HomeMy WebLinkAboutClearwater Construction & Management - Murraysmith - WWTP Improvements, Ph 1 - Change Order No. 2 (19-2692) (19072)CHANGE ORDER NO.: 002
Owner: City of Pasco Owner's Project No.:
Engineer: Murraysmith Engineer's Project No.:
Contractor: Clearwater Construction & Contractor's Project No.
Management, LLC
Project: City of Pasco 19072 WWTP Improvements Phase 1
Date Issued: 02/24/2022 Effective Date: 02/24/2022
The Contract is modified as follows upon execution of this Change Order:
Description:
CPR Description
005 HVAC — Heat Pump Addition
CHANGE ORDER TOTAL
Attachments:
CPR 005
CPR 005 — ECOLOGY EMAIL CORRESPONDENCE
19-2692
Conformed Contract Documents
Cost
$ 22,251.71
$ 22,251.71
19072
19-2692
2142
0 Days
0 Days
Change Order
0125 01C -1
Original Contract Price (Not Including Sales Original Contract Times:
Tax):
$ 16,517,300.00
[Increase] { )eeFease}from previously
approved Change Orders No. 0 to No. 001
(Not Including Sales Tax):
$ 18,943.84
Contract Price prior to this Change Order
(Not Including Sales Tax):
$ 16,536,243.84
[increase] [Deffeasel this Change Order
(Not Including Sales Tax):
$ 22,251.71
Contract Price incorporating this Change
Order (Not Including Sales Tax):
$ 16,558,495.55
19-2692
Conformed Contract Documents
Substantial Completion: August 25, 2023
Ready for final payment: October 9, 2023
[FeeFease] [Deefease} from previously approved
Change Orders No.0 to No. 001:
Substantial Completion: August 25, 2023
Ready for final payment: October 9, 2023
Contract Times prior to this Change Order:
Substantial Completion: August 25, 2023
Ready for final payment: October 9, 2023
{IReFease} {BecFease] this Change Order:
Substantial Completion:
August 25, 2023
Ready for final payment:
October 9, 2023
Contract Times with all approved Change
Orders:
Substantial Completion:
August 25, 2023
Ready for final payment:
October 9, 2023
Change Order
012501C-2
By:
Title:
Date:
%fie .c ,,_�
Engineer
3/2/2022
By: _ Kiri a paLvu,er _ -----
Title: project_ Manager
Date: 3/3/2022
Approved by Ecology Contract
Project Manager
By:
Title:
• -
Title: Ecology Project Manager
Date: 03/02/2022
19-2692
Conformed Contract Documents
Accepted by Owner
Approved by Ecology Technical Reviewer
-Ecology_—ngineer
03/02/2.0- —
Change Order
0125 01C - 3