HomeMy WebLinkAbout4285 Resolution - CERB Grant - Contingency Agreement with Darigold RESOLUTION NO.4285
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
AUTHORIZING SUBMISSION OF THE INTERIM CITY MANAGER TO
ENTER INTO AN AGREEMENT FOR A COMMUNITY ECONOMIC
REVITALIZATION BOARD (CERB) LOAN WITH THE WASHINGTON
STATE DEPARTMENT OF COMMERCE FOR THE PROCESS WATER
REUSE FACILITY PRETREATMENT PHASE 3 PROJECT.
WHEREAS,the City currently owns and operates a Process Water Reuse Facility(PWRF)
that operates for the benefit of large agriculture food processors to pretreat, treat, and dispose of
approximately one billion gallons of agricultural industrial wastewater via land application on
1854 acres of City-owned farmland pursuant to Washington State Discharge Permit No.
ST0005369; and
WHEREAS, the PWRF is being improved via multiple projects that will increase the
treatment and storage capacity of industrial wastewater for Pasco; and
WHEREAS, through the process outlined in RCW 70A.140, the City selected Burnham
SEV Pasco, LLC (Burnham) to be the PWRF Pretreatment Phase 3 project developer. The City
and Burnham are currently working on an agreement for the design and construction of the project
that will include wastewater treatment, development of renewable natural gas, and biological
nitrogen removal; and
WHEREAS, to help fund these improvements, Community Economic Revitalization
Board (CERB) funds are available to support economic development projects that are ready to
implement and for which jobs are to be created or retained; and
WHEREAS,the City desires to apply far $5 million in CERB loan funding at an interest
rate of 1.5-2.0% (depending on eligibility) for the PWRF Pretreatment Phase 3 project, of which
said project is consistent with the purposes of the CERB; and
WHEREAS,the specific CERB loan program being pursued requires a Committed Private
Partner, which Darigold has agreed to be for this loan; and
WHEREAS, the loan application requires the attachment of a Contingency Agreement
between the applicant(City), the PWRF project developer(Burnham), and the Committed Private
Partner(Darigold)to ensure that the public and private improvements will be completed contingent
on receiving a CERB loan.
Resolution-Contingency Agreement for CERB Loan Application-Page 1
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PASCO,WASHINGTON:
That the Interim City Manager is hereby authorized to execute the attached Contingency
Agreement for the purposes of including it with the CERB loan application for the PWRF
Pretreatment Phase 3 project, a copy of which is attached hereto and incorporated herein by
reference as Exhibit A.
Be It Further Resolved that the Interim City Manager is hereby further authorized to
provide such additional information as may be necessary to secure approval of such loan
application.
Be It Further Resolved that the Interim City Manager is hereby authorized to make minor,
non-substantive edits to the Contingency Agreement as needed by all parties.
Be It Further Resolved that this Resolution shall take effect immediately.
PASSED by the City Council of the City of Pasco, Washington, this 5`h day of December
2022.
_ —__---,
.,
\
�
Blanche ara�as
Mayor
ATTEST: APPROVED AS TO FORM:
C � �
Debra Bar�am, CMC Kerr Fe son Law, PLLC
City Clerk Cit ttorneys
Resolution-Contingency Agreement far CERB Loan Application-Page 2
FILED FOR RECORD AT REQUEST OF:
City of Pasco,Washington
WHEN RECORDED RETURN TO:
City Clerk
City of Pasco,Washington
525 North 3rd
Pasco WA 99301
PROCESS WATER REUSE FACILITY
CONTINGENCY AGREEEMENT
COMMUNITY ECONOMIC REVITILIZATION BOARD LOAN
THIS AGREEMENT between the City of Pasco, a Washington Municipal Corporation,
hereinafter referred to as "City", Darigold, Inc., hereinafter referred to as "Darigold", and
Burnham SEV Pasco, LLC, hereinafter referred to as "Developer", collectively referred to as
"Parties", enter into this agreement ("Contingency Agreement") for the purpose of making a loan
application to the Community Economic Revitalization Board, hereinafter referred to as "CERB",
related to the proposed improvements to City's Process Water Reuse Facility, hereinafter referred
to as "PWRF", in accordance with the following terms and conditions.
WHEREAS, the City owns, operates, and maintains a Washington State Department of
Ecology ("Ecology")-approved Process Water Reuse Facility (PWRF) along with 14 nearby farm
circles for the treahnent and disposal of over 900 million gallons of industrial wastewater from six
local agricultural food processing plants; and
WHEREAS, Darigold proposes to build a $500 million milk processing plant in Pasco,
scheduled to be operational in early 2024, and plans to send industrial wastewater from the new
plant to the City's PWRF; and
WHEREAS, the City has an opportunity to apply for a low-interest loan in the
approximate amount of $5 million from the CERB and said loan program requires this
Contingency Agreement and a Committed Private Partner; and
WHEREAS, City, Developer, and Darigold agree it is in the interest of the Parties to enter
into this Contingency Agreement for the mutual benefit of the parties.
NOW, THEREFORE, and in consideration of the mutual covenants contained herein, the
Parties agree as follows:
City-Burnham-Darigold PWRF Pretreahnent Project-CERB Contingency Agreement Page 1 of 5
A. Pur�ose•
A. Clarify the intentions of the Parties regarding the completion of the PWRF
Pretreatment Improvement Project and the construction of Darigold's new milk processing
facility.
B. City to prepare and submit a loan application to the CERB to help finance the
proposed Project which will accommodate industrial wastewater from Darigold's new
plant.
