HomeMy WebLinkAbout4238 Resolution - Project Acceptance for North 93_Powerline Pathway RESOLUTION NO. 4238
A RESOLUTION OF THE CITY OF PASCO, WASHINGTON,
ACCEPTING WORK PERFORMED BY ELLISON EARTHWORKS, LLC.,
UNDER CONTRACT FOR THE NORTH 93/POWERLINE PATHWAY
PROJECT.
WHEREAS, the work performed by Ellison Earthworks, LLC., under contract for the
North 93/Powerline Pathway project,has been examined by City of Pasco staff and has been found
to be in apparent compliance with the applicable project specifications and drawings; and
WHEREAS, it is the City Staff's recommendation that the City of Pasco formally accepts
the contractor's work and the project as complete.
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PASCO,WASHINGTON:
That the City Council concurs with the Staff s recommendation and thereby accepts the
work performed by Ellison Earthworks, LLC.,under contract for the North 93/Powerline Pathway
project, as being completed in apparent compliance with the project specifications and drawings;
and
Be It Further Resolved, that the City Clerk is hereby directed to notify the Washington
State Department of Revenue of this acceptance; and
Be It Further Resolved, that the final payment of retainage being withheld pursuant to
applicable laws, regulations and administrative determination shall be released upon satisfaction
of same and verification thereof by the Public Works Director and Finance Director.
PASSED by the City Council of the City of Pasco,Washington, this 6th day of September,
2022.
\�
Blanche Barajas
Mayor
ATTEST: APPROVED AS TO FORM:
��-c.����� �
Debra Barham, CMC Kerr ergus , PLLC
City Clerk City At ieys
Resolution—North 93/Powerline Pathway Project Closeout- 1