD Executive Director (Watkins)
City AC&S (Ratkai)
City Public Works (Worley or designee)
Grading Criteria
Proposed Staff, Qualifications (15%) - Proposed staff, working titles,
degrees, certificates, and license; roles and responsibility of each team
member; individual’s experience and capacity for providing the
services being requested. Key members by name, position, discipline,
and firm, as well as key back up personnel.
Project History Summary & Matrix (30%) - Previous experience,
Project History Matrix, services the proposed firm rendered. 5 recent
municipal alternative delivery contracts/projects the Consultant has
completed in the last 10 years
References (10%)
Understanding of Requested Services (20%)
Description of Approach (20%)
Formatting, Document Clarity (5%)
Interview Process
In-Person or Phone
30-minute presentation
30 minutes for questions and answers.
Candidate Selection
Following the interviews the Selection Team will review interviews,
submissions, score candidate and choose preferred consultant.
PFD Executive Director with City assistance negotiate a specific
scope of services, fees, and schedule with the selected Owners’
Representative.
If an agreement cannot be reached with the first selected Owners’
Representative, the PFD will terminate negotiations t and open
negotiations with the second ranked Owners’ Representative.
Compensation discussed with one Owners’ Representative is
confidential and will not be discussed or disclosed with others.
Once a Owners’ Representative is chosen and terms negotiated, a
recommendation to the PFD Board will be made
Contract Signed