C. Darigold identified as a Committed Private Partner related to the CERB loan
application for the proposed PWRF Pretreatment Improvement Project.
B. BackQround•
1. City and Developer are negotiating a final agreement for the design and
construction of the PWRF Pretreatment Improvement Project, which consists of two 35-
million-gallon anaerobic digesters, a biological nitrogen removal system, and a renewable
natural gas ("RNG")plant, (hereinafter referred to as the "Public Facilities Project").
2. Darigold's industrial wastewater, along with increased volumes of existing food
processor's industrial wastewater, will be pretreated through the Public Facilities Project
prior to being disposed of via irrigation to City farm circles.
3. The Public Facilities Project and Darigold's new milk processing plant are currently
scheduled to be completed in early 2024.
C. A�reement•
1. City and Developer agree to construct the Public Facilities Project to support the
pretreatment of industrial wastewater from the new Darigold milk processing plant, subject
to reaching final agreement.
2. Darigold agrees to construct a new milk processing plant, which is currently
estimated to create 200 new permanent, full-time jobs to operate the plant.
3. Darigold's estimated private investrnent for the new milk processing plant in Pasco
is $500 million.
4. Darigold agrees to contact the local Workforce Development Council (WDC) and
the State Employment Security Department for assistance in filling new positions.
5. Darigold agrees to provide City with employment and investment data as requested
by CERB for a period no less than five years following the completion of the Public
Facilities Project.
City-Burnham-Darigold PWRF Pretreatment Project-CERB Contingency Agreement Page 2 of 5
6. Developer expects to invest up to $150 million to construct the Public Facilities
Project.
D. Contin enc : This Contingency Agreement is contingent upon receipt of CERB funds by
City and is intended to provide convincing evidence of private development as required by CERB.
E. Other Terms and Conditions:
1. Dis ute Resolution. In the event of dispute, the parties shall first meet in a good
faith attempt to resolve such dispute, with or without the assistance of inediation.
In the event the dispute remains, it shall be resolved by binding arbitration pursuant to
RCW 7.04A, as amended, and the Mandatory Rules of Arbitration (MAR} with all parties
waiving the right of a jury trial upon de novo review. Venue shall be placed in Franklin
County, Washington; the laws of the State of Washington shall apply; and the substantially
prevailing pariy shall be entitled to its reasonable attorney fees and costs.
2. AssiQnabilitv. This Contingency Agreement, and the rights and responsibilities
hereunder, shall not be assigned, conveyed, sublet, or transferred by Developer or Darigold
without the prior written consent of the City, which consent shall not be unreasonably
withheld.
3. Notice. Any notice or infortnation required or permitted to be given to the parties
under this Contingency Agreement shall be to the following addresses, unless otherwise
specified:
City of Pasco Burnham SEV Pasco, LLC Dari�
City Manager Attn: Chris Tynan Attn: General Counsel
525 North 3rd 1201 Wilson Blvd., 27�Floor 5601 6�'Ave S, Suite#300
Pasco, WA 99301 Arlington, VA 22209 Seattle, WA 98108
Notice shall be deemed given upon receipt of personal delivery, e-mail transmission, or
five (5) days after deposit in the United States Mail in the case of regular mail, or next day
in the case of overnight delivery.
4. Modification. This Contingency Agreement may not be amended, modified, or
terminated except by written agreement signed and approved by all parties.
5. Effective Date. This Contingency Agreement shall become effective upon the date
of signature approval by the last pariy as indicated below.
DATED this day of , 2022.
[Signature pages follows.]
City-Burnham-Darigold PWRF Pretreatment Project-CERB Contingency Agreement Page 3 of 5
CITY OF PASCO,WASHINGTON:
By:
Adam Lincoln
Interim City Manager
STATE OF WASHINGTON )
: ss
COUNTY OF FRANKLIN )
On this day personally appeared before me Adam Lincoln, Interim City Manager of the
City of Pasco, Washington, described in and who executed the within and foregoing instrument,
and acknowledged that he signed the same as his free and voluntary act and deed for the uses and
purposes therein mentioned.
GIVEN under my hand and official seal this_day of , 2022.
Notary Public in and for the State of Washington
Residing at
My Commission Expires:
BURNHAM SEV PASCO,LLC
By:
Chris Tynan
Chief Executive Officer
STATE OF VIRGINIA )
: ss
COUNTY OF ARLINGTON)
On this day personally appeared before me Chris Tynan, Chief Executive Officer of the
Burnham SEV Pasco, LLC, described in and who executed the within and foregoing instrument,
and acknowledged that he signed the same as his free and voluntary act and deed for the uses and
purposes therein mentioned.
GIVEN under my hand and official seal this_day of , 2022.
Notary Public in and for the State of Virginia
Residing at
My Commission Expires:
City-Burnham-Darigold PWRF Pretreatment Project-CERB Contingency Agreement Page 4 of 5
DARIGOLD, INC.:
By:
Joe Coote
Chief Executive Officer
STATE OF WASHINGTON )
: ss
COUNTY OF FRANKLIN )
On this day personally appeared before me Joe Coote, Chief Executive Officer of King
County, Washington, described in and who executed the within and foregoing instrument, and
acknowledged that they signed the same as their free and voluntary act and deed for the uses and
purposes therein mentioned.
GIVEN under my hand and official seal this_day of , 2022.
Notary Public in and for the State of Washington
Residing at
My Commission Expires:
City-Burnham-Darigold PWRF Pretreatment Project-CERB Contingency Agreement Page 5 of 5