HomeMy WebLinkAboutClearwater Construction & Management - Murraysmith - WWTP Improvements, Ph 1 - Change Order No. 2 (19-2692) (19072)CHANGE ORDER NO.: 002 Owner: City of Pasco Owner's Project No.: Engineer: Murraysmith Engineer's Project No.: Contractor: Clearwater Construction & Contractor's Project No. Management, LLC Project: City of Pasco 19072 WWTP Improvements Phase 1 Date Issued: 02/24/2022 Effective Date: 02/24/2022 The Contract is modified as follows upon execution of this Change Order: Description: CPR Description 005 HVAC — Heat Pump Addition CHANGE ORDER TOTAL Attachments: CPR 005 CPR 005 — ECOLOGY EMAIL CORRESPONDENCE 19-2692 Conformed Contract Documents Cost $ 22,251.71 $ 22,251.71 19072 19-2692 2142 0 Days 0 Days Change Order 0125 01C -1 Original Contract Price (Not Including Sales Original Contract Times: Tax): $ 16,517,300.00 [Increase] { )eeFease}from previously approved Change Orders No. 0 to No. 001 (Not Including Sales Tax): $ 18,943.84 Contract Price prior to this Change Order (Not Including Sales Tax): $ 16,536,243.84 [increase] [Deffeasel this Change Order (Not Including Sales Tax): $ 22,251.71 Contract Price incorporating this Change Order (Not Including Sales Tax): $ 16,558,495.55 19-2692 Conformed Contract Documents Substantial Completion: August 25, 2023 Ready for final payment: October 9, 2023 [FeeFease] [Deefease} from previously approved Change Orders No.0 to No. 001: Substantial Completion: August 25, 2023 Ready for final payment: October 9, 2023 Contract Times prior to this Change Order: Substantial Completion: August 25, 2023 Ready for final payment: October 9, 2023 {IReFease} {BecFease] this Change Order: Substantial Completion: August 25, 2023 Ready for final payment: October 9, 2023 Contract Times with all approved Change Orders: Substantial Completion: August 25, 2023 Ready for final payment: October 9, 2023 Change Order 012501C-2 By: Title: Date: %fie .c ,,_� Engineer 3/2/2022 By: _ Kiri a paLvu,er _ ----- Title: project_ Manager Date: 3/3/2022 Approved by Ecology Contract Project Manager By: Title: • - Title: Ecology Project Manager Date: 03/02/2022 19-2692 Conformed Contract Documents Accepted by Owner Approved by Ecology Technical Reviewer -Ecology_—ngineer 03/02/2.0- — Change Order 0125 01C - 